Planning application
East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Submission of Details reserved by Requirement 35 Amendments to approved details pursuant to The East Anglia 3 Offshore Wind Farm Order 2017
As published by the council, reference DC/26/04031
Application record
- Reference
- DC/26/04031
- Type
- Discharge of Requirement
- Status
- Awaiting decision
- Received
- 16 Sep 2026
- Validated
- 16 Sep 2026
- Ward
- Bramford
- Parish
- Bramford
Site history
Applications at this address on the Babergh register
This site has had 4 applications since 2020: 3 approved, 0 refused.
-
DC/26/02487 Granted
East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk
East Anglia Three - Onshore Cable Route: Out of hours working request for the following dates June: 21st, 28th, July: 05th, 12th 19th and 26th (10:00 - 16:00).
-
DC/26/02120 Granted
East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk
East Anglia 3 Onshore Converter Station - Application pursuant to discharge of requirements 24 and 25(2)(f). to agree out of hours working (a request for out of hours working on the following dates May: 24th, 25th & 31st (07:00 hrs to 17:00hrs) and June: 7th, 14th, 21st & 28th (07:00 hrs to 17:00hrs)
-
DC/21/00067 Granted
East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk
Approval of details reserved by Requirement 24 (Control of noise during operational phase (Part 2)) pursuant to The East Anglia ONE Offshore Wind Farm Order 2014
Timeline
Dates from the published record
-
16 Sep 2026
Received by Babergh
-
23 Sep 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 11 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Babergh took a median of 52 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
1 document on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Babergh for determination, against a statutory target of eight weeks. Over the last year Babergh decided condition discharge and variation applications in a median of 49 days. More in our guide to how long planning decisions take.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk
East Anglia 3 Onshore Converter Station - Application pursuant to discharge of requirements 24 and 25(2)(f). to agree out of hours working (a request for out of hours working on the following dates May: 24th, 25th & 31st (07:00 hrs to 17:00hrs) and June: 7th, 14th, 21st & 28th (07:00 hrs to 17:00hrs)
Granted Conditions 3 docs -
East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk
East Anglia 3 Onshore Converter Station - Application pursuant to discharge of requirements 24 and 25(2)(f). to agree out of hours working (a request for out of hours working on the following dates May: 24th, 25th & 31st (07:00 hrs to 17:00hrs) and June: 7th, 14th, 21st & 28th (07:00 hrs to 17:00hrs)
Granted Conditions 3 docs -
East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk
East Anglia Three - Onshore Cable Route: Out of hours working request for the following dates June: 21st, 28th, July: 05th, 12th 19th and 26th (10:00 - 16:00).
Granted Conditions 3 docs -
East Anglia 3-Converter Station
Out of Hours Working request - 7am-7pm on 19/10/25, 26/10/25 and 02/11/25
Granted Conditions 2 docs -
East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk
Approval of details reserved by Requirement 24 (Control of noise during operational phase (Part 2)) pursuant to The East Anglia ONE Offshore Wind Farm Order 2014
Granted Conditions 6 docs -
East Anglia Three Offshore Windfarm
Approval of details reserved by Requirement 23 (External Lighting and Control of Artificial Light Emissions (Parts 1 and 2)) pursuant to The East Anglia THREE Offshore Wind Farm Order 2017
Granted Conditions 9 docs
Other condition discharge and variation applications
In Babergh
-
DC/26/00236 Granted
Chilton Woods Mixed Development To North Of Woodhall Business Park Sudbury Suffolk
Discharge of Conditions Application for B/15/01718 - Part discharge of Conditions 38 (Landscaping) and 43 (Open Space) for phase 4 only.
-
DC/26/00355 Refused
Land To The Rear Of 30 Market Hill Sudbury Suffolk
Application under Section 73 of The Town and Country Planning Act 1990 - Variation of Condition 2 (Approved Plans and Documents) and Condition 12 (Provision of Access Prior to Any Other Works Commencing) of Planning Permission DC/25/05227 dated 23/01/2026 - Erection of 4No. (terraced) dwellings and alterations/improvement to: (1) outbuilding to form cycle store, (2) boundary wall and (3) existing access.
-
DC/26/04408 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement 6 Detailed Written Scheme of Investigation for Stage 3 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024
-
DC/26/04407 Awaiting decision
High Elm Bungalow Crowfield Road Stonham Aspal Suffolk
Discharge of Conditions Application for DC/24/01026 - Condition 3 (Biodiversity Net Gain)
-
DC/26/04395 Awaiting decision
Little Wenham Hall Hall Lane Wenham Parva Colchester Suffolk CO7 6PZ
Discharge of Conditions for DC/24/02709 - Condition 14 (Historic Floor Finishes- Building D)