Planning application
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Details pursuant to condition 15 (materials) of Full Planning Permission reference 23/0578 dated ...
As published by the council, reference 26/2052
Application record
- Reference
- 26/2052
- Status
- Registered
- Received
- 13 Aug 2026
- Validated
- 13 Aug 2026
- Postcode
- HA9 0NU
Site history
Applications at this address on the Brent register
This site has had 13 applications since 2016: 9 approved, 0 refused.
-
26/2025 Awaiting decision
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Details pursuant to condition 18 (counter-terrorism measures) of Full Planning Permission referen...
-
26/1991 Awaiting decision
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Details pursuant to condition 16 (landscaping) of Full Planning Permission reference 23/0578 date...
-
26/1640 Decided
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Details pursuant to condition 17 (Plan showing arrangement of cycle storage within the developmen...
-
26/1146 Granted
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Details pursuant to condition 14 (communal television/full fibre connectivity infrastructure) of Full Planning Permission reference 23/0578 dated 15 March, 2024, for Demolition of existing building and erection of building for use as a purpose-built Further Education College Campus with associated plant at roof level, provision of hard and soft landscaping and cycle parking facilities, loading bay and accessible parking bays on Rutherford Road frontage and drop off bay on Fulton Road, subject to Deed of Agreement dated 14th March 2024 under Section 106 of Town and Country Planning Act, 1990 as amended
-
26/0691 Granted
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Details pursuant to condition 6 (flood risk assessment) of Full Planning Permission reference 23/0578 dated 15 March, 2024, for Demolition of existing building and erection of building for use as a purpose-built Further Education College Campus with associated plant at roof level, provision of hard and soft landscaping and cycle parking facilities, loading bay and accessible parking bays on Rutherford Road frontage and drop off bay on Fulton Road, subject to Deed of Agreement dated 14th March 2024 under Section 106 of Town and Country Planning Act, 1990 as amended
-
26/0455 Granted
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Details pursuant to partial discharge of condition 12 (Site investigation and verification report), of Full planning permission application reference 23/0578 dated 15/03/2024 for Demolition of existing building and erection of building for use as a purpose-built Further Education College Campus with associated plant at roof level, provision of hard and soft landscaping and cycle parking facilities, loading bay and accessible parking bays on Rutherford Road frontage and drop off bay on Fulton Road.
-
26/0280 Granted
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Details pursuant to condition 28 (flood warning and evacuation plan) of Full Planning Permission reference 23/0578 dated 15 March, 2024, for Demolition of existing building and erection of building for use as a purpose-built Further Education College Campus with associated plant at roof level, provision of hard and soft landscaping and cycle parking facilities, loading bay and accessible parking bays on Rutherford Road frontage and drop off bay on Fulton Road, subject to Deed of Agreement dated 14th March 2024 under Section 106 of Town and Country Planning Act, 1990 as amended
-
26/0279 Granted
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Details pursuant to condition 13 (district heating) of Full Planning Permission reference 23/0578 dated 15 March, 2024, for Demolition of existing building and erection of building for use as a purpose-built Further Education College Campus with associated plant at roof level, provision of hard and soft landscaping and cycle parking facilities, loading bay and accessible parking bays on Rutherford Road frontage and drop off bay on Fulton Road, subject to Deed of Agreement dated 14th March 2024 under Section 106 of Town and Country Planning Act, 1990 as amended
-
26/0049 Granted
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Non-material amendment to condition 9 (tree protection plan and arboricultural method statement for removal of a silver birch tree T28) of Full Planning Permission reference 23/0578 dated 15 March, 2024, for Demolition of existing building and erection of building for use as a purpose-built Further Education College Campus with associated plant at roof level, provision of hard and soft landscaping and cycle parking facilities, loading bay and accessible parking bays on Rutherford Road frontage and drop off bay on Fulton Road, subject to Deed of Agreement dated 14th March 2024 under Section 106 of Town and Country Planning Act, 1990 as amended
-
25/2494 Granted
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Details pursuant to conditions 10 (construction method statement) and 11 (construction logistics plan) of Full Planning Permission reference 23/0578 dated 15 March, 2024, for Demolition of existing building and erection of building for use as a purpose-built Further Education College Campus with associated plant at roof level, provision of hard and soft landscaping and cycle parking facilities, loading bay and accessible parking bays on Rutherford Road frontage and drop off bay on Fulton Road, subject to Deed of Agreement dated 14th March 2024 under Section 106 of Town and Country Planning Act, 1990 as amended
Timeline
Dates from the published record
-
13 Aug 2026
Received by Brent
-
20 Aug 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 8 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Brent took a median of 56 days over the applications it decided in the last year.
What happens while it is decided
This application is with Brent for determination, against a statutory target of eight weeks. Over the last year Brent's median decision took 56 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Brent's portal will say. Our guide explains the common types.
Nearby applications
Within 500 metres
-
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
79% historically approved · decision due ~24 Aug
Details pursuant to condition 17 (Plan showing arrangement of cycle storage within the developmen...
Decided -
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
79% historically approved · decision due ~8 Oct
Details pursuant to condition 18 (counter-terrorism measures) of Full Planning Permission referen...
Awaiting decision -
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
79% historically approved · decision due ~29 Sep
Details pursuant to condition 16 (landscaping) of Full Planning Permission reference 23/0578 date...
Awaiting decision -
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Details pursuant to condition 6 (flood risk assessment) of Full Planning Permission reference 23/0578 dated 15 March, 2024, for Demolition of existing building and erection of building for use as a purpose-built Further Education College Campus with associated plant at roof level, provision of hard and soft landscaping and cycle parking facilities, loading bay and accessible parking bays on Rutherford Road frontage and drop off bay on Fulton Road, subject to Deed of Agreement dated 14th March 2024 under Section 106 of Town and Country Planning Act, 1990 as amended
Granted Conditions Demolition 8 docs -
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Non-material amendment to condition 9 (tree protection plan and arboricultural method statement for removal of a silver birch tree T28) of Full Planning Permission reference 23/0578 dated 15 March, 2024, for Demolition of existing building and erection of building for use as a purpose-built Further Education College Campus with associated plant at roof level, provision of hard and soft landscaping and cycle parking facilities, loading bay and accessible parking bays on Rutherford Road frontage and drop off bay on Fulton Road, subject to Deed of Agreement dated 14th March 2024 under Section 106 of Town and Country Planning Act, 1990 as amended
Granted Amendments Demolition Trees 7 docs -
Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU
Details pursuant to condition 28 (flood warning and evacuation plan) of Full Planning Permission reference 23/0578 dated 15 March, 2024, for Demolition of existing building and erection of building for use as a purpose-built Further Education College Campus with associated plant at roof level, provision of hard and soft landscaping and cycle parking facilities, loading bay and accessible parking bays on Rutherford Road frontage and drop off bay on Fulton Road, subject to Deed of Agreement dated 14th March 2024 under Section 106 of Town and Country Planning Act, 1990 as amended
Granted Conditions Demolition 5 docs