Brownside Farm Mountblairy Banff Aberdeenshire AB45 3YD
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Formation of 35MW Solar Farm, Battery Energy Storage System (BESS) with an Installed Capacity of up to 14.9MW, Substation and Associated Infrastructure
As published by the council, reference APP/2025/0205
Application record
- Reference
- APP/2025/0205
- Type
- Full Planning Permission
- Status
- Decided
- Decision
- Granted As published: Approved
- Received
- 13 Feb 2025
- Validated
- 17 Mar 2025
- Decided
- 18 Jun 2025
- Ward
- Banff And District
- Parish
- Alvah & Forglen
- Decision by
- Committee
- Postcode
- AB45 3YD
Site history
Applications at this address on the Aberdeenshire register
This site has had 2 applications since 2024: 1 approved, 0 refused.
-
ENQ/2024/1328 Decided
Brownside Farm Mountblairy Banff Aberdeenshire AB45 3YD
Major Development of a Photovoltaic Electricity Production Facility with Capacity of up to 35MW, Together with a Battery Energy Storage System with Capacity of up to 14.9MW and Associated Infrastructure
Timeline
Dates from the published record
-
13 Feb 2025
Received by Aberdeenshire
-
17 Mar 2025
Validated
Checked as complete and ready for consideration.
-
18 Jun 2025
Decision issued: Approved
-
1 Sep 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
75 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Aberdeenshire granted permission on 18 June 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Brownside Farm Mountblairy Banff Aberdeenshire AB45 3YD
Major Development of a Photovoltaic Electricity Production Facility with Capacity of up to 35MW, Together with a Battery Energy Storage System with Capacity of up to 14.9MW and Associated Infrastructure
Decided 3 docs
Other full applications
In Aberdeenshire
-
APP/2026/1621 Awaiting decision
Base Station Tullich Invercauld Estate Pass Of Ballater Aberdeenshire
Installation Of Generator
-
APP/2026/1506 Awaiting decision
Surfside Caravan Park Harbour Road Fraserburgh AB43 9TB
Extension to Caravan Site Operating Times (March to January)
-
APP/2026/1489 Awaiting decision
3 Gean Court Balmedie AB23 8ST
Extension to Dwellinghouse and Installation of Flue
-
APP/2026/1494 Awaiting decision
18 David Mclean Drive Alford Aberdeenshire AB33 8PW
Erection of Garden Room (Retrospective)
-
APP/2026/1476 Awaiting decision
Huntly Hotel 18 The Square Huntly Aberdeenshire AB54 8BR
Alterations to Hotel Including Replacement Doors