Skip to content
PlanIndex Get alerts
Menu

Planning application

Land To North And South Wilsden Old Allen Road BD13 3RU

Awaiting decision Bradford 25/03275/MAF Major Full Application

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Construction, operation and decommissioning of a Battery Energy Storage System (BESS) facility and associated infrastructure

As published by the council, reference 25/03275/MAF

Application record

Reference
25/03275/MAF
Type
Major Full Application
Status
Pending Consideration
Received
2 Oct 2025
Validated
2 Oct 2025
Ward
Thornton And Allerton (ward 23)
Parish
Not In A Parish
Postcode
BD13 3RU

Timeline

Dates from the published record

  1. 2 Oct 2025

    Received by Bradford

  2. 26 Jul 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 1 January 2026, 13 weeks from validation under the statutory target. Extensions of time are common and are agreed case by case.

    Bradford took a median of 56 days over the applications it decided in the last year.

Who's behind it

Company information only, from the register and Companies House

GP Planning Ltd Agent, a planning consultancy registered in Daventry

Active · incorporated 2006 · Daventry

55 applications on PlanIndex · across 26 councils · 97% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Renewable Connections Developments Limited Applicant, a developer registered in Norwich

Active · incorporated 2019 · Norwich

1 application on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

134 documents on file for this application

  • WY FIRE SERVICE Consultee Comment · 10 Dec 2025
  • WEST YORKSHIRE FIRE AND RESCUE SERVICE Consultee Comment · 10 Dec 2025
  • CONSULTEE: TREES TEAM Consultee Comment · 05 Dec 2025
  • CONSULTEE: TREES TEAM Consultee Comment · 04 Dec 2025
  • CONSULTEE: ENVIRONMENTAL HEALTH LAND CONTAMINATION Consultee Comment · 01 Dec 2025
  • CONSULTEE: LANDSCAPE DESIGN TEAM Consultee Comment · 28 Nov 2025
  • YORKSHIRE WATER Consultee Comment · 20 Nov 2025
  • HIGHWAYS CONSULTATION RESPONSE Consultee Comment · 19 Nov 2025
  • CONSULTEE: ENVIRONMENTAL HEALTH NUISANCE Consultee Comment · 12 Nov 2025
  • CONSULTEE: RIGHTS OF WAY Consultee Comment · 12 Nov 2025
  • CONSULTEE: BIODIVERSITY TEAM Consultee Comment · 12 Nov 2025
  • ENVIRONMENT AGENCY Consultee Comment · 10 Nov 2025
  • CONSULTEE: CONSERVATION TEAM Consultee Comment · 06 Nov 2025
  • CLEAN AIR TEAM Consultee Comment · 05 Nov 2025
  • ARCHAEOLOGY SERVICE - MR DAVID WILLIAMS Consultee Comment · 05 Nov 2025
  • CONSULTEE: WILSDEN PARISH COUNCIL Consultee Comment · 04 Nov 2025
  • CONSULTEE: DRAINAGE CONSULTATIONS Consultee Comment · 04 Nov 2025
  • CONSULTEE: CHRIS HUGHES - WEST YORKSHIRE POLICE - DOCO Consultee Comment · 03 Nov 2025
  • CONSULTEE: LOCAL PLAN Consultee Comment · 31 Oct 2025
  • COAL AUTHORITY Consultee Comment · 30 Oct 2025
  • THE COAL AUTHORITY Consultee Comment · 28 Oct 2025
  • ECOLOGICAL IMPACT ASSESSMENT Revised Supporting Information · 28 Oct 2025
  • SITE NOTICE Publicity · 21 Oct 2025
  • SITE NOTICE Publicity · 21 Oct 2025
  • SITE NOTICE Publicity · 21 Oct 2025
  • SITE NOTICE MAP Publicity · 20 Oct 2025
  • PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025 PART 6 Supporting Information · 02 Oct 2025
  • NOISE IMPACT ASSESSMENT Supporting Information · 02 Oct 2025
  • PCS CONTAINER DETAILS Drawing · 02 Oct 2025
  • BATTERY CONTAINER DETAILS Drawing · 02 Oct 2025
  • LVA REPORT - APPENDIX A 07 Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 08 Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 09 Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 10 Supporting Information · 02 Oct 2025
  • THE LANDFORM AND LANDSCAPE STRATEGY PLAN Drawing · 02 Oct 2025
  • THE LANDFORM AND LANDSCAPE STRATEGY PLAN Drawing · 02 Oct 2025
  • FLOOD RISK ASSESSMENT FINAL - PART 2 Supporting Information · 02 Oct 2025
  • FLOOD RISK ASSESSMENT FINAL - PART 3 Supporting Information · 02 Oct 2025
  • FLOOD RISK ASSESSMENT FINAL - PART 4 Supporting Information · 02 Oct 2025
  • FLOOR RISK ASSESSMENT FINAL - PART 1 Supporting Information · 02 Oct 2025
  • TOPOGRAPHICAL SURVEY Drawing · 02 Oct 2025
  • TOPOGRAPHICAL SURVEY Drawing · 02 Oct 2025
  • APPLICATION FORM REDACTED Application Form · 02 Oct 2025
  • PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025 PART3 Supporting Information · 02 Oct 2025
  • PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025 PART 8 Supporting Information · 02 Oct 2025
  • FENCE AND GATES DETAILS Drawing · 02 Oct 2025
  • ACCESS TRACK SECTION DETAILS Drawing · 02 Oct 2025
  • STATEMENT OF COMMUNITY INVOLVEMENT SEPTEMBER 2025 Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 05 Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 12 Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 14 Supporting Information · 02 Oct 2025
  • TREE SURVEY AND CONSTRAINTS PLAN PROTECTION MEASURES Drawing · 02 Oct 2025
  • THE LANDFORM AND LANDSCAPE STRATEGY PLAN Drawing · 02 Oct 2025
  • LANDFORM AND LANDSCAPE STRATEGY Drawing · 02 Oct 2025
  • SITE LOCATION PLAN Drawing · 02 Oct 2025
  • TOPOGRAPHICAL SURVEY Drawing · 02 Oct 2025
  • FINAL ALTERNATIVE SITE ASSESSMENT SEPTEMBER 2025 Supporting Information · 02 Oct 2025
  • MINERALS RESOURCE ASSESSMENT SEPTEMBER 2025 Supporting Information · 02 Oct 2025
  • HISTORIC ENVIRONMENT DESK BASED ASSESSMENT Supporting Information · 02 Oct 2025
  • PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025 PART4 Supporting Information · 02 Oct 2025
  • PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025 PART 5 Supporting Information · 02 Oct 2025
  • PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025 PART1 Supporting Information · 02 Oct 2025
  • CUSTOMER SUBSTATION DETAILS Drawing · 02 Oct 2025
  • SPARE PARTS CONTAINER DETAILS Drawing · 02 Oct 2025
  • OUTLINE BATTERY SAFETY MANAGEMENT PLAN Supporting Information · 02 Oct 2025
  • CONSTRUCTION TRAFFIC MANAGEMENT PLAN 2025-08-22_COMPRESSED Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 15 Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 01 Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 02 Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 03 Supporting Information · 02 Oct 2025
  • BESS LAYOUT Drawing · 02 Oct 2025
  • DEVELOPMENT ZONES Drawing · 02 Oct 2025
  • TREE SURVEY AND CONSTRAINTS PLAN PROTECTION MEASURES Drawing · 02 Oct 2025
  • TREE SURVEY AND ARBORICULTURAL IMPACT ASSESSMENT Supporting Information · 02 Oct 2025
  • BIA PROPOSED CONDITIONS VISUALISATION (ATLAS)_V2R3_OPTIMIZED Supporting Information · 02 Oct 2025
  • BIA PROPOSED VISUALISATION (ATLAS)_V2R3_OPTIMIZED Supporting Information · 02 Oct 2025
  • BIA RETENTION VISUALISATION (ATLAS)_V2R3_OPTIMIZED Supporting Information · 02 Oct 2025
  • PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025 PART 7 Supporting Information · 02 Oct 2025
  • AUXILIARY TRANSFORMER DETAILS Drawing · 02 Oct 2025
  • DNO DETAILS Drawing · 02 Oct 2025
  • TRANSPORT STATEMENT 2025-08-22 Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 04 Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 06 Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 11 Supporting Information · 02 Oct 2025
  • LVA REPORT - APPENDIX A 13 Supporting Information · 02 Oct 2025
  • LVA REPORT Supporting Information · 02 Oct 2025
  • THE LANDFORM AND LANDSCAPE STRATEGY PLAN Drawing · 02 Oct 2025
  • ARTICLE 13 NOTICE Supporting Information · 02 Oct 2025
  • BESS LAYOUT Drawing · 02 Oct 2025
  • BIA BASELINE CONDITIONS VISUALISATION (ATLAS)_V2R3_OPTIMIZED Supporting Information · 02 Oct 2025
  • BIA BASELINE VISUALISATION_PARCEL REF (ATLAS)_V2R3_OPTIMIZED Supporting Information · 02 Oct 2025
  • HV SUBSTATION SITE CROSS-SECTION Drawing · 02 Oct 2025
  • COVERING LETTER Supporting Information · 02 Oct 2025
  • TOPOGRAPHICAL SURVEY Drawing · 02 Oct 2025
  • TOPOGRAPHICAL SURVEY Drawing · 02 Oct 2025
  • BIA BASELINE VISUALISATION (ATLAS)_V2R3_OPTIMIZED Supporting Information · 02 Oct 2025
  • ECOLOGICAL IMPACT ASSESSMENT Superseded Supporting Information · 02 Oct 2025
  • PLANNING, DESIGN AND ACCESS STATEMENT SEPTEMBER 2025 Supporting Information · 02 Oct 2025
  • BNG METRIC Supporting Information · 02 Oct 2025
  • TOPOGRAPHICAL SURVEY Drawing · 02 Oct 2025
  • STATUTORY BIODIVERSITY METRIC Supporting Information · 02 Oct 2025
  • CCTV POLE MOUNTING DETAILS Drawing · 02 Oct 2025
  • TOPOGRAPHICAL SURVEY Drawing · 02 Oct 2025
  • TOPOGRAPHICAL SURVEY Drawing · 02 Oct 2025
  • REV B PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025_PART3 Supporting Information · 22 Aug 2025
  • 12875 REV B PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025_PART7 Supporting Information · 22 Aug 2025
  • 12875 REV B PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025_PART8 Supporting Information · 22 Aug 2025
  • 12875 REV B PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025_PART6 Supporting Information · 22 Aug 2025
  • DEVELOPMENT ZONES Drawing · 22 Aug 2025
  • SITE LOCATION PLAN Drawing · 22 Aug 2025
  • BESS LAYOUT Drawing · 22 Aug 2025
  • BATTERY SAFETY MANAGEMENT PLAN Supporting Information · 22 Aug 2025
  • APPLICATION FORM REDACTED Application Form · 22 Aug 2025
  • HISTORIC ENVIRONMENT DESK BASED ASSESSMENT Supporting Information · 22 Aug 2025
  • 12875 REV B PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025_PART5 Supporting Information · 22 Aug 2025
  • REV B PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025_PART2 Supporting Information · 22 Aug 2025
  • NOISE IMPACT ASSESSMENT Supporting Information · 22 Aug 2025
  • PCS CONTAINER DETAILS Drawing · 22 Aug 2025
  • CUSTOMER SUBSTATION DETAILS Drawing · 22 Aug 2025
  • BESS LAYOUT Drawing · 22 Aug 2025
  • CONSTRUCTION TRAFFIC MANAGEMENT PLAN Supporting Information · 22 Aug 2025
  • ALTERNATIVE SITE ASSESSMENT OLD ALLEN ROAD BESS JULY 2025 Supporting Information · 22 Aug 2025
  • MINERAL RESOURCE ASSESSMENT OLD ALLEN ROAD BESS JULY 2025 Supporting Information · 22 Aug 2025
  • FENCE AND GATES DETAILS Drawing · 22 Aug 2025
  • AUXILIARY TRANSFORMER DETAILS Drawing · 22 Aug 2025
  • WATER TANK DETAILS Drawing · 22 Aug 2025
  • ACCESS TRACK SECTION DETAILS Drawing · 22 Aug 2025
  • 12875 REV B PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025_PART4 Supporting Information · 22 Aug 2025
  • REV B PHASE I GEO-ENVIRONMENTAL ASSESSMENT REPORT 31 JAN 2025_PART1 Supporting Information · 22 Aug 2025
  • BESS LAYOUT SIDE VIEW Superseded Drawings · 22 Aug 2025
  • BATTERY CONTAINER DETAILS Drawing · 22 Aug 2025
  • DNO DETAILS Drawing · 22 Aug 2025
  • SPARE PARTS CONTAINER DETAILS Drawing · 22 Aug 2025
  • R01-GPBRAD-TRANSPORT STATEMENT 2025-08-22_COMPRESSED Supporting Information · 22 Aug 2025

Watch members (£5 a month) open the document list from here.

Open the documents

What happens while it is decided

This application is with Bradford for determination, against a statutory target of thirteen weeks. Over the last year Bradford decided full applications in a median of 56 days. More in our guide to how long planning decisions take.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

In Bradford

  • 26/03106/FUL Awaiting decision

    Flats 1 & 2 31 Lister Street Ilkley West Yorkshire LS29 9ET

    Amalgamation of two existing flats to form 1 x 5-bed dwelling

    Full applications
  • 26/03021/FUL Awaiting decision

    Fernhill Jew Lane Oxenhope Keighley West Yorkshire BD22 9HS

    Demolition of shed. Construction of a single storey residential property with raised decking, to be used as a holiday let

    Full applications
  • 26/02204/FUL Refused

    337A Thornton Road Bradford West Yorkshire BD8 9BS

    Front extension to form dessert bar, new shopfront, roller shutters, front canopy, timber store & front decking

    10 Sep 2026 Full applications
  • 26/02494/FUL Refused

    155 Bierley Lane Bradford West Yorkshire BD4 6DU

    Change of use of existing garage to light commercial garage and single storey infill extension between garage and dwelling (part retrospective)

    10 Sep 2026 Full applications
  • 26/02545/FUL Refused

    87 Manningham Lane Bradford West Yorkshire BD1 3BN

    Removal of existing 6no antennas on 3no steelwork support structures and replacement with 10 metre high stub tower supporting 6no antennas and 2no transmission dishes, removal of 2no radio equipment cabinets and replacement with 1no new cabinet and ancillary development thereto

    10 Sep 2026 Full applications