Planning application
Field 650M North Of Glenskinno Farm Glenskinno Montrose
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Section 36 Consultation to Angus Council for construction and operation of 120MW Craigo Glenskinno Solar Park and Battery Energy Storage System
As published by the council, reference 26/00530/S36
Application record
- Reference
- 26/00530/S36
- Status
- Awaiting decision
- Received
- 11 Sep 2026
- Validated
- 16 Sep 2026
Timeline
Dates from the published record
-
11 Sep 2026
Received by Angus
-
16 Sep 2026
Validated
Checked as complete and ready for consideration.
-
16 Sep 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 11 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Angus took a median of 65 days over the applications it decided in the last year.
What happens while it is decided
This application is with Angus for determination, against a statutory target of eight weeks. Over the last year Angus's median decision took 65 days. More in our guide to how long planning decisions take.
About this record