Planning application
1 and 2 Martello Terrace, Holywood, BT18 9BE
Works: Demolition
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Discharge of Condition 2 of previously approved application LA06/2024/0806/F which states - No work shall commence on site until a demolition method statement, detailing how the demolitions will be carried out to, and around, the listed buildings without adversely affecting its structural stability and without damaging the historic fabric proposed for retention, has been submitted to and agreed in writing with the Council, and all work shall conform to the agreed method statement. Submission of required demolition method statement.
As published by the council, reference LA06/2026/0042/DC
Application record
- Reference
- LA06/2026/0042/DC
- Type
- Discharge of Condition
- Status
- Determined
- Decision
- Granted As published: Condition Partially Discharged
- Received
- 19 Jan 2026
- Validated
- 19 Jan 2026
- Decided
- 8 May 2026
- Ward
- Holywood
- Postcode
- BT18 9BE
Site history
Applications at this address on the Ards and North Down register
This site has had 2 applications since 2026: 2 approved, 0 refused.
-
LA06/2026/0043/DC Granted
1 and 2 Martello Terrace, Holywood, BT18 9BE
Discharge of Condition 2 of previously approved application LA06/2024/0808/LBC which states - No work shall commence on site until a demolition method statement, detailing how the demolitions will be carried out to, and around, the listed buildings without adversely affecting its structural stability and without damaging the historic fabric proposed for retention, has been submitted to and agreed in writing with the Council, and all work shall conform to the agreed method statement. Submission of required demolition method statement.
Timeline
Dates from the published record
-
19 Jan 2026
Received by Ards and North Down
-
8 May 2026
Decision issued: Condition Partially Discharged
-
29 Jul 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
Des Ewing Residential Architects Agent, an architecture practice
17 applications on PlanIndex · across 6 councils · 100% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
6 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Ards and North Down granted permission on 8 May 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
1 and 2 Martello Terrace, Holywood, BT18 9BE
Discharge of Condition 2 of previously approved application LA06/2024/0808/LBC which states - No work shall commence on site until a demolition method statement, detailing how the demolitions will be carried out to, and around, the listed buildings without adversely affecting its structural stability and without damaging the historic fabric proposed for retention, has been submitted to and agreed in writing with the Council, and all work shall conform to the agreed method statement. Submission of required demolition method statement.
Granted Conditions Demolition 7 docs -
4 Tudor Park Holywood BT18 0NX
96% historically approved · decision due ~13 Oct
Demolition and replacement of first floor internal solid wall with a timber and plaster-boarded stud wall. Levelling of existing floor on both sides of replacement wall and redecoration and reinstatement of existing decorative feature.
Awaiting decision Heritage and listed buildings Demolition 6 docs -
9 Bangor Road Holywood BT18 0NU
Demolition of entrance pillars/gates, studio/garage, entrance portico & garden office
Granted Heritage and listed buildings Demolition 11 docs -
9 Bangor Road Holywood BT18 0NU
Demolition of existing garage/studio & entrance gates & pillars. Replacement garage & private art studio & office. New entrance gate & pillars to match existing with site works.
Granted Full applications Demolition 8 docs -
9 Bangor Road Holywood BT18 0NU
Demolition of existing portico. Single storey rear extension, sunroom & replacement portico with site works
Granted Full applications Extension Demolition 28 docsSmall domestic -
Site to the rear of 5 Bangor Road, Holywood, BT18 ONU
Erection of new 2 storey dwelling to rear of Ardshane House. Access via existing shared driveway (Amended Proposal)
Granted Outline 21 docsDomestic
Other condition discharge and variation applications
In Ards and North Down
-
LA06/2026/0884/DC Awaiting decision
Vacant site North of Balloo Road, West of Bangor Grammar sports pitches and to the rear of nos 1-13 Rowan Glen, Balloo Road, Bangor, BT19 7UU
Discharge of Condiition 10 of previously approved application LA06/2022/0873/F which states - Prior to the construction of the drainage network, the applicant shall submit a Drainage Assessment, compliant with Policy FLD 3 & Annex D of PPS 15, to be agreed in writing with the Council, which demonstrates the safe management of any out of sewer flooding emanating from the surface water drainage network, agreed under Article 161 under the Water and Sewerage Services Act (Northern Ireland) 2016, in a 1 in 100 year event. Reason: In order to safeguard against surface water flood risk
-
LA06/2026/0887/DC Awaiting decision
Former Juvenile Justice Services Centre site (169 Rathgael Road) and surrounding lands which lie to the north of the Rathgael Road and west of the Rathgael Road/Balloo Road/Newtownards Road roundabout junction Bangor
Discharge of Condition 9 of previously approved application LA06/2016/0596/F which states - Prior to the occupation of the proposed development, the applicant shall provide to the Council, for approval, a Verification Report. This report must demonstrate that all the measures outlined in Section 10 of the RPS report entitled Proposed Residential Development, Rathgael Road, Bangor, Remedial Strategy referenced IBR0736 and bearing the Council date stamp 17th June 2016 have been fully implemented. The Verification Report shall demonstrate the successful completion of the remediation works and that the site is now fit for end-use. It must demonstrate that the identified potential pollutant linkages are effectively broken. The Verification Report shall be in accordance with current best practice and guidance as outlined by the Environment Agency. In particular, this Verification Report must demonstrate: a) Full Details of the installation and depths of the clean cover barriers have been confirmed as per layout. b) All fuel transfer lines and all associated pipework have been traced and removed in accordance with PPG 2 Above Ground Oil Storage Tanks. All remaining soils (or base and side-walls of all excavations) have been sampled and proven suitable for the proposed end-use. c) The hotspots of heavy metal and hydrocarbon contamination have been removed by excavation to a depth of 0.5m below the depth of the exceedance. All remaining soils (or base and side-walls of all excavations) have been sampled and demonstrably proven suitable for the proposed end-use. d) All imported soil brought on to the site has been accompanied by traceability documentation and has been demonstrably proven to be suitable for the end use. Reason: In the interests of living conditions of residents of the proposed development. Remedial Verification Report
-
LA06/2026/0879/DC Awaiting decision
Royal Hotel and Windsor Bar, 22-28 Quay Street, Bangor, BT20 5ED
Discharge of Condition 6 of previously approved application LA06/2021/1477/F which states - Prior to the construction of the drainage network, a Drainage Assessment, compliant with FLD 3 & Annex D of PPS 15, shall be submitted to and agreed in writing by the Council which demonstrates the safe management of any out of sewer flooding emanating from the surface water drainage network, in a 1 in 100 year event with an additional allowance for climate change. Reason: To safeguard against flood risk to the development and from the development to elsewhere. Drainage Assessment produced by Design ID ref 19053-DID-ZZ-XX-RP-0002
-
LA06/2026/0878/DC Awaiting decision
Royal Hotel and Windsor Bar, 22-28 Quay Street, Bangor, T20 5ED
Discharge of Condition 5 of previously approved application LA06/2021/1477/F which states - No development shall take place on-site until the method of sewage disposal has been agreed in writing with Northern Ireland Water (NIW) or a consent to discharge has been granted under the terms of the Water (NI) Order 1999. Reason: To ensure there will be no adverse impact on the environment. NI Water agreement
-
LA06/2026/0873/DC Awaiting decision
Lands South of 37-77 Court Street and 1-11 Canal Row, situated within Bawn Wall and bounded by the canal, Newtowards
Discharge of Condition 15 of previously approved application LA06/2023/2434/F which states - On completion of the remediation and prior to the occupation of any dwelling hereby approved, the applicant shall provide to the Council, for approval in writing, a Verification Report. This report shall demonstrate that the remediation measures outlined in the report titled; ‘Contaminated Land Assessment (Phase 1 PRA, Phase 2 GQRA and Outline Remediation Strategy) Lands within the Bawn Wall, Newtownards, referenced P3098-1 and dated November 2023, have been fully implemented. This report shall demonstrate the successful completion of remediation works and demonstrate that the site is now fit for end-use and include details of: • Capping system • The methodology and programme of the capping system • Photographs and records of any excavation works within the source area including photographs showing depths to accommodate the capping layer • Photographs of the clean material being used and placed on the source area, also showing depths being placed • Records and photographs showing the depth of the capping system as required • Details of the materials that were used for the capping system along with laboratory certificates and results which confirm that the materials are suitable for use. Reason: Protection of human health. VERIFICATION REPORT FOR PHASE 5 (UNITS 1-6 AND 34-41)