Planning application
Land To West Of Aylesbury Extending From The Princes Risborough To Aylesbury Railway Line To Public Right Of Way SBH/34/1, Buckinghamshire.
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
In accordance with requirements of Paragraph 9(4)(b) of Schedule 17 to the High-Speed Rail (London - West Midlands) Act 2017, the nominated undertaker hereby requests approval of a SCHEME OF MITIGATION for Work No. 2/28(in part), 2/43 and 2/47 described in Schedule 1 of the HS2 (London - West Midlands) Act 2017.
As published by the council, reference PL/26/08386/HS2
Application record
- Reference
- PL/26/08386/HS2
- Status
- Registered
- Validated
- 15 Oct 2026
Site history
Applications at this address on the Buckinghamshire register
This site has had 3 applications since 2026.
-
PL/26/08381/HS2 Awaiting decision
Land To West Of Aylesbury Extending From The Princes Risborough To Aylesbury Railway Line To Public Right Of Way SBH/34/1, Buckinghamshire.
In accordance with requirements of Paragraph 9(1) of Schedule 17 to the High Speed Rail (London - West Midlands) Act 2017, the nominated undertaker hereby requests approval for Work Nos. 2/43 and 2/47 described in Schedule 1 of the HS2 (London - West Midlands) Act 2017 to BE BROUGHT INTO USE.
-
PL/26/08389/HS2 Awaiting decision
Land To West Of Aylesbury Extending From The Princes Risborough To Aylesbury Railway Line To Public Right Of Way SBH/34/1, Buckinghamshire.
Plans and specifications submission under Schedule 17 of the High Speed Rail (London - West Midlands) Act 2017 for works comprising: - Footpath SMA/16 Accommodation Overbridge and associated earthworks - SBH/19 Bridleway Oat Close Overbridge and associated earthworks - Footpath SBH/34 Accommodation Overbridge and associated earthworks - Aylesbury South Cutting (Part of) - Aylesbury Embankment - Aylesbury North Cutting (Part of) - Earthworks associated with Footpath SMA/16 realignment - Earthworks associated with Access Track 1 - HS2 maintenance access to Drainage Ponds 6 and 7 - Earthworks associated with SBH/19 Oat Close Bridleway - Stoke Brook Watercourse Enhancements Diversion - Sedrup North Watercourse Diversion -Earthworks associated with the 8 No. Ecology Ponds - Earthworks associated with the 7 No. Drainage Ponds - Drainage Ditches - 6 No. Culverts (above ground elements) - Noise Barriers - 7 No. Ditch Crossings ('Slab Crossings') - Location of the Vehicle Restraint Barriers - Location of the permanent (security and boundary) fencing
Timeline
Dates from the published record
-
15 Oct 2026
Validated
Checked as complete and ready for consideration.
-
21 Oct 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 10 December 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Buckinghamshire took a median of 60 days over the applications it decided in the last year.
What happens while it is decided
This application is with Buckinghamshire for determination, against a statutory target of eight weeks. Over the last year Buckinghamshire's median decision took 60 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Buckinghamshire's portal will say. Our guide explains the common types.