Planning application
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Relates to 25/03757/EFUL
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Discharge of condition 9 (Travel Plan) of application 25/03757/EFUL (Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts)
As published by the council, reference 26/02891/COND
Application record
- Reference
- 26/02891/COND
- Type
- Discharge of Condition
- Status
- Pending Consideration
- Received
- 3 Aug 2026
- Validated
- 3 Aug 2026
- Ward
- Bathwick
Comment by 15 September 2026
The council is taking comments on this application until then. Comments go to Bath and North East Somerset through their own planning portal.
Site history
Applications at this address on the Bath and North East Somerset register
This site has had 15 applications since 2024: 2 approved, 0 refused.
-
26/03293/COND Awaiting decision
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Discharge of condition 16 (Landscape and Ecological Management Plan (Pre-occupation)) of application 25/03757/EFUL (Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts).
-
26/03128/D6A Awaiting decision
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Discharge of planning obligations in Schedule 3, Section 2, Clause 1.3 (Targeted Recruitment and Training) of the Section 106 agreement attached to Planning Permission reference 25/03757/EFUL.
-
26/02917/COND Decided
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Discharge of condition 6 (Ecological Construction Environmental Management Plan (Pre-commencement)) of application 25/03757/EFUL (Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts).
-
26/02914/COND Decided
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Discharge of conditions 7 (Construction Environmental Management Plan (Environmental Protection) (Pre-commencement)) and 8 (Construction Management Plan (Pre-commencement)) of application 25/03757/EFUL (Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts).
-
26/02892/COND Decided
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Discharge of condition 3 (Arboricultural Method Statement and Tree Protection Plan) of application 25/03757/EFUL (Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts)
-
26/02889/COND Decided
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Discharge of conditions 4 (Archaeology - Controlled Excavation) and 19 (Archaeology - Post Excavation and Publication) of 25/03757/EFUL (Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts)
-
26/02888/COND Decided
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Discharge of conditions 2 (Biodiversity Gain Plan) of application 25/03757/EFUL (Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts)
-
26/02890/COND Decided
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Discharge of condition 5 (Detailed Drainage Design) of application 25/03757/EFUL (Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts)
-
25/03757/EFUL Granted
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts
-
25/01963/SCOPE Awaiting decision
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Request for Screening Opinion in relation to the proposed delivery of 8 blocks of student residences and associated access/internal highways, drainage, open space, and landscaping within the existing Eastern Playing Fields and Eastern Car park extensions at the east of the Universitys Claverton Down Campus.
Timeline
Dates from the published record
-
3 Aug 2026
Received by Bath and North East Somerset
-
10 Aug 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 28 September 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Bath and North East Somerset took a median of 51 days over the applications it decided in the last year.
Related applications
Cases linked to this one on the register
-
25/03757/EFUL Granted
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts
Documents
Plans, drawings, consultee responses and the officer's report
Documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat happens while it is decided
This application is with Bath and North East Somerset for determination, against a statutory target of eight weeks. Over the last year Bath and North East Somerset decided condition discharge and variation applications in a median of 55 days. More in our guide to how long planning decisions take.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts
Granted Full applications -
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Discharge of condition 6 (Ecological Construction Environmental Management Plan (Pre-commencement)) of application 25/03757/EFUL (Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts).
Decided Conditions -
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Discharge of conditions 7 (Construction Environmental Management Plan (Environmental Protection) (Pre-commencement)) and 8 (Construction Management Plan (Pre-commencement)) of application 25/03757/EFUL (Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts).
Decided Conditions -
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Discharge of condition 3 (Arboricultural Method Statement and Tree Protection Plan) of application 25/03757/EFUL (Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts)
Decided Conditions Trees -
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Discharge of conditions 4 (Archaeology - Controlled Excavation) and 19 (Archaeology - Post Excavation and Publication) of 25/03757/EFUL (Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts)
Decided Conditions -
Eastern Sports Field, Sports Training Village, University Of Bath Campus, Claverton Down, Bath, Bath And North East Somerset,
Discharge of conditions 2 (Biodiversity Gain Plan) of application 25/03757/EFUL (Full planning application for the delivery of student accommodation with associated vehicular, pedestrian and cycle access, internal highways, car parking (including reconfiguration of an existing parking area), cycle parking, green and blue infrastructure (including drainage features and soft landscape planting), hard landscaping, boundary treatment, new and replacement external lighting, ancillary infrastructure (including storage, substations, pumping stations, photovoltaic panels, and internal and external plant), ground remodelling, and two padel courts)
Decided Conditions
Other condition discharge and variation applications
In Bath and North East Somerset
-
26/03342/COND Awaiting decision
Bath Fire Station, Bathwick Street, Bathwick, Bath, BA2 6PU
Discharge of condition 13 (Landscape Design Proposals (Bespoke Trigger)) and 14 (Design Details Strategy (Bespoke Trigger)) of application 25/02735/FUL (Erection of fire station, offices and drill tower with revised access, car parking, landscaping and associated ancillary works following demolition of existing fire station, offices and drill tower).
-
26/03339/COND Awaiting decision
High Hall , The Street, Compton Martin, Bristol, Bath And North East Somerset, BS40 6JQ
Discharge of conditions 2 (Materials - Submission of Schedule and Samples (Bespoke Trigger)) and 3 (Window) of application 26/00256/FUL (Erection of single storey front extension (replacement and enlargement) following demolition of existing front extension. Landscape alterations including new stone retaining walls and steps).
-
26/03237/COND Decided
58 Rosewarn Close, Whiteway, Bath, Bath And North East Somerset, BA2 1PB
Discharge of conditions 2 (Bicycle/Refuse Storage) of application 26/00623/FUL (Change of use from 3-bed dwelling (Use Class C3) to 4-bed house of multiple occupation (HMO) (Use Class C4))
-
26/03316/COND Awaiting decision
Bath Fire Station, Bathwick Street, Bathwick, Bath, BA2 6PU
Discharge of conditions 11 (Materials - Submission of Materials Schedule (Bespoke Trigger)), 15 (Privacy Screen (Bespoke Trigger)) and 16 (External Lighting (Bespoke Trigger)) of application 25/02735/FUL (Erection of fire station, offices and drill tower with revised access, car parking, landscaping and associated ancillary works following demolition of existing fire station, offices and drill tower).
-
26/03300/COND Awaiting decision
Freshford Mill , Rosemary Lane, Freshford, Bath, Bath And North East Somerset, BA2 7PL
Discharge of condition 13 (Materials samples (Bespoke Trigger)) of application 20/02020/VAR (Variation of conditions 2, 3, 4, 6,7, 11, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 26, 27, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39 and 40 of application 14/05048/FUL (Proposed residential development comprising 21 units, incorporating amendments to previously approved planning permission 05/02563/FUL and associated works. (Retrospective)).