Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth

Granted Bristol, City of 21/P/1472/DCM Development Consent Order - Major

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Formal submission to discharge Requirement 6(1)(b), 17, 19 and 21 (Drainage Management Plan for Stage 8 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

As published by the council, reference 21/P/1472/DCM

Application record

Reference
21/P/1472/DCM
Type
Development Consent Order - Major
Status
Decided
Decision
Approve
Received
17 May 2021
Validated
17 May 2021
Decided
5 Jul 2021
Parish
Unparished
Decision by
Delegated Decision

Site history

Applications at this address on the Bristol, City of register

This site has had 26 applications since 2019: 26 approved, 0 refused.

  • 26/P/1284/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal submission to extend the time for discharge of Requirements 15 (Reinstatement schemes) and 20 (Removal of temporary bridges and culverts) for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 20 Aug 2026 Full applications
  • 26/P/0912/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal submission to extend the time to discharge Requirements 15 (Reinstatement schemes) and 20 (Removal of temporary bridges and culverts) for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 18 Jun 2026 Full applications
  • 25/P/2633/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth

    Formal submission to discharge Requirement 15 (Reinstatement schemes) for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 29 Apr 2026 Full applications
  • 25/P/1772/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth

    Formal submission to discharge Requirement 15 (Reinstatement schemes) for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 21 Oct 2025 Full applications
  • 25/P/1750/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth

    Formal submission to discharge Requirement 22 (Highway Works (Bellmouth Design)) for Stage 7.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 17 Oct 2025 Full applications
  • 25/P/1749/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal submission to discharge Requirement 5(2)(d) (Construction Traffic Management Plan Addendum) for Stage 7.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 21 Oct 2025 Full applications
  • 23/P/0407/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal Submission to discharge of Requirement 6(1)(f) (Emergency Response Plan for Flood Events for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as amended)

    Decided 18 Apr 2023 Full applications
  • 23/P/0240/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal submission to discharge Requirement 5(2)(b) (Biodiversity Mitigation Strategy for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 25 Apr 2023 Full applications
  • 22/P/2976/DCM Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal submission to discharge Requirement 10 (Scheme of Replacement Planting for Stage 8 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).

    Decided 6 Feb 2023 Full applications
  • 22/P/2194/DCO Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth

    Formal Submission to discharge of Requirement 20 (Removal of temporary bridges and culverts for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016

    Decided 15 Mar 2023

Timeline

Dates from the published record

  1. 17 May 2021

    Received by Bristol, City of

  2. 5 Jul 2021

    Decision issued: Approve

  3. 19 Aug 2026

    Added to PlanIndex

Who's behind it

Company information only, from the register and Companies House

PATZ Town Planning & Environmental Ltd Agent, a planning consultancy registered in London

Dissolved · incorporated 2020 · London

15 applications on PlanIndex · across 4 councils · 100% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

18 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Bristol, City of granted permission on 5 July 2021, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

In Bristol, City of

  • 26/P/0379/FUL Awaiting decision

    45 Clevedon Road Tickenham Clevedon BS21 6RB

    Proposed erection of a self-build dwelling following demolition of the existing dwelling and garage. Erection of detached garage and ground mounted solar panels.

    20 Feb 2026 Full applications
  • 26/P/1305/FUL Granted

    7 Brampton Way Portishead BS20 6UZ

    Proposed change of use of existing amenity land to residential garden and erection of a single-storey wraparound side/rear extension with attached double garage.

    22 Jun 2026 Full applications
  • 26/P/1001/FUL Granted

    The Nightjar Nightingale Close Weston-super-Mare BS22 8SX

    Change of use and extension of the former Public House to provide 3no. commercial units (Use Class E and sui generis hot food takeaway) at ground floor level and the creation of 2no. residential units (Use Class C3) at first floor level. Creation of new access from Redwing Drive, parking, landscaping and associated works

    13 May 2026 Full applications
  • 26/P/0871/FUL Granted

    8 Upper Church Road Weston-super-Mare BS23 2DT

    Proposed change of use of existing Class E property to form 1no. self-contained flat including alterations to fenestration.

    24 Apr 2026 Full applications
  • 26/P/1527/FUL Granted

    Waterloo Hall 17 Waterloo Street Weston-super-Mare BS23 1LF

    Proposed alterations to existing entrance to provide level access