Planning application
Land At Quarry Lane Chichester Trade Centre Chichester PO19 8ET
Relates to 26/00521/FUL
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Discharge of conditions 3 (surface water drainage system) and 6 (external lighting) from planning permission CC/26/00521/FUL.
As published by the council, reference 26/01781/DOC
Application record
- Reference
- 26/01781/DOC
- Category
- Conditions
- Status
- Unknown
- Received
- 12 Aug 2026
- Validated
- 12 Aug 2026
- Ward
- Chichester South
- Parish
- Chichester
- Decision by
- Delegated
- Postcode
- PO19 8ET
Site history
Applications at this address on the Chichester register
This site has had 2 applications since 2026: 1 approved, 0 refused.
-
26/00521/FUL Granted
Land At Quarry Lane Chichester Trade Centre Chichester PO19 8ET
Erection of 14 no. Tesla Superchargers, 2 no. substations, along with ancillary infrastructure including ducts, cables and operational equipment.
Timeline
Dates from the published record
-
12 Aug 2026
Received by Chichester
-
21 Aug 2026
Added to PlanIndex
-
2 Oct 2026
Status changed to Unknown
Previously Pending Consideration.
-
Decision
Awaiting decision
Decision expected by 7 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Chichester took a median of 58 days over the applications it decided in the last year.
Related applications
Cases linked to this one on the register
-
26/00521/FUL Granted
Land At Quarry Lane Chichester Trade Centre Chichester PO19 8ET
Erection of 14 no. Tesla Superchargers, 2 no. substations, along with ancillary infrastructure including ducts, cables and operational equipment.
Documents
Plans, drawings, consultee responses and the officer's report
8 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Chichester for determination, against a statutory target of eight weeks. Over the last year Chichester decided condition discharge and variation applications in a median of 54 days. More in our guide to how long planning decisions take.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Land At Quarry Lane Chichester Trade Centre Chichester PO19 8ET
92% historically approved · decision due ~7 Oct
Discharge of conditions 3 (surface water drainage system) and 6 (external lighting) from planning permission CC/26/00521/FUL.
Awaiting decision Conditions 8 docs -
Land At Quarry Lane Chichester Trade Centre Chichester PO19 8ET
Erection of 14 no. Tesla Superchargers, 2 no. substations, along with ancillary infrastructure including ducts, cables and operational equipment.
Granted Full applications 20 docs -
Land At Quarry Lane Chichester Trade Centre Chichester PO19 8ET
78% historically approved · decision due ~7 May
Erection of 14 no. Tesla Superchargers, 2 no. substations, along with ancillary infrastructure including ducts, cables and operational equipment.
Awaiting decision Full applications 13 docs -
Phase 3 Chichester Trade Centre Quarry Lane Chichester West Sussex
Variation of condition 1 of permission 08/04993/FUL to extend the period of temporary use beyond 28th February 2012 by 3 further years for the use as a vehicle washing and valeting centre Monday - Sunday 8am - 6pm.
Granted Full applications 10 docs -
Phase 3 Chichester Trade Centre Quarry Lane Chichester West Sussex
Variation of condition 1 of permission 08/04993/FUL to extend the period of temporary use beyond 28th February 2012 by 3 further years for the use as a vehicle washing and valeting centre Monday - Sunday 8am - 6pm.
Granted Full applications 10 docs -
Unit 10 Chichester Trade Centre Quarry Lane Chichester West Sussex PO19 8ET
78% historically approved · decision due ~16 Nov
Change of use to Class B8 with ancillary retail and additional ancillary use as offices under Class E(g)(i) of the Town and Country Planning (Use Classes) Order 1987 as amended.
Awaiting decision Full applications 9 docs
Other condition discharge and variation applications
In Chichester
-
26/01358/DOC Granted
Phase 8, Chapel Green Blomfield Drive Graylingwell Park Chichester PO19 6BZ
Discharge of Condition 5 (schedule of materials) from reserved matters approval CC/22/02807/REM.
-
26/01273/DOC Granted
Earnley Concourse Clappers Lane Earnley Chichester West Sussex PO20 7JN
Discharge of Condition 4 (Hard and Soft Landscaping Details) of Reserved Matters approval E/24/01775/REM.
-
26/01672/DOC Granted
Land South Of Racton View Marlpit Lane Hambrook Westbourne Emsworth West Sussex PO10 8EQ
Discharge of conditions 5 (contaminated land phase 1 report), 6 (contaminated land phase 2 report), 7 (contaminated land remediation), 9 (package treatment plant maintenance and management), 12 (boundary treatments), 13 (hard and soft landscaping works) and 17 (external illumination) from planning permission WE/24/00806/FUL.
-
26/01827/DOC Refused
Baker Barracks Emsworth Road Thorney Island Emsworth West Sussex PO10 8DH
This discharge of condition 8 (surface water drainage) from planning application 26/00503/FUL
-
26/02106/DOC Granted
The Coach House Pigbush Lane Loxwood Billingshurst West Sussex RH14 0QY
Discharge of Condition 3 (material schedule) from Planning Permission LX/26/00387/DOM.