Skip to content
PlanIndex Get alerts
Menu

Planning application

Field to West of National Grid Converter Substation, Church Lane, Aldington, Kent, TN25 6AF

Awaiting decision Ashford PA/2026/1511 Lawful development: Existing use

Relates to PA/2026/0214

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Application for a Lawful Development Certificate -Existing - to confirm the lawful commencement of development pursuant to planning permission PA/2026/0214.

As published by the council, reference PA/2026/1511

Application record

Reference
PA/2026/1511
Type
Lawful development: Existing use
Status
Under Consultation
Received
20 Aug 2026
Validated
20 Aug 2026
Ward
Bircholt
Parish
Smeeth
Decision by
Delegated Decision
Postcode
TN25 6AF

Comment by 19 September 2026

The council is taking comments on this application until then. Comments go to Ashford through their own planning portal.

Site history

Applications at this address on the Ashford register

This site has had 2 applications since 2026: 1 approved, 0 refused.

  • PA/2026/0214 Granted

    Field to West of National Grid Converter Substation, Church Lane, Aldington, Kent, TN25 6AF

    Variation of conditions 2 (Approved Plans), 4 (CEMP), 5 (Tree Protection), 7 (Noise Impact Assessment), 10 (Surface Water Drainage), 12 (Fire Pollutants Control), 13 (Soft Landscaping), 15 (LEMP), 16 (EMMP), 18 (External Lighting) and removal of Condition 6(i) (Highway condition Survey) in its entirety for Planning Permission PA/2022/2544 "The laying out of a battery storage facility, intermediate substation, water storage tank, cabling, fencing, access tracks and associated drainage infrastructure on field to west of National Grid Sellindge Converter Substation"; to allow for changes to layout and alternative technology to be installed.

    Decided 12 Jun 2026 Amendments

Timeline

Dates from the published record

  1. 20 Aug 2026

    Received by Ashford

  2. 28 Aug 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 15 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Ashford took a median of 59 days over the applications it decided in the last year.

Cases linked to this one on the register

  • PA/2026/0214 Granted

    Field to West of National Grid Converter Substation, Church Lane, Aldington, Kent, TN25 6AF

    Variation of conditions 2 (Approved Plans), 4 (CEMP), 5 (Tree Protection), 7 (Noise Impact Assessment), 10 (Surface Water Drainage), 12 (Fire Pollutants Control), 13 (Soft Landscaping), 15 (LEMP), 16 (EMMP), 18 (External Lighting) and removal of Condition 6(i) (Highway condition Survey) in its entirety for Planning Permission PA/2022/2544 "The laying out of a battery storage facility, intermediate substation, water storage tank, cabling, fencing, access tracks and associated drainage infrastructure on field to west of National Grid Sellindge Converter Substation"; to allow for changes to layout and alternative technology to be installed.

    Decided 12 Jun 2026 Amendments

Documents

Plans, drawings, consultee responses and the officer's report

8 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Ashford for determination, against a statutory target of eight weeks. Over the last year Ashford decided lawful development applications in a median of 56 days. More in our guide to how long planning decisions take.

About lawful development applications

A lawful development certificate is a legal determination that existing or proposed works do not need planning permission; the merits of the scheme are not considered. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • Field to West of National Grid Converter Substation, Church Lane, Aldington, Kent, TN25 6AF

    PA/2026/0214 Submitted 4 Feb 2026 0m away

    Variation of conditions 2 (Approved Plans), 4 (CEMP), 5 (Tree Protection), 7 (Noise Impact Assessment), 10 (Surface Water Drainage), 12 (Fire Pollutants Control), 13 (Soft Landscaping), 15 (LEMP), 16 (EMMP), 18 (External Lighting) and removal of Condition 6(i) (Highway condition Survey) in its entirety for Planning Permission PA/2022/2544 "The laying out of a battery storage facility, intermediate substation, water storage tank, cabling, fencing, access tracks and associated drainage infrastructure on field to west of National Grid Sellindge Converter Substation"; to allow for changes to layout and alternative technology to be installed.

    Granted Amendments Trees 75 docs

In Ashford

  • PA/2026/0855 Decided

    3, Steeds Close, Kingsnorth, TN26 1NF

    Lawful Development Certificate - Proposed single storey rear extension , rear facing first floor dormer and front roof lights.

    11 May 2026 Lawful development
  • PA/2026/0806 Decided

    14, Hayward Close, Willesborough, TN24 0JS

    Lawful Development Certificate - Proposed extension of vehicle crossover and associated hardstanding.

    5 May 2026 Lawful development
  • PA/2026/0719 Withdrawn

    8, Old Orchard, Singleton, TN23 4PY

    Lawful development certificate - proposed - construction of an outbuilding for use as a dog grooming business

    20 Apr 2026 Lawful development
  • PA/2026/1207 Decided

    Bryn Heulog, Magpie Hall Road, Kingsnorth, TN26 1HG

    Lawful Development Certificate - Proposed - Single storey side extension

    7 Jul 2026 Lawful development
  • PA/2026/1312 Withdrawn

    Shadow Barn, Brook Street, Woodchurch, TN26 3SN

    Lawful Development Certificate - Proposed - Erection of 2 bay garage following the demolition of the existing car barn

    23 Jul 2026 Lawful development