Planning application
Land East Of Gainsborough Road Bole Nottinghamshire
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Discharge of Condition 25 (Contamination) and 26 (Verification Report) on P/A 22/01713/FUL - Construction and Operation of a Battery Energy Storage System with an Electrical Output Capacity of up to 500MW and Associated Development Including Power Inverter Systems, Electrical Banking Station, Electrical Cabling including Below Ground Cabling to 400KV Switchyard, Welfare Facilities, Internal Access Roads, Site Security Infrastructure, Lighting, Boundary Treatments, and Landscaping.
As published by the council, reference 26/01304/COND
Application record
- Reference
- 26/01304/COND
- Type
- Request for Condition Discharge
- Status
- Awaiting decision
- Received
- 7 Oct 2026
- Validated
- 7 Oct 2026
- Ward
- Sturton
- Parish
- West Burton
- Decision by
- Delegated Decision
Site history
Applications at this address on the Bassetlaw register
This site has had 5 applications since 2026: 1 approved, 0 refused.
-
26/01226/VPO8 Granted
Land East Of Gainsborough Road Bole Nottinghamshire
Discharge of Biodivisity Net Gain Agreements of Section 106 Agreement under P.A. 22/01713/FUL - Construction and Operation of a Battery Energy Storage System with an Electrical Output Capacity of up to 500MW and Associated
-
26/00910/COND Decided
Land East Of Gainsborough Road Bole Nottinghamshire
Discharge Condition 21 ( Construction Management Plan ) on P.A 22/01713/FUL - Construction and Operation of a Battery Energy Storage System with an Electrical Output Capacity of up to 500MW and Associated Development Including Power Inverter Systems, Electrical Banking Station, Electrical Cabling including Below Ground Cabling to 400KV Switchyard, Welfare Facilities, Internal Access Roads, Site Security Infrastructure, Lighting, Boundary Treatments, and Landscaping.
-
26/00860/COND Decided
Land East Of Gainsborough Road Bole Nottinghamshire
Discharge of Conditions 11 (Surface Water Drainage) and 14 (Foul Water Drainage) of P.A. 22/01713/FUL - Construction and Operation of a Battery Energy Storage System with an Electrical Output Capacity of up to 500MW and Associated Development Including Power Inverter Systems, Electrical Banking Station, Electrical Cabling including Below Ground Cabling to 400KV Switchyard, Welfare Facilities, Internal Access Roads, Site Security Infrastructure, Lighting, Boundary Treatments, and Landscaping.
-
26/00847/COND Decided
Land East Of Gainsborough Road Bole Nottinghamshire
Discharge of Condition 31 (Landscape Plan) on P/A 22/01713/FUL - Construction and Operation of a Battery Energy Storage System with an Electrical Output Capacity of up to 500MW and Associated Development Including Power Inverter Systems, Electrical Banking Station, Electrical Cabling including Below Ground Cabling to 400KV Switchyard, Welfare Facilities, Internal Access Roads, Site Security Infrastructure, Lighting, Boundary Treatments, and Landscaping.
Timeline
Dates from the published record
-
7 Oct 2026
Received by Bassetlaw
-
18 Nov 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 2 December 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Bassetlaw took a median of 67 days over the applications it decided in the last year.
Who's behind it
Company information only, from the register and Companies House
DWD Property and Planning Limited Agent, a planning consultancy registered in Helsby
Active · incorporated 2023 · Helsby
129 applications on PlanIndex · across 42 councils · 94% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
14 documents on file for this application
A planning file usually holds the application form, the consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWorking a patch? Trade sends you every new job in your area each morning. 14 days free.
What happens while it is decided
This application is with Bassetlaw for determination, against a statutory target of eight weeks. Over the last year Bassetlaw decided condition discharge and variation applications in a median of 54 days. More in our guide to how long planning decisions take.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Other condition discharge and variation applications
In Bassetlaw
-
26/01474/COND Awaiting decision
31 Market Place Retford Nottinghamshire DN22 6DW
Discharge of Condition 4 (Door Repair to Framework and Door Detail) on P/A 25/01306/LBA
-
26/01471/COND Awaiting decision
12 High Street Misterton South Yorkshire DN10 4BU
Discharge of Condition 3- (Sound Insulation), 4 - (Shop Front Design), and 5 (Bins) to P/A 26/00633/FUL - Change of use of the Ground Floor of Dwelling to Form a Retail Shop, Create a Kitchen and Lounge on the First Floor. Retain External Staircase to the Rear and Erection of a Detached Garage following Demolition of Existing Garage
-
26/01221/COND Decided
The Brick Barn Ratcliffe Grange Farm Mansfield Road Worksop Nottinghamshire S80 3DW
Discharge Conditions 3 ( Windows and Doors) 4 (Heads and Cills) 7 (Facing Materials) 8 (Roof Lights) on P.A 24/00599/LBA
-
26/00089/COND Decided
First Floor And Second Floor 15 Bridgegate Retford Nottinghamshire DN22 6AE
Discharge of Condition 6 (Details Methodology) of P.A. 24/01408/LBA (Application for the Conversion of Existing Offices (Class E) into 2 Residential Dwellings (Class C3))
-
26/01445/COND Awaiting decision
West Burton Power Station North Road West Burton Nottinghamshire DN22 9BL
Application for Discharge of Requirement 15 - Construction Traffic Management Plan