Lands at Existing NI Water Clanbrassil WwPS, Farmhill Road, Holywood, BT18 0AD (circa 40metres SW of 1a Clanbrassil Terrace, Holywood)

Granted Ards and North Down Discharge of Condition

Proposal

Discharge of condition 2 of previously approved application LA06/2024.0665/F which states :- A final Construction Environmental Management Plan (CEMP) must be submitted to and agreed in writing by the Council, prior to the commencement of the development hereby approved. The CEMP must include potential pollution sources and pathways and all pollution prevention measures detailed in the Outline CEMP (AG Wilson – Aug 2023) and incorporate the recommendations of WMU in its consultation response dated 25/10/24. The approved final CEMP shall be adhered in full, unless otherwise agreed in writing by the Council. Reason: To ensure the project will not have an adverse effect on the integrity of any European site. 1) Cover Letter 2) Documents A through J (including J1 through J34)

As published by the council, reference LA06/2026/0434/DC

Timeline

Dates from the published record

  1. 15 May 2026

    Received by Ards and North Down

  2. 29 Jul 2026

    Added to PlanIndex

What a grant of permission means

The process from here

Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.

Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.

About conditions applications

How this application type works

This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.

More on conditions applications in our guide

Nearby applications

Within 500 metres

  • 3 Clanbrassil Terrace, Cultra, Holywood, BT18 0AP

    Demolition of lean-to boiler store, block up gable window and erection of end townhouse (Amended/Additonal documents)

    22 Apr 2026 64m away Full applications
  • 3 Clanbrassil Terrace, Cultra, Holywood, BT18 0AP

    Demolition of lean-to boiler store, block up gable window and erection of end townhouse (Amended/Additonal documents)

    22 Apr 2026 64m away Heritage and listed buildings
  • 5 Tarawood, Holywood, BT18 0HS

    Non-material change to previous approval LA06/2023/2406/F to include omission of 1no. window on northwest elevation, reduction in height of 3no. windows on northwest elevation and relocation of garden room.

    23 Jun 2026 218m away Amendments
  • 5 Tarawood, Holywood, BT18 0HS

    Discharge of Condition 7 of previously approved application LA06/2023/2406/F which states: - DETAILED LANDSCAPE ARCHITECTS PLAN A detailed landscaping and boundary treatment scheme shall be submitted to the Council for approval prior to the commencement of development. Such a scheme shall provide for species, siting and planting. It shall include indications of all existing trees and hedgerows on the land together with details of any to be retained and measures for their protection during the course of development. The landscaping shall be carried out as approved and completed during the first available planting season following the occupation of the dwelling hereby approved and shall be permanently retained thereafter Please find attached Landscape architects drawings and supporting statement in relation to the discharge of Condition 7.

    14 Nov 2025 218m away Conditions
  • 5 Tarawood, Holywood, BT18 0HS

    Non-material change to approval LA06/2023/2406/F to include: omit open fire and chimney, raise the sills of the kitchen window & adjacent living room window to the south-east elevation, add brick base detail to the window located under the rear covered terrace detail, raise the window sill on the north-west elevation and reduce the length of glazing to the north-west elevation of the garden room and addition of rooflight over "master snug".

    25 Jan 2026 218m away Amendments
  • LA06/2026/0240/F Awaiting decision

    15 Clanbrassil Road Holywood BT18 0AR

    Erection of garage & carport

    20 Mar 2026 253m away Full applications

In Ards and North Down

  • Lands to the rear of 23-61 Castle Street, Comber, BT23 5EA

    Discharge of Condition 6 of previously approved application LA06/2021/1220/F which states - Prior to the occupation of the proposed development, a Verification Report shall be submitted to and agreed in writing by the Council. This report shall demonstrate that the remediation measures outlined in the Pentland Macdonald report; Contamination Assessment and remediation strategy, Castle Lane, Comber referenced PM19- 1137 and dated December 20219 have been implemented. The Verification Report shall demonstrate the successful completion of remediation works and that the site is now fit for end-use (Residential with Plant Uptake). It must demonstrate that the identified potential pollutant linkages are effectively broken. The Verification Report shall be in accordance with current guidance and best practice. In particular, this Verification Report must demonstrate that: • The final site layout including areas of hardstandlng, gardens and soft landscaped areas are as specified in the Site Plan Proposed Drawing No. 03A. • The emplacement of capping layers across gardens and landscaped areas is as specified: In garden areas- 1m capping layer comprising a capillary break layer of a minimum of 300mm of granular material; overlain by 700mm of clean subsoil and topsoil and in soft landscaped areas- the emplacement of a 0.5m thick capping layer of glean gravel/ subsoil topsoil. All material used in the capping layers must be demonstrably proven suitable for use. • Gas protection measures have been installed in line with a Characteristic Situation 2 scenario which attain a gas protection score of 3.5 (Table 4, B88485) and shall include two or more of the following measures: • Concrete floor slabs; • A proprietary gas resistant membrane installed across the entire footprint of the buildings; • A passively ventilated under floor void. The verification of the gas protection measures shall follow CIRIA C735 Good Practice on the testing and verification of protection systems for buildings against hazardous ground gases. Information Submitted: Verification Report

    11 Jun 2026 Conditions
  • LA06/2026/0656/DC Awaiting decision

    Lands to and South of Nos 37-77 Court Street and Nos 1-11 Canal Row, situated within Bawn Wall and bounded by the Canal, Newtownards

    Discharge of condition 15 of planning approval LA06/2023/2434/F Which States: "On completion of the remediation and prior to the occupation of any dwelling hereby approved, the applicant shall provide to the Council, for approval in writing, a Verification Report. This report shall demonstrate that the remediation measures outlined in the report titled; ‘Contaminated Land Assessment (Phase 1 PRA, Phase 2 GQRA and Outline Remediation Strategy) Lands within the Bawn Wall, Newtownards, referenced P3098-1 and dated November 2023, have been fully implemented. This report shall demonstrate the successful completion of remediation works and demonstrate that the site is now fit for end-use and include details of: • Capping system • The methodology and programme of the capping system • Photographs and records of any excavation works within the source area including photographs showing depths to accommodate the capping layer • Photographs of the clean material being used and placed on the source area, also showing depths being placed • Records and photographs showing the depth of the capping system as required • Details of the materials that were used for the capping system along with laboratory certificates and results which confirm that the materials are suitable for use."

    20 Jul 2026 Conditions
  • Lands to the rear of Nos. 23-61 Castle Street, Comber, BT23 5EA

    Discharge of Condition 12 of previously approved application LA06/2021/1220/F which states:- No residential units shall be occupied until a Landscape Management and Maintenance Plan has been submitted to and approved by the Council in writing. The plan shall set out the period of the plan, long term objectives, management responsibilities, performance measures and maintenance schedules for all areas of landscaping and open space. The landscape management plan shall be carried out as approved in perpetuity. Landscape Management & Maintenance Plan Condition and Discharge of Condition 13. which states:- The long term management and maintenance of the open space, as indicated in blue on Drawing No. 19 shall be undertaken by a management company commissioned by the developer. Details of the arrangements to be put in place to establish the management company and details of the alternative measures which will take effect in the event that the management arrangements break down, must be submitted to and agreed in writing with the Council prior to the occupation of any part of the development hereby permitted Radius Housing letter

    11 Jun 2026 Conditions
  • Lands to the NW of Kiltonga Industrial Estate SW of Belfast Road and South of Milecross Road Newtownards

    Discharge of Condition 20 of previously approved application LA06/2021/1476/F which states:- Prior to the occupation of any dwelling, details of the proposed phased implementation of hard and soft landscaping works must be submitted to and agreed in writing by the Council. The hard and soft landscaping works shall be implemented in accordance with the details and timings agreed in the approved phasing plan. Phase plan to show when we plan to have landscaped areas completed

    10 Jun 2026 Conditions
  • LA06/2026/0645/DC Awaiting decision

    Lands at 21 Bridge Road South Helen's Bay

    Discharge of Condition 13 of previously approved application LA06/2022/0701/F which states: Prior to any development works commencing on site, the applicant shall submit to the Council for approval in writing an updated Contaminated Land Risk Assessment that has considered and incorporated all available site investigations, data and assessments conducted on this site, and all current and previous correspondence issued by the Environmental Health, Protection and Development Service and the Northern Ireland Environment Agency in relation to land contamination matters present on this site. Reason: In the interests of public health to ensure the site is suitable for use.

    15 Jul 2026 Conditions