Planning application

The National Grid (Bramford To Twinstead Reinforcement) Order 2024

Granted Babergh DC/25/04511 Discharge of Requirement

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Approval of Details reserved by Schedule 3, Requirement 4(a) - Construction Environmental Management Plan for Stage 3 pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024

As published by the council, reference DC/25/04511

Application record

Reference
DC/25/04511
Type
Discharge of Requirement
Status
Granted
Decision
Granted
Received
10 Oct 2025
Validated
10 Oct 2025
Decided
21 Nov 2025
Decision by
Delegated Decision

Site history

Applications at this address on the Babergh register

This site has had 75 applications since 2025: 38 approved, 1 refused.

  • DC/26/04408 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 6 Detailed Written Scheme of Investigation for Stage 3 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submitted 9 Oct 2026 Conditions
  • DC/26/04237 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Approval of Details reserved by Stage 3 Requirement 6 of the Detailed Written Scheme of Investigation (DWSI) pursuant to the The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) - where no further archaeological investigation is required at land in the vicinity of Trenches 367-370 - as marked on the attached plans.

    Submitted 29 Sep 2026 Conditions
  • DC/26/04195 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Approval of Details reserved by Stage 3 Requirement 6 of the Detailed Written Scheme of Investigation (DWSI) pursuant to the The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) - where no further archaeological investigation is required at land in the vicinity of Trenches 305-320 - as marked on the attached plans.

    Submitted 25 Sep 2026 Conditions
  • DC/26/04067 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Schedule 3; Requirement 8 Retention and Removal of Trees, Woodlands and Hedgerows Plan for Stage 6 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    Submitted 17 Sep 2026 Conditions
  • DC/26/04076 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 8(1) Retention and Removal of Trees, Woodlands and Hedgerows for Stage 8 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    Submitted 17 Sep 2026 Conditions
  • DC/26/04068 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 8(1) Retention and Removal of Trees, Woodlands and Hedgerows for Stage 7 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submitted 17 Sep 2026 Conditions
  • DC/26/04022 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Detials reserved by Requirement 14 - Soil Management Plan for Stages 6-8 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    Submitted 15 Sep 2026 Conditions
  • DC/26/03944 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 4(1)(d) - Landscape and Ecological Management Plan for Stage 8 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    Submitted 10 Sep 2026 Conditions
  • DC/26/03938 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 4(1)(d) Landscape and Ecological Management Plan for Stage 7 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    Submitted 9 Sep 2026 Conditions
  • DC/26/03856 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 8 Retention and Removal of Trees, Woodlands and Hedgerows Plan for Stage 4.2 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submitted 4 Sep 2026 Conditions

Timeline

Dates from the published record

  1. 10 Oct 2025

    Received by Babergh

  2. 21 Nov 2025

    Decision issued: Granted

  3. 9 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

5 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Babergh granted permission on 21 November 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/03850 Submitted 4 Sep 2026 50 yards away

    95% historically approved · decision due ~30 Oct

    Submission of details reserved by Requirement 4(1)(d) Landscape and Ecological Management Plan for Stage 6 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    Awaiting decision Conditions
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/02061 Submitted 14 May 2026 50 yards away

    The National Grid (Bramford to Twinstead Reinforcement) Order 2024: Written notice of the commencement of construction of Stage 4.2 of the Authorised Development (Schedule 3, Requirement 3(4)) - commenced on 11 May 2026.

    Awaiting decision Conditions 1 doc
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/03842 Submitted 3 Sep 2026 50 yards away

    95% historically approved · decision due ~29 Oct

    Submission of Details reserved by Requirement 4(a) - Construction Environmental Management Plan for Stages 6-8 of the authorised development pursuant to the The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    Awaiting decision Conditions 1 doc
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/03080 Submitted 16 Jul 2026 50 yards away

    Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) where no further archaeological investigation is required at land in vicinity of Polstead Heath, Holt Road and B1068, Leavenheath.

    Granted Conditions 5 docs
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/25/04004 Submitted 9 Sep 2025 50 yards away

    Approval of Details reserved by Schedule 3, Requirement 3(1) - Notification of Pre-commencement Operations

    Decided Conditions 1 doc
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/03856 Submitted 4 Sep 2026 50 yards away

    95% historically approved · decision due ~30 Oct

    Submission of Details reserved by Requirement 8 Retention and Removal of Trees, Woodlands and Hedgerows Plan for Stage 4.2 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Awaiting decision Conditions Trees 8 docs

In Babergh

  • DC/26/00236 Granted

    Chilton Woods Mixed Development To North Of Woodhall Business Park Sudbury Suffolk

    Discharge of Conditions Application for B/15/01718 - Part discharge of Conditions 38 (Landscaping) and 43 (Open Space) for phase 4 only.

    Received 21 Jan, published by the council 24 Jul 2026 Conditions
  • DC/26/00355 Refused

    Land To The Rear Of 30 Market Hill Sudbury Suffolk

    Application under Section 73 of The Town and Country Planning Act 1990 - Variation of Condition 2 (Approved Plans and Documents) and Condition 12 (Provision of Access Prior to Any Other Works Commencing) of Planning Permission DC/25/05227 dated 23/01/2026 - Erection of 4No. (terraced) dwellings and alterations/improvement to: (1) outbuilding to form cycle store, (2) boundary wall and (3) existing access.

    Received 28 Jan, published by the council 24 Jul 2026 Conditions
  • DC/26/04408 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 6 Detailed Written Scheme of Investigation for Stage 3 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Received 9 Oct, published by the council 11 Oct 2026 Conditions
  • DC/26/04407 Awaiting decision

    High Elm Bungalow Crowfield Road Stonham Aspal Suffolk

    Discharge of Conditions Application for DC/24/01026 - Condition 3 (Biodiversity Net Gain)

    Received 9 Oct, published by the council 11 Oct 2026 Conditions
  • DC/26/04395 Awaiting decision

    Little Wenham Hall Hall Lane Wenham Parva Colchester Suffolk CO7 6PZ

    Discharge of Conditions for DC/24/02709 - Condition 14 (Historic Floor Finishes- Building D)

    Received 8 Oct, published by the council 11 Oct 2026 Conditions