Euston Approaches Worksite
Relates to 2019/4700/HS2
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Temporary lorry route to the Euston Approaches HS2 worksite, via Stanhope Street, Mackworth Street, Harrington Street and Varndell Street, connecting to A400 and the Transport for London Network (TLRN) in association with main HS2 works activities, which will amend existing approved lorry route (ref:2019/4700/HS2) whilst temporary utility works are undertaken.
As published by the council, reference 2023/3399/HS2
Application record
- Reference
- 2023/3399/HS2
- Type
- Schedule 17 - Conditions of Deemed Planning Permission
- Status
- Final Decision
- Decision
- Approval
- Received
- 18 Aug 2023
- Validated
- 22 Aug 2023
- Decided
- 11 Dec 2023
- Ward
- Regents Park
- Decision by
- Delegated
Timeline
Dates from the published record
-
18 Aug 2023
Received by Camden
-
22 Aug 2023
Validated
Checked as complete and ready for consideration.
-
11 Dec 2023
Decision issued: Approval
-
22 Jul 2026
Added to PlanIndex
Related applications
Cases linked to this one on the register
-
2019/4700/HS2 At appeal
Euston Approaches Worksite and Adelaide Road Worksite
Lorry routes to and from the Euston Approaches and Adelaide Road worksites associated with works for HS2. Main works activities include: Construction of the Park Village East retaining wall, portal and high-speed dive unders including the installation of ground anchors; Removal of excavated material from the station approach, tunnel portal and headhouse works; Construction of the decks over the high-speed dive under and railway south of Mornington Street Bridge; Construction of the west and east side retaining wall around Hampstead Road Bridge; Extension of Hampstead Road Bridge as well as associated utilities and highway works; Support the movement of plant and material down into the Euston approach railway cutting; Support the removal of excavated material generated in the railway cutting; Construction of Adelaide Road vent shaft and single storey headhouse building; and all other activities for the purposes and in connection with the scheduled and ancillary works. Incorporating lorry routes detailed in 'List of Roads for Approval' document.
Documents
Plans, drawings, consultee responses and the officer's report
9 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
Camden granted permission on 11 December 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
Netley Primary School 30 William Road London NW1 3EN
Details pursuant to conditions 25 (Open Space Management Plan), 27 (Service Management Plan), 28 (Travel Plan (residential element only)), 37 (Sustainability Plan), 38 (Energy Statement) and shadow S106. clauses 4.10 (Water Management Plan) and 4.17 (Energy Efficiency and Renewable Energy Plan) of planning permission dated 16/10/12 (Ref: 2012/2089/P) for erection of a 5 storey building plus basement to accommodate a Foundation Unit, Primary Pupil Referral Unit and Community Learning Centre and 36 residential units (Class C3) fronting Stanhope Street; erection of a 8 storey building plus lower ground floor to accommodate 34 residential units (Class C3) at the junction of Stanhope Street and William Road (following demolition of existing post-war primary school building); remodelling to the Victorian Board School to accommodate a lift core to provide access to the new play space at roof level. Demolition of Woodhall Garages and erection of a 2 storey block to provide 10 x social rented family houses (Class C3) and associated public realm improvements to Everton Buildings, landscaping and access works.
Granted Full applications Demolition -
Netley Primary School 30 William Road London NW1 3EN
Erection of gas meter and enclosure adjacent to the northern elevation of building (retrospective). Erection of a brick screen wall surrounding the gas meter.
Granted Full applications -
Netley Primary School 30 William Road London NW1 3EN
Details of acoustics report as required by condition 18 of planning permission dated 16/10/12 (Ref: 2012/2089/P) for erection of a 5 storey building plus basement to accommodate a Foundation Unit, Primary Pupil Referral Unit and Community Learning Centre and 36 residential units (Class C3) fronting Stanhope Street; erection of a 8 storey building plus lower ground floor to accommodate 34 residential units (Class C3) at the junction of Stanhope Street and William Road (following demolition of existing post-war primary school building); remodelling to the Victorian Board School to accommodate a lift core to provide access to the new play space at roof level. Demolition of Woodhall Garages and erection of a 2 storey block to provide 10 x social rented family houses (Class C3) and associated public realm improvements to Everton Buildings, landscaping and access works.
Granted Full applications Demolition -
30 Netley Primary School William Road London NW1 3EN
Display of two non-illuminated banners to the entrance of Netley School on William Road
Granted -
Netley Primary School 30 William Road London NW1 3EN
Details required by condition 4a ( sample panel of brick work), 4b (sample panel of all facing/cladding materials) of 4c (details of railings and boundary treatment), 4d (details of windows), 9 (hard and soft landscape), 13 (green roof), 14 (details of bird and bat box), 20i (prior investigation and laboratory result), 22a (green roof for block A, B and housing unit E), 22b (off-site run-off and flooding affection), 22c (discharge of surface water) and 22d (details of drainage scheme) to planning permission dated 16/10/12 (Ref: 2012/2089/P) for erection of a 5 storey building plus basement to accommodate a Foundation Unit, Primary Pupil Referral Unit and Community Learning Centre and 36 residential units, erection of a 8 storey building plus lower ground floor to accommodate 34 residential units, remodelling to the Victorian Board School, demolition of Woodhall Garages and erection of a 2 storey block to provide 10 x social rented family houses.
Granted Full applications Demolition Windows or glazing -
Netley Primary School 30 William Road London NW1 3EN
Installation of 2 x entrance signs to residential block A, and 1 x entrance sign to residential block B (class C3).
Withdrawn
Other condition discharge and variation applications
In Camden
-
2025/5635/HS2 Granted
Park Village East NW1 2DU
Reinstatement of parts of the Park Village East Parapet wall and Planter wall, between Granby Terrace Bridge in the south, and the location for the Euston Cavern Shaft Headhouse and Compound in the north.
-
2025/5474/HS2 Granted
Centre for the Magic Arts 12 Stephenson Way London NW1 2HD
Erection of an end wall to the eastern facade; minor alteration to the north facade with partial render and roof cornice.
-
2025/5472/HS2 Granted
Royal College of General Practitioners 30 Euston Square London NW1 2FB
Erection of two end walls to the north facing gable end facades.
-
2024/1945/HS2 Granted
Park Village East NW1 2DU
Non-material amendment to Schedule 17 - Conditions of Deemed Planning Permission Approval 2023/4585/HS2 dated 19/12/2023 (which itself amended 2021/0126/HS2, dated 17/03/2021) for; installation of Wall Berm and Upstand Support Strucure to structurally support the existing Park Village East retaining wall. The berm will be located in the railway cutting, adjacent to the existing Park Village East retaining wall and extending from Euston Scissor Box (open section) to Parkway Tunnel; and the installation of Euston Scissor Box (open section) - structurally supporting the portal between the Euston Tunnels and Scissor Cut, located within the railway cutting bound by Mornington Street and Granby terrace Bridge and forming part of the portal for the new HS2 tunnels.
-
2024/1734/HS2 Granted
Land to the North of Exmouth Arms, fronting Coburg Street 1 Starcross Street London NW1 2HR
Construction of a UKPN Substation building comprising two permanent transformers and a Transition Field Upgrade (TFU) unit, with a masonry facade finish fronting Coburg Street.