Skip to content
PlanIndex Get alerts
Menu

Planning application

Site Adjacent To Craig Alvah Lodge Banff Aberdeenshire

Granted Aberdeenshire APP/2023/1689 Full Planning Permission

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Erection of Holiday Lodge

As published by the council, reference APP/2023/1689

Application record

Reference
APP/2023/1689
Type
Full Planning Permission
Status
Decided
Decision
Granted As published: Approved
Received
8 Sep 2023
Validated
12 Sep 2023
Decided
8 Nov 2024
Ward
Banff And District
Parish
Alvah & Forglen
Decision by
Delegated

Timeline

Dates from the published record

  1. 8 Sep 2023

    Received by Aberdeenshire

  2. 12 Sep 2023

    Validated

    Checked as complete and ready for consideration.

  3. 8 Nov 2024

    Decision issued: Approved

  4. 1 Sep 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

29 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Aberdeenshire granted permission on 8 November 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Site Adjacent To Craig Alvah Lodge Banff

    APP/2025/1894 Submitted 20 Nov 2025 100 yards away

    Change of Use of Woodland to Garden Ground and Siting of 2 Glamping Pods

    Granted Full applications 17 docs
  • Boyndie Bay To New Deer

    APP/2024/1812 Submitted 7 Nov 2024 300 yards away

    Onshore Transmission Infrastructure for Caledonia Offshore Wind Farm including Formation of Onshore Landfall Point, Laying of Underground Cables, Erection of 2 Co-Located Substations, and Associated Works to connect to the Transmission Grid

    Granted Outline 176 docs

In Aberdeenshire

  • APP/2026/1621 Awaiting decision

    Base Station Tullich Invercauld Estate Pass Of Ballater Aberdeenshire

    Installation Of Generator

    Received 25 Sep, published by the council 2 Oct 2026 Full applications
  • APP/2026/1506 Awaiting decision

    Surfside Caravan Park Harbour Road Fraserburgh AB43 9TB

    Extension to Caravan Site Operating Times (March to January)

    Received 2 Sep, published by the council 3 Sep 2026 Full applications
  • APP/2026/1489 Awaiting decision

    3 Gean Court Balmedie AB23 8ST

    Extension to Dwellinghouse and Installation of Flue

    Received 31 Aug, published by the council 2 Sep 2026 Full applications
  • APP/2026/1494 Awaiting decision

    18 David Mclean Drive Alford Aberdeenshire AB33 8PW

    Erection of Garden Room (Retrospective)

    Received 31 Aug, published by the council 3 Sep 2026 Full applications
  • APP/2026/1476 Awaiting decision

    Huntly Hotel 18 The Square Huntly Aberdeenshire AB54 8BR

    Alterations to Hotel Including Replacement Doors

    Received 28 Aug, published by the council 3 Sep 2026 Full applications