Lands approx 400m north east of 60 Ballyutoag Road, Belfast, County Antrim, BT14 8SR

Awaiting decision Antrim and Newtownabbey LA03/2026/0669/S54 Section 54

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Proposed single wind turbine with 64m hub height and 71 m rotor diameter with associated ancillary development including construction of section of new laneway and crane hardstanding, on site sub station and control building, underground cables all other ancillary and associated works (Removal of Conditions 3 and 4 from approval LA03/2024/0014/F regarding submission of Radar Mitigation Scheme)

As published by the council, reference LA03/2026/0669/S54

Application record

Reference
LA03/2026/0669/S54
Type
Section 54
Status
Consultation Open
Received
15 Sep 2026
Validated
16 Sep 2026
Ward
Clady
Postcode
BT14 8SR

Timeline

Dates from the published record

  1. 15 Sep 2026

    Received by Antrim and Newtownabbey

  2. 16 Sep 2026

    Validated

    Checked as complete and ready for consideration.

  3. 24 Sep 2026

    Added to PlanIndex

  4. 28 Sep 2026

    Status changed to Consultation Open

    Previously Valid.

  5. Decision

    Awaiting decision

    Decision expected by 11 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Antrim and Newtownabbey took a median of 79 days over the applications it decided in the last year.

Documents

Plans, drawings, consultee responses and the officer's report

7 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What happens while it is decided

This application is with Antrim and Newtownabbey for determination, against a statutory target of eight weeks. Over the last year Antrim and Newtownabbey's median decision took 79 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Antrim and Newtownabbey's portal will say. Our guide explains the common types.

Nearby applications

Within 0.3 miles

  • Approximately 430m North East Of Number 60 Ballyutoag Road Belfast, County Antrim

    LA03/2023/0106/S54 Submitted 15 Feb 2023 50 yards away

    Proposed wind turbine with max hub height of 40m and max blade length of 26m to generate electricity for on site use or export to the grid, with associated access lane and switch control room (Variation of Condition 7 from approval LA03/2016/0214/F to change text from "No development shall take place" to "No above ground infrastructure (wind turbine shall be erected)

    Granted 13 docs