Proposal

24 New poles from existing line to connect the 2 new transmission substation buildings

As published by the council, reference 26/01220/PNELEC

Timeline

Dates from the published record

  1. 15 Jul 2026

    Received by Argyll and Bute

  2. 28 Jul 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.

What happens while it is decided

The process from here

This application is with Argyll and Bute for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.

The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.

About other applications

How this application type works

This application sits outside the common categories, which can include county matters such as minerals and waste, works by statutory undertakers, demolition notifications and other less frequent procedures. The council record linked below sets out the specific procedure that applies, and the description above is taken directly from the published register.

More on other applications in our guide

Nearby applications

Within 500 metres

  • 26/01220/PAELEC Awaiting decision

    Land At Strone Farm Minard Argyll And Bute

    24 New poles from existing line to connect the 2 new transmission substation buildings

    21 Jul 2026 113m away Prior approval
  • 26/00810/SCREEN Awaiting decision

    SSE Crarae Substation Minard Argyll And Bute PA32 8YF

    Screening Opinion for proposed 33kV overhead line spur transmission DNO connections

    8 May 2026 278m away Outline

In Argyll and Bute

  • 26/01138/ELCNOT Awaiting decision

    Land At Colintraive Argyll And Bute

    Installation of a new 33kV overhead spur

    2 Jul 2026 Other
  • 26/00995/ELCNOT Awaiting decision

    Land West Of Clachan Farm Kilninver Argyll And Bute

    Installation of 11kV overhead line spur

    10 Jun 2026 Other
  • 26/00958/ELCNOT Decided

    Land At Clachaig Glen Clachaig Argyll And Bute

    Installation of 33kV overhead line

    4 Jun 2026 Other
  • 26/00939/PNELEC Awaiting decision

    Crossaig South Sub Station To High Constellation Wind Farm Skipness Argyll And Bute

    Installation of underground cable connecting Crossaig South Substation to High Constellation Project

    2 Jun 2026 Other
  • 26/00885/PNAGRI Awaiting decision

    Killocraw Farm Bellochantuy Argyll And Bute PA28 6QE

    Erection of agricultural building

    25 May 2026 Other