Craigneil Wind Farm Land To The North And North East Of Hillside Rickarton Stonehaven AB39 3SQ

Awaiting decision Aberdeenshire ENQ/2024/0640 Proposal of Application Notice

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Erection of up to 7 180m to Blade Tip Wind Turbines, Access Tracks, Hardstandings, Substation, Control Building, Met Mast, Borrow Pit, Associated Infrastructure and Temporary Construction Compound

As published by the council, reference ENQ/2024/0640

Application record

Reference
ENQ/2024/0640
Type
Proposal of Application Notice
Status
Awaiting decision
Received
1 May 2024
Validated
5 Jun 2024
Ward
Stonehaven And Lower Deeside
Parish
Stonehaven & District
Postcode
AB39 3SQ

Timeline

Dates from the published record

  1. 1 May 2024

    Received by Aberdeenshire

  2. 5 Jun 2024

    Validated

    Checked as complete and ready for consideration.

  3. 1 Sep 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 31 July 2024, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Aberdeenshire took a median of 64 days over the applications it decided in the last year.

Documents

Plans, drawings, consultee responses and the officer's report

3 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Aberdeenshire for determination, against a statutory target of eight weeks. Over the last year Aberdeenshire's median decision took 64 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Aberdeenshire's portal will say. Our guide explains the common types.

Nearby applications

Within 500 metres

  • Craigneil Hill Rickarton Stonehaven

    ENQ/2016/2225 Submitted 15 Nov 2016 182m away

    Erection of Wind Farm comprising Eleven Turbines (135m to Tip) Up to 37.95MW

    Decided 2 docs