Planning application
Barmolloch Kilmichael Glen Lochgilphead Argyll And Bute PA31 8RJ
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Erection of polytunnel
As published by the council, reference 24/01479/PNAGRI
Application record
- Reference
- 24/01479/PNAGRI
- Type
- Prior Notif. AGRICULTURAL works
- Status
- Awaiting decision
- Decision
- Granted As published: Prior Approval is NOT Required
- Received
- 13 Aug 2024
- Validated
- 27 Aug 2024
- Decided
- 11 Sep 2024
- Ward
- Mid Argyll
- Parish
- Dunadd Community Council
- Decision by
- Local Delegated Decision
- Postcode
- PA31 8RJ
Site history
Applications at this address on the Argyll and Bute register
This site has had 4 applications since 2022: 2 approved, 0 refused.
-
23/02253/PP Granted
Barmolloch Kilmichael Glen Lochgilphead Argyll And Bute PA31 8RJ
Proposed re-siting of therapy hut for use associated with the treatment rooms and upgrading of existing access and parking area
-
23/01044/PP Withdrawn
Barmolloch Kilmichael Glen Lochgilphead Argyll And Bute PA31 8RJ
Erection of therapy treatment hut (retrospective)
-
22/01247/PP Withdrawn
Barmolloch Kilmichael Glen Lochgilphead Argyll And Bute PA31 8RJ
Erection of non-residential therapy hut (retrospective)
Timeline
Dates from the published record
-
13 Aug 2024
Received by Argyll and Bute
-
27 Aug 2024
Validated
Checked as complete and ready for consideration.
-
11 Sep 2024
Decision issued: Prior Approval is NOT Required
-
6 Sep 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
Architectural Illustration Agent, an architecture practice
2 applications on PlanIndex
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
12 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Argyll and Bute granted permission on 11 September 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About less common application types
This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Barmolloch Kilmichael Glen Lochgilphead Argyll And Bute PA31 8RJ
Erection of non-residential therapy hut (retrospective)
Withdrawn Full applications 37 docs -
Barmolloch Kilmichael Glen Lochgilphead Argyll And Bute PA31 8RJ
Proposed re-siting of therapy hut for use associated with the treatment rooms and upgrading of existing access and parking area
Granted Full applications 50 docs -
Barmolloch Kilmichael Glen Lochgilphead Argyll And Bute PA31 8RJ
Erection of therapy treatment hut (retrospective)
Withdrawn Full applications 39 docs -
Land North East Of Barmolloch Kilmichael Glen Lochgilphead Argyll And Bute
Erection of agricultural polytunnel
Decided Other 7 docs
Other less common application types
In Argyll and Bute
-
26/01444/MIN Awaiting decision
Clachan Quarry Cairndow Argyll And Bute PA26 8BH
Section 42 application to vary condition 2 relative to planning permission reference 22/02506/MIN (Extraction of hard rock (Variation of conditions 2, 4 and 5 of planning permission reference 13/02424/MIN - to allow continued working of the hard rock quarry until 31 December 2027)) variation to wording of condition 2 to extend the duration of the development, condition 3 to update the approved restoration scheme and condition 6 to update the excavation area to reflect the proposed extension of the quarry to allow for the lateral expansion of the permitted hard rock extraction area
-
26/01264/PNAGRI Granted
Port An Truain Farm Port Ellen Isle Of Islay Argyll And Bute
Erection of agricultural shed
-
26/00885/PNAGRI Granted
Killocraw Farm Bellochantuy Argyll And Bute PA28 6QE
Erection of agricultural building
-
26/01220/PNELEC Decided
Land At Strone Farm Minard Argyll And Bute
24 New poles from existing line to connect the 2 new transmission substation buildings
-
26/01138/ELCNOT Awaiting decision
Land At Colintraive Argyll And Bute
Installation of a new 33kV overhead spur