Planning application
On lands to the South and East of Ulster Flying Club along the Southern side of the A20 Portaferry Road along existing pathways to the South and West of the all-weather pitches at Londonderry Park and along the Southern bank of the canal towards Georges Street Newtownards.
Works: Demolition
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Discharge of condition 2,3, 4, 5 & 6 of planning approval LA06/2019/0544/F which states '2. The mitigation measures outlined in the approved Outline Construction Environmental Management Plan submitted by Aecom dated July 2021 shall be fully implemented during the construction phase of the development to the satisfaction of the council. 3. The applicant must refer and adhere to (and the final CEMP must reflect) the precepts in the following published pollution prevention documents: - PPG 1: Understanding your environmental responsibilities -GPP 2: Above ground oil storage tanks - GPP 5: Works and maintenance in or near water - PPG 6: Working at construction and demolition sites - PPG 7: Safe storage - The safe operation of refuelling facilities - GPP 21: Pollution incident response planning - PPG 22: Incident response - dealing with spills - PPG 26: Safe storage - drums and intermediate bulk containers 4. The final CEMP should be submitted to and approved by the council in writing and should contain a method of works for the site where the bridge is being replaced. 5. Further detail shall be included in the final CEMP regarding the collection, control and treatment of surface water discharge during the construction phase. 6. Direct reference to the Control of Pollution (oil Storage) Regulations (Northern Ireland) 2010 shall be made in the final CEMP with details of how the activities will comply with the oil storage regulations.
As published by the council, reference LA06/2024/0759/DC
Application record
- Reference
- LA06/2024/0759/DC
- Type
- Discharge of Condition
- Status
- Determined
- Decision
- Granted As published: Condition Partially Discharged
- Received
- 2 Sep 2024
- Validated
- 2 Sep 2024
- Decided
- 7 Nov 2024
- Ward
- Gregstown
Timeline
Dates from the published record
-
2 Sep 2024
Received by Ards and North Down
-
7 Nov 2024
Decision issued: Condition Partially Discharged
-
27 Aug 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
Charles Brand Group Limited Agent, registered in Belfast
Active · incorporated 2013 · Belfast
3 applications on PlanIndex
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
8 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Ards and North Down granted permission on 7 November 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
South Eastern Boundary of 45 Portaferry Road, Newtownards, BT23 8NN
Free standing traditional 48 sheet advertisement hoarding
Granted Advertising 17 docs -
-
39 Portaferry Road, Newtownards, BT23 8NN
Retention of change of use from sui generis (car sales) to retail (bulky electrical goods), access, parking and ancillary site works
Granted Full applications 18 docs -
Kia (Downeys), 39 Portaferry Road, Newtownards, BT23 8NN
4 Illuminated shop signs, 1 illuminated totem sign, 1 Entrance Gate sign
Granted Advertising 16 docs -
33 Lenamore Park, Newtownards, BT23 8NL
Single storey rear extension with level access.
Granted Full applications Extension 9 docsSmall domestic -
151 UPPER GREENWELL STREET CORPORATION NORTH NEWTOWNARDS DOWN BT23 8LY
Rear extension, level access to the side and stepped access to rear to facilitate disabled person
Granted Full applications Extension 5 docs
Other condition discharge and variation applications
In Ards and North Down
-
LA06/2026/0884/DC Awaiting decision
Vacant site North of Balloo Road, West of Bangor Grammar sports pitches and to the rear of nos 1-13 Rowan Glen, Balloo Road, Bangor, BT19 7UU
Discharge of Condiition 10 of previously approved application LA06/2022/0873/F which states - Prior to the construction of the drainage network, the applicant shall submit a Drainage Assessment, compliant with Policy FLD 3 & Annex D of PPS 15, to be agreed in writing with the Council, which demonstrates the safe management of any out of sewer flooding emanating from the surface water drainage network, agreed under Article 161 under the Water and Sewerage Services Act (Northern Ireland) 2016, in a 1 in 100 year event. Reason: In order to safeguard against surface water flood risk
-
LA06/2026/0887/DC Awaiting decision
Former Juvenile Justice Services Centre site (169 Rathgael Road) and surrounding lands which lie to the north of the Rathgael Road and west of the Rathgael Road/Balloo Road/Newtownards Road roundabout junction Bangor
Discharge of Condition 9 of previously approved application LA06/2016/0596/F which states - Prior to the occupation of the proposed development, the applicant shall provide to the Council, for approval, a Verification Report. This report must demonstrate that all the measures outlined in Section 10 of the RPS report entitled Proposed Residential Development, Rathgael Road, Bangor, Remedial Strategy referenced IBR0736 and bearing the Council date stamp 17th June 2016 have been fully implemented. The Verification Report shall demonstrate the successful completion of the remediation works and that the site is now fit for end-use. It must demonstrate that the identified potential pollutant linkages are effectively broken. The Verification Report shall be in accordance with current best practice and guidance as outlined by the Environment Agency. In particular, this Verification Report must demonstrate: a) Full Details of the installation and depths of the clean cover barriers have been confirmed as per layout. b) All fuel transfer lines and all associated pipework have been traced and removed in accordance with PPG 2 Above Ground Oil Storage Tanks. All remaining soils (or base and side-walls of all excavations) have been sampled and proven suitable for the proposed end-use. c) The hotspots of heavy metal and hydrocarbon contamination have been removed by excavation to a depth of 0.5m below the depth of the exceedance. All remaining soils (or base and side-walls of all excavations) have been sampled and demonstrably proven suitable for the proposed end-use. d) All imported soil brought on to the site has been accompanied by traceability documentation and has been demonstrably proven to be suitable for the end use. Reason: In the interests of living conditions of residents of the proposed development. Remedial Verification Report
-
LA06/2026/0879/DC Awaiting decision
Royal Hotel and Windsor Bar, 22-28 Quay Street, Bangor, BT20 5ED
Discharge of Condition 6 of previously approved application LA06/2021/1477/F which states - Prior to the construction of the drainage network, a Drainage Assessment, compliant with FLD 3 & Annex D of PPS 15, shall be submitted to and agreed in writing by the Council which demonstrates the safe management of any out of sewer flooding emanating from the surface water drainage network, in a 1 in 100 year event with an additional allowance for climate change. Reason: To safeguard against flood risk to the development and from the development to elsewhere. Drainage Assessment produced by Design ID ref 19053-DID-ZZ-XX-RP-0002
-
LA06/2026/0878/DC Awaiting decision
Royal Hotel and Windsor Bar, 22-28 Quay Street, Bangor, T20 5ED
Discharge of Condition 5 of previously approved application LA06/2021/1477/F which states - No development shall take place on-site until the method of sewage disposal has been agreed in writing with Northern Ireland Water (NIW) or a consent to discharge has been granted under the terms of the Water (NI) Order 1999. Reason: To ensure there will be no adverse impact on the environment. NI Water agreement
-
LA06/2026/0873/DC Awaiting decision
Lands South of 37-77 Court Street and 1-11 Canal Row, situated within Bawn Wall and bounded by the canal, Newtowards
Discharge of Condition 15 of previously approved application LA06/2023/2434/F which states - On completion of the remediation and prior to the occupation of any dwelling hereby approved, the applicant shall provide to the Council, for approval in writing, a Verification Report. This report shall demonstrate that the remediation measures outlined in the report titled; ‘Contaminated Land Assessment (Phase 1 PRA, Phase 2 GQRA and Outline Remediation Strategy) Lands within the Bawn Wall, Newtownards, referenced P3098-1 and dated November 2023, have been fully implemented. This report shall demonstrate the successful completion of remediation works and demonstrate that the site is now fit for end-use and include details of: • Capping system • The methodology and programme of the capping system • Photographs and records of any excavation works within the source area including photographs showing depths to accommodate the capping layer • Photographs of the clean material being used and placed on the source area, also showing depths being placed • Records and photographs showing the depth of the capping system as required • Details of the materials that were used for the capping system along with laboratory certificates and results which confirm that the materials are suitable for use. Reason: Protection of human health. VERIFICATION REPORT FOR PHASE 5 (UNITS 1-6 AND 34-41)