Planning application
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Formal Submission to discharge of Requirement 6(1)(b) (Drainage Management Plan for Stage 2.1 of the authorised development) and 17 (Surface Water Drainage for Stage 2.1 of the authorised development) and 19 (Inspection of Temporary Watercourses for Stage 2.1 of the authorised development) and 21 (Accumulation and Deposits for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended)
As published by the council, reference 19/P/2898/DCM
Application record
- Reference
- 19/P/2898/DCM
- Type
- Development Consent Order - Major
- Status
- Decided
- Decision
- Granted As published: Approve
- Received
- 20 Nov 2019
- Validated
- 20 Nov 2019
- Decided
- 20 Dec 2019
- Parish
- Unparished
- Decision by
- Delegated Decision
Site history
Applications at this address on the Bristol, City of register
This site has had 27 applications since 2019: 27 approved, 0 refused.
-
26/P/1284/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal submission to extend the time for discharge of Requirements 15 (Reinstatement schemes) and 20 (Removal of temporary bridges and culverts) for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
26/P/0912/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal submission to extend the time to discharge Requirements 15 (Reinstatement schemes) and 20 (Removal of temporary bridges and culverts) for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
25/P/2633/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth
Formal submission to discharge Requirement 15 (Reinstatement schemes) for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
25/P/1772/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth
Formal submission to discharge Requirement 15 (Reinstatement schemes) for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
25/P/1750/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth
Formal submission to discharge Requirement 22 (Highway Works (Bellmouth Design)) for Stage 7.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
25/P/1749/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal submission to discharge Requirement 5(2)(d) (Construction Traffic Management Plan Addendum) for Stage 7.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
23/P/0407/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal Submission to discharge of Requirement 6(1)(f) (Emergency Response Plan for Flood Events for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as amended)
-
23/P/0240/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal submission to discharge Requirement 5(2)(b) (Biodiversity Mitigation Strategy for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
22/P/2976/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal submission to discharge Requirement 10 (Scheme of Replacement Planting for Stage 8 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
22/P/2194/DCO Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth
Formal Submission to discharge of Requirement 20 (Removal of temporary bridges and culverts for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016
Timeline
Dates from the published record
-
20 Nov 2019
Received by Bristol, City of
-
20 Dec 2019
Decision issued: Approve
-
19 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
18 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Bristol, City of granted permission on 20 December 2019, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Other full applications
In Bristol, City of
-
26/P/0379/FUL Awaiting decision
45 Clevedon Road Tickenham Clevedon BS21 6RB
Proposed erection of a self-build dwelling following demolition of the existing dwelling and garage. Erection of detached garage and ground mounted solar panels.
-
26/P/1486/FUL Granted
Sandringham Hotel 1 Victoria Square Weston-super-Mare BS23 1AN
Rebuild, extension and refurbishment of existing hotel building frontage following demolition of more recent additions, replacement shop building and other associated works
-
26/P/1305/FUL Granted
7 Brampton Way Portishead BS20 6UZ
Proposed change of use of existing amenity land to residential garden and erection of a single-storey wraparound side/rear extension with attached double garage.
-
26/P/1001/FUL Granted
The Nightjar Nightingale Close Weston-super-Mare BS22 8SX
Change of use and extension of the former Public House to provide 3no. commercial units (Use Class E and sui generis hot food takeaway) at ground floor level and the creation of 2no. residential units (Use Class C3) at first floor level. Creation of new access from Redwing Drive, parking, landscaping and associated works
-
26/P/0871/FUL Granted
8 Upper Church Road Weston-super-Mare BS23 2DT
Proposed change of use of existing Class E property to form 1no. self-contained flat including alterations to fenestration.