Skip to content
PlanIndex Get alerts
Menu

Planning application

Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth

Granted Bristol, City of 21/P/1572/DCM Development Consent Order - Major

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Formal submission to discharge Requirement 5(4) (Construction Environmental Management Plan) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

As published by the council, reference 21/P/1572/DCM

Application record

Reference
21/P/1572/DCM
Type
Development Consent Order - Major
Status
Decided
Decision
Granted As published: Approve
Received
26 May 2021
Validated
26 May 2021
Decided
1 Sep 2021
Parish
Unparished
Decision by
Delegated Decision

Site history

Applications at this address on the Bristol, City of register

This site has had 26 applications since 2019: 26 approved, 0 refused.

  • 26/P/1284/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal submission to extend the time for discharge of Requirements 15 (Reinstatement schemes) and 20 (Removal of temporary bridges and culverts) for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 20 Aug 2026 Full applications
  • 26/P/0912/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal submission to extend the time to discharge Requirements 15 (Reinstatement schemes) and 20 (Removal of temporary bridges and culverts) for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 18 Jun 2026 Full applications
  • 25/P/2633/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth

    Formal submission to discharge Requirement 15 (Reinstatement schemes) for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 29 Apr 2026 Full applications
  • 25/P/1772/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth

    Formal submission to discharge Requirement 15 (Reinstatement schemes) for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 21 Oct 2025 Full applications
  • 25/P/1750/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth

    Formal submission to discharge Requirement 22 (Highway Works (Bellmouth Design)) for Stage 7.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 17 Oct 2025 Full applications
  • 25/P/1749/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal submission to discharge Requirement 5(2)(d) (Construction Traffic Management Plan Addendum) for Stage 7.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 21 Oct 2025 Full applications
  • 23/P/0407/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal Submission to discharge of Requirement 6(1)(f) (Emergency Response Plan for Flood Events for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as amended)

    Decided 18 Apr 2023 Full applications
  • 23/P/0240/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal submission to discharge Requirement 5(2)(b) (Biodiversity Mitigation Strategy for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 25 Apr 2023 Full applications
  • 22/P/2976/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal submission to discharge Requirement 10 (Scheme of Replacement Planting for Stage 8 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 6 Feb 2023 Full applications
  • 22/P/2194/DCO Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth

    Formal Submission to discharge of Requirement 20 (Removal of temporary bridges and culverts for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016

    Decided 15 Mar 2023

Timeline

Dates from the published record

  1. 26 May 2021

    Received by Bristol, City of

  2. 1 Sep 2021

    Decision issued: Approve

  3. 28 Aug 2026

    Added to PlanIndex

Who's behind it

Company information only, from the register and Companies House

Arup Agent, registered in London

Active · incorporated 1990 · London

255 applications on PlanIndex · across 56 councils · 99% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

National Grid PLC Applicant, registered in London

Active · incorporated 2000 · London

94 applications on PlanIndex · across 30 councils · 100% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

25 documents on file for this application

  • DELEGATED REPORT DCO/DMO Delegated Report · 02 Sep 2021
  • DECISION (DCM) APPROVE Decision Notice · 02 Sep 2021
  • DELEGATED REPORT DCO/DMO Delegated Report · 31 Aug 2021
  • HPCC - SW 5D D - REQ 5 4 - COVER LETTER 03 08 2021 Report · 03 Aug 2021
  • HPCC - SW 5D D - CONSTRUCTION TRAFFIC MANAGEMENT PLAN ADDENDUM 03 08 2021 Report · 03 Aug 2021
  • HPCC - SW 5D D - APPENDIX B 03 08 2021 Report · 03 Aug 2021
  • HCP ? SW 5D D ? APPENDIX SHEET 8 - 03 08 2021 Report · 03 Aug 2021
  • HCP ? SW 5D D ? APPENDIX SHEET 3 - 03 08 2021 Report · 03 Aug 2021
  • HPCC - SW 5D D - APPENDIX C 03 08 2021 Report · 03 Aug 2021
  • HPCC - SW 5D C - CONSTRUCTION TRAFFIC MANAGEMENT PLAN ADDENDUM 14 07 2021 Report · 16 Jul 2021
  • HCP ? SW 5D C ? APPENDIX SHEET 1 - 14 07 2021 Report · 15 Jul 2021
  • HCP ? SW 5D C ? APPENDIX SHEET 2 - 14 07 2021 Report · 15 Jul 2021
  • HCP ? SW 5D C ? APPENDIX SHEET 3 - 14 07 2021 Report · 15 Jul 2021
  • HCP ? SW 5D C ? APPENDIX SHEET 4 - 14 07 2021 Report · 15 Jul 2021
  • HCP ? SW 5D C ? APPENDIX SHEET 5 - 14 07 2021 Report · 15 Jul 2021
  • HCP ? SW 5D C ? APPENDIX SHEET 6 - 14 07 2021 Report · 15 Jul 2021
  • HCP ? SW 5D C ? APPENDIX SHEET 10 - 14 07 2021 Report · 15 Jul 2021
  • HCP ? SW 5D C ? APPENDIX SHEET 11 - 14 07 2021 Report · 15 Jul 2021
  • HCP ? SW 5D C ? APPENDIX SHEET 7 - 14 07 2021 Report · 15 Jul 2021
  • HCP ? SW 5D C ? APPENDIX SHEET 8 - 14 07 2021 Report · 15 Jul 2021
  • HCP ? SW 5D C ? APPENDIX SHEET 9 - 14 07 2021 Report · 15 Jul 2021
  • HPCC - SW 5D C - APPENDIX B 14 07 2021 Report · 15 Jul 2021
  • HCP ? SW 5D C ? APPENDIX SHEET 13 - 14 07 2021 Report · 15 Jul 2021
  • HCP ? SW 5D C ? APPENDIX SHEET 12 - 14 07 2021 Report · 15 Jul 2021
  • APPLICATIONFORMREDACTED Application Form · 26 May 2021

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Bristol, City of granted permission on 1 September 2021, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

In Bristol, City of

  • 26/P/1091/FUL Granted

    12 Beach Road Kewstoke Weston-super-Mare BS22 9UZ

    Creation of a new highway access and provision for parking area/bin store together with the proposed erection of a boundary enclosure wall.

    Received 26 May, published by the council 21 Jul 2026 Full applications
  • 25/P/2513/FUL Granted

    12 Clevedon Road Tickenham Clevedon BS21 6QT

    Demolition of existing dwelling and agricultural buildings, and the erection of 3no. dwelling houses, including 3no. detached double garages, and creation of new vehicular access on to Clevedon Road

    Received 3 Dec, published by the council 21 Jul 2026 Full applications
  • 26/P/0576/FUL Granted

    The Grain Barn, Midgell Farm Chelvey Road Chelvey BS48 4AA

    The change of use of land to residential garden and the erection of an outbuilding, planter, fence, and hardstandings (Retrospective).

    Received 16 Mar, published by the council 21 Jul 2026 Full applications
  • 26/P/1227/FUL Granted

    66A Clifton Road Weston-super-Mare BS23 1BW

    Proposed change of use and alteration to a self-contained coach house to form a single two-bedroom dwelling (Class C3).

    Received 11 Jun, published by the council 21 Jul 2026 Full applications
  • 26/P/0222/FUL Granted

    Scouts Barn Oxhouse Lane Failand BS8 3SL

    Change of use of land to garden land (C3 use Class), erection of a timber lodge for use as annexed accommodation, erection of a hay storage barn, retention of garden patio (retrospective); Removal of a garden gazebo and part of gravel parking area to front of dwelling. Erection of additional metal railings and new fencing around garden area.

    Received 2 Feb, published by the council 21 Jul 2026 Full applications