Planning application
2026/1570
Plot 5 4 Mackintosh Way Brooke Norfolk NR15 1DQ
Proposal
Erection of a custom build two storey dwelling, garages, and associated works (plot 5) [in lieu of approved Plot 5 bungalow approved by 2023/3020, as amended by 2024/3152 ]
As published by the council, reference 2026/1570
Timeline
Dates from the published record
-
2 Jun 2026
Received by Broadland
-
26 Jun 2026
Validated
Checked as complete and ready for consideration.
-
20 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with Broadland for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
2026/1570 Awaiting decision
Plot 5 4 Mackintosh Way Brooke Norfolk NR15 1DQ
Erection of a custom build two storey dwelling, garages, and associated works (plot 5) [in lieu of approved Plot 5 bungalow approved by 2023/3020, as amended by 2024/3152 ]
-
2026/0893 Awaiting decision
Former Site Of 49 High Green Brooke Norfolk
Details for Conditions 3 - External Materials (phase 2), 5 - Soil evaluation (Phase 2) from (2023/3020), 6 - Tree Protection (Phase 2), 7 - Landscaping Scheme (Phase 2), 11 - Ecological Enhancement (phase 2), 12 - Construction Parking (Phase 2), 13 - Wheel cleaning (Phase 2) of permission 2024/3152
-
2026/0893 Awaiting decision
Former Site Of 49 High Green Brooke Norfolk
Details for Conditions 3 - External Materials (phase 2), 5 - Soil evaluation (Phase 2) from (2023/3020), 6 - Tree Protection (Phase 2), 7 - Landscaping Scheme (Phase 2), 11 - Ecological Enhancement (phase 2), 12 - Construction Parking (Phase 2), 13 - Wheel cleaning (Phase 2) of permission 2024/3152
-
2021/2391 Refused
Annexe At 62 High Green Brooke NR15 1JD
Removal of Condition 5 of permission 2016/2188 - to allow separation into two individual semi-detached dwellings
-
2021/2391 Refused
Annexe At 62 High Green Brooke NR15 1JD
Removal of Condition 5 of permission 2016/2188 - to allow separation into two individual semi-detached dwellings
-
2025/4014 Granted
60 High Green Brooke Norfolk NR15 1JD
Felling of multi-stemmed 15m high Beech tree
Other full applications applications
In Broadland
-
2026/0754 Granted
Land Adj The Grove Booton Norfolk
Installation of post construction field drainage to support the operation of the Hornsea Project Three onshore export cable route (EIA Development).
-
2025/2830 Granted
Land South Of Dairy Farm Burgh Road Wheatacre Norfolk
Erection of new self build 3-bedroom detached single storey dwelling/farmhouse
-
2026/0612 Granted
Land South East Of Easton Road Marlingford Norfolk
Retention of vehicular crossover Access Point 32 created by Orsted Power (UK) Ltd for the 'Hornsea Project Three Offshore Wind Farm' Project
-
2026/0861 Granted
The School House The Street Framingham Earl Norfolk NR14 7QY
Change of use from a fostering agency (sui generis) to children's day nursery (class E(f)) and associated external alterations
-
2026/2106 Awaiting decision
The Old Vineyard Overwood Lane Forncett St Peter Norfolk
Construction of 1no. rural worker and self build dwelling.