Planning application
25/0643/COND
Y Fron Mountain View Pwllypant Caerphilly CF83 3HW
Proposal
Discharge conditions 03 (Materials - samples/details req) and condition 05 (Retaining Walls) of planning consent 25/0382/NCC (Vary conditions 02 (Plans) and 03 (Approval of the Proposed Amendments of Some of External Materials) of planning consent 20/0634/COU (Change use and erect extension at Y Fron from Guest House (C1) to HMO to be used for Emergency Housing/Move on Accommodation (Sui Generis) and associated works) to amend plans)
As published by the council, reference 25/0643/COND
Timeline
Dates from the published record
-
19 Sep 2025
Received by Caerphilly
-
28 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with Caerphilly for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About conditions applications
How this application type works
This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.
Nearby applications
Within 500 metres
-
26/0042/TPO Refused
1 Bryn Derwen Penyrheol Caerphilly CF83 2UZ
Remove the diseased limb of Oak tree T1 protected by (TPO 8/99/CCBC) back to the main trunk
-
25/0810/FULL Granted
Syballwyn 42 Heol Pwllypant Energlyn Caerphilly CF83 2ND
Enlarge and regrade front driveway and associated works
-
26/0217/COU Granted
29-30 Sir Alfred Owen Way Pontygwindy Industrial Estate Caerphilly CF83 3HU
Change the use to B1/B2/B8 (Industrial) units
Other conditions applications
In Caerphilly
-
26/0493/COND Awaiting decision
Tredegar Junction Hotel Commercial Street Pontllanfraith Blackwood NP12 2JY
Discharge condition 04 (Soft Landscaping Scheme) of planning consent 25/0814/FULL (Erect residential development consisting of 36 affordable apartments, landscaping, car parking, drainage and associated works)
-
26/0113/COND Decided
Gwent Tertiary College - Coleg Gwent Cross Keys Campus Risca Road Crosskeys Newport NP11 7ZA
Discharge condition 08 (Contamination - soil import testing) of planning consent 25/0088/OUT (Hybrid application for the redevelopment of Coleg Gwent, Crosskeys Campus comprising: Full planning application for Phase 1 including the construction of a three-storey teaching building and a single-storey energy centre, together with associated access, parking, and landscaping works, Outline planning application for Phases 2-4, comprising the phased demolition of existing buildings and their replacement with new buildings, along with associated access, parking and landscaping across the campus site)
-
26/0372/COND Granted
23 Quantock Close Trenewydd Park Risca Newport NP11 6QW
Discharge conditions 04 (GIS) and 05 (Structural calcs) of planning consent 26/0158/HH (Create hardstanding) in order to commense work
-
26/0474/COND Awaiting decision
Trinant Sports And Social Club CIO Conway Road Trinant Newport NP11 3JP
Discharge conditions 8 (Contamination - scheme to treat), 13 (Habitat Management Plan), 14 (Biodiversity Drainage Scheme), 16 (Biodiversity Strategy) and 18 (Japanese Knotweed) of planning consent 22/0718/OUT (Erect residential development along with associated infrastructure in order to facilitate improvement of the club)
-
26/0156/COND Decided
Cilfynydd Substation Craig-evan-leyshon Common Road Llanfabon
Discharge condition 11 (Noise Complaints) of planning consent 25/0243/FULL (Install and operate electrical infrastructure and associated infrastructure, including a grid connection)