Proposal

Installation of solar panels, replacement of heating system and installation of air source heat pump, replacement windows and doors, installation of internal wall and ceiling insulation, installation of secondary glazing, replacement of external render with through colour thermal render with lime finish. Replacement and regrading of flat roof covering, replacement garage doors, and installation of solar panels to modern garage outbuilding.

As published by the council, reference AVA/2025/0880

Application record

Reference
AVA/2025/0880
Status
Pending Consideration
Received
24 Dec 2025
Validated
5 Jan 2026
Ward
Kilburn, Denby, Holbrook & Horsley
Decision by
Delegated
Postcode
DE56 0LU

Site history

Applications at this address on the Amber Valley register

This site has had 2 applications since 2025.

  • AVA/2025/0881 Awaiting decision

    Kilburn Hall Church Street Kilburn Belper Derbyshire DE56 0LU

    Listed building consent for installation of solar panels, replacement of heating system and installation of air source heat pump, replacement windows and doors, installation of internal wall and ceiling insulation, installation of secondary glazing, replacement of external render with through colour thermal render with lime finish.

    Submitted 24 Dec 2025

Timeline

Dates from the published record

  1. 24 Dec 2025

    Received by Amber Valley

  2. 5 Jan 2026

    Validated

    Checked as complete and ready for consideration.

  3. 22 Jul 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 2 March 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Amber Valley took a median of 57 days over the applications it decided in the last year.

Documents

Plans, drawings, consultee responses and the officer's report

42 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Amber Valley for determination, against a statutory target of eight weeks. Over the last year Amber Valley's median decision took 57 days. More in our guide to how long planning decisions take.