Planning application
Phase 1A Quarryline Street Chapelton Newtonhill
Works: Trees Major scheme
Read from the description, not a valuation. How we read the register
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Conditions (3) a) Levels Survey, b) Drainage Plan, c) Foul Water Drainage Connections, e) Cut and Fill Operations, f) Roads, Footpaths, Cycleways, g) Screen Walls/Fencing, h) Landscaping, j) Layout, Siting, Design and Finish, l) Waste/Recycling Collection Points, (4) Phasing Plan, (6) a) Ground Levels, b) Existing Landscape Features/Vegetation, c) Cables, Pipelines, Substations, (d) New Trees, Shrubs, Hedges, e) Schedule of Plants, f) Hard Landscaping, g) Existing Trees/Shrubs/Hedges to be Removed, j) Programme and Maintenance of Proposed Landscaping, 7(a-f) Drainage, (8) Street Design, (17) Construction Method Statement, (36) Waste Management Plan and (37) Environmental Management Plan of Planning Permission in Principle Reference APP/2011/3100 for New Settlement Comprising Residential (up to 4045 Dwellinghouses), Commercial, Retail and Community Facilities with Associated Landscaping, Open Space, Drainage and Roads Infrastructure and Services
As published by the council, reference APP/2019/2922
Application record
- Reference
- APP/2019/2922
- Type
- Approval of Matters Specified in Conds
- Status
- Decided
- Decision
- Granted As published: Approved
- Received
- 23 Dec 2019
- Validated
- 24 Dec 2019
- Decided
- 29 Jan 2021
- Ward
- North Kincardine
- Parish
- North Kincardine Rural
- Decision by
- Local Member Delegated
Timeline
Dates from the published record
-
23 Dec 2019
Received by Aberdeenshire
-
24 Dec 2019
Validated
Checked as complete and ready for consideration.
-
29 Jan 2021
Decision issued: Approved
-
5 Oct 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
102 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Aberdeenshire granted permission on 29 January 2021, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Phase 1A (Zero C, Plots B1 - B5) Quarryline Street Chapelton Newtonhill Aberdeenshire
Conditions 3 a) (Level and Cross Sections), c) (Connection to Existing Scottish Water) and j) (Layout, Siting, Design and Finish), 4 (Phasing), 8) (Street Design) of Planning Permission in Principle Reference APP/2011/3100 for New Settlement Comprising Residential (up to 4045 Dwellinghouses), Commercial, Retail and Community Facilities, with Associated Landscaping, Open Space, Drainage and Roads Infrastructure and Services
Granted Conditions 26 docsMajor scheme -
29 Quarryline Street Chapelton Stonehaven Aberdeenshire AB39 8BT
Painting of Shop Front
Granted Full applications Windows or glazing 8 docs -
29 Quarryline Street Chapelton Stonehaven Aberdeenshire AB39 8BT
Erection of Signage
Granted Advertising 6 docs -
Phase 1A, Stage 2 Retirement Village Land To West Of Chapelton Newtonhill Stonehaven
Conditions 3a (Existing and Proposed Ground/Floor Levels), 3b (Drainage Plan), 3c (Connection to Scottish Water Foul Water Drainage Network), 3e (Cut and Fill Operations), 3f (Roads, Footpaths and Cycleways), 3g (Screen Walls/Fencing), 3h (Landscaping), 3j (Layout, Siting, Design and Finish of Residential Properties), 3k (Layout, Siting, Design and Finish of Non-Residential Properties), 3l (Waste/Recycling Points), 4 (Phasing of Development), 6a (Existing and Proposed Ground Levels), 6b (Landscaping/Vegetation to be Retained), 6c (Existing and Proposed Services), 6d (Location of New Landscape Features), 6e (Schedule of Plants), 6f (Hard Landscaping Works), 6g (Landscaping to be Removed), 6h (Biodiversity Action Plan), 6i (Management Plan for Watercourse Buffer Strips), 6j (Maintenance of Landscaping), 8 (Street Design) and 25 (Energy Statement) to create retirement village, of Previously Approved Planning Application APP/2011/3100 for New Settlement Comprising Residential (up to 4045 Dwellinghouses), Commercial, Retail and Community Facilities with Associated Landscaping, Open Space, Drainage and Roads Infrastructure and Services
Granted Conditions 33 docsMajor scheme -
Site C, Tranche 1, Plots 108-115 Liddell Place Land To West Of Chapelton Newtonhill Stonehaven
Conditions 3a, b, c, e, f, g, h, j and l (Levels Survey, Drainage Plan, Foul Water Drainage Network, Cut out & Fill Operations, Details of Roads, Footpaths and Cycleways, Screen Walls/Fencing, Landscaping, Layout, Siting, and Design, Waste/Recycling Collection Points) 4 (Phasing of Development), 6 a,b,c,d,e,f,g,h,i,j (Existing and Proposed Finished Ground Levels, Existing Landscape Features to be Retained, Existing and Proposed Services, Landscaping, Schedule of Plants, Hard Landscaping, Existing Landscaping to be Removed, Biodiversity Action Plan, Management Plan, Programme for Completion and Maintenance of Landscaping), 7a, b, c, d, e, f (Inspection Regime for Offlets/Inlets, Frequency/Method for Cleaning Filter Trenches, Cutting/Weeding of Swales, Access for Future Maintenance, Planting not to be Undertaken over Perforated Pipes, Contact Parties for Factoring/Maintenance of Scheme), 8 (Street Design - Parking, Road Junctions, Visibility Splays, Gradients, Level Details, Finishing/Surfacing Materials, Crossing Points), 14 (Public Transport Strategy, 15 (Joint Condition Survey), 17 (Construction Method Statement), 19 (Site Investigation), 20 (Remediation Scheme), 21 (Badger Survey), 22 (Bat Survey), 24 (Archaeology Works), 25a, b (Energy Efficient Measures, SAP/SBEM Calculations), 27 (Soil Audit), 30 (Flood Risk Assessment), 33 (Walking and Cycling Strategy to Connection to Newtonhill and Portlethen), 36 (Site Waste Management Plan) and 37 (Site Specific Environmental Management Plan) of Planning Permission in Principle Reference APP/2011/3100 for New Settlement Comprising Residential (up to 4045 Dwellinghouses), Commercial, Retail and Community Facilities, with Associated Landscaping, Open Space, Drainage and Roads Infrastructure and Services in relation to Planning Permission APP/2011/3100 (for erection of 8 dwellinghouses)
Granted Conditions 149 docsMajor scheme -
Phase 1A Stage 2, Liddell Park And Hut Land To West Of Chapelton Newtonhill Stonehaven
Conditions 3a, b, c, e, f, g, h, k and l (Levels Survey, Drainage Plan, Foul Water Drainage Network, Cut out & Fill Operations, Details of Roads, Footpaths and Cycleways, Screen Walls/Fencing, Landscaping, Layout, Siting, and Design, Waste/Recycling Collection Points) 4 (Phasing of Development), 6 a, b,c,d,e,f,g,h,i,j, (Existing and Proposed Finished Ground Levels, Existing Landscape Features to be Retained, Existing and Proposed Services, Landscaping, Schedule of Plants, Hard Landscaping, Existing Landscaping to be Removed, Biodiversity Action Plan, Management Plan, Programme for Completion and Maintenance of Landscaping), 7a, b, c, d, e, f (Inspection Regime for Offlets/Inlets, Frequency/Method for Cleaning Filter Trenches, Cutting/Weeding of Swales, Access for Future Maintenance, Planting not to be Undertaken over Perforated Pipes, Contact Parties for Factoring/Maintenance of Scheme), 8 (Street Design - Parking, Road Junctions, Visibility Splays, Gradients, Level Details, Finishing/Surfacing Materials, Crossing Points), 14 (Public Transport Strategy, 15 (Joint Condition Survey), 17 (Construction Method Statement), 19 (Site Investigation), 20 (Remediation Scheme), 21 (Badger Survey), 22 (Bat Survey), 24 (Archaeology Works), 25a, b (Energy Efficient Measures, SAP/SBEM Calculations), 27 (Soil Audit), 30 (Flood Risk Assessment), 33 (Walking and Cycling Strategy to Connection to Newtonhill and Portlethen), 36 (Site Waste Management Plan) and 37 (Site Specific Environmental Management Plan) of Planning Permission in Principle Reference APP/2011/3100 for New Settlement Comprising Residential (up to 4045 Dwellinghouses), Commercial, Retail and Community Facilities, with Associated Landscaping, Open Space, Drainage and Roads Infrastructure and Services in relation to Planning Permission APP/2011/3100 (Phase 1a, Stage 2 - Liddell Park and Hut)
Granted Conditions 139 docsMajor scheme
Other condition discharge and variation applications
In Aberdeenshire
-
APP/2026/1059 Granted
Plots 26 & 27 Queen Elizabeth Drive South Of Pheppie Burn Chapelton Stonehaven
Condition 3J (Layout, Siting, Design and Finish) of Planning Permission in Principle Reference APP/2011/3100 for New Settlement Comprising Residential (Up to 4045 Dwellinghouses), Commercial, Retail and Community Facilities with Associated Landscaping, Open Space, Drainage and Roads Infrastructure and Services
-
APP/2026/0959 Granted
Land At Backhill Lenabo Kinknockie Mintlaw Aberdeenshire AB42 5BA
Condition 2(a) Layout, Siting, (b) External Appearance, Finishing Materials, (c) Landscaping, (d) Levels, Cross Sections, Finished Floor Levels, (e) Drainage, (f) Means of Access, Visibility Splays, (g) Car Parking, Vehicle Turning Area, (h) Biodiversity Enhancement Plan of Planning Permission Reference APP/2024/0870 for Erection of Dwellinghouse
-
APP/2026/1097 Granted
Stables At Glencommon Farm Bridge Of Canny Banchory AB31 4FN
Condition 2a (Layout & Siting), 2b (External Appearance), 2c (Levels), 2d (Disposal of Foul & Surface Water), 2e (Visibility Splays), 2f (Parking/Vehicle Turning Area/Lay-by), 2g (Refuse Uplift), 2h (Biodiversity & Habitat Enhancement) of Planning Permission in Principle Reference APP/2024/1247 for Erection of Dwellinghouse
-
APP/2026/1341 Awaiting decision
Kirkton Heights Phase 2 Development Boothby Road Fraserburgh Aberdeenshire
Discharge of Planning Obligation (Waste and Recylcing) of APP/2025/1683 for Erection of 175 Dwellinghouses and Associated Infrastructure
-
APP/2026/1340 Awaiting decision
Kirkton Heights Phase 2 Development Boothby Road Fraserburgh Aberdeenshire
Discharge of Planning Obligation (Sports and Recreation) of APP/2025/1683 for Erection of 175 Dwellinghouses and Associated Infrastructure