Decision times · South West
How long planning decisions take in Wiltshire
50 days. Ranked 31 of 343.
In the year to September 2026, the median planning application decided by Wiltshire took 50 days from submission to decision — 6 days inside the eight week target. That is measured across 5,787 decisions where the council published both dates.
How Wiltshire compares
Year to September 2026
Wiltshire decides faster than the country as a whole: 6 days below the national median of 56 days. Nationally 55% of applications are decided within eight weeks; here it is 67%.
The average here is 65 days, longer than the median because a handful of applications take very much longer than the rest. For planning around, 112 days is the more useful number: nine applications in ten were decided inside it.
-
Within eight weeks the statutory target 3,889 67%
-
Eight to thirteen weeks the major development band 1,058 18%
-
Over thirteen weeks commonly an agreed extension 840 15%
The last few years
Each row is a full twelve months of decisions, ending in the quarter shown
Rolling twelve month windows overlap by nine months, so this reads as a trend rather than as four separate quarters. Only windows our records reach far enough back to measure in full are listed.
| Twelve months to | Median days | UK rank |
|---|---|---|
| September 2026 | 50 | 31 of 343 |
| June 2026 | 49 | 39 of 328 |
| March 2026 | 43 | 27 of 243 |
| December 2025 | 42 | 38 of 236 |
| September 2025 | 44 | 43 of 324 |
| June 2025 | 43 | 10 of 313 |
| March 2025 | 43 | 10 of 315 |
| December 2024 | 43 | 12 of 319 |
Against the same twelve months a year earlier, when the median was 44 days, Wiltshire has moved up 12 places in the table.
By type of application
Year to September 2026 · types with at least ten decisions
The headline median mixes every kind of application together. A householder extension and an outline application for a housing site are not the same job, and the difference between them is usually larger than the difference between two councils.
-
Prior approval 262 decided 28 days
-
Trees 1,738 decided 38 days
-
Other 23 decided 45 days
-
Lawful development 208 decided 50 days
-
Conditions 515 decided 53 days
-
Outline 81 decided 55 days
-
Advertising 59 decided 56 days
-
Amendments 204 decided 56 days
-
Heritage and listed buildings 542 decided 56 days
-
Householder 1,369 decided 56 days
-
Full applications 725 decided 79 days
-
Reserved matters 14 decided 217 days
What Wiltshire decides
Year to September 2026
Wiltshire issued 5,787 decisions in the year to September 2026. Of the clear-cut outcomes, 95% were approvals: 5,057 granted against 277 refused. Split decisions, withdrawals and other outcomes sit outside that percentage rather than being counted as either.
Speed and approval rate are separate things. A council that refuses quickly is not doing the same job as one that negotiates an approval slowly, and neither figure alone says which served the applicant better.
Common questions
How long does a planning decision take in Wiltshire?
The median planning application decided by Wiltshire in the year to September 2026 took 50 days from submission to decision, 6 days inside the eight week target. That is measured across 5,787 decisions where the council published both a start date and a decision date. It ranks 31 of 343 UK councils on decision speed.
Does Wiltshire meet the eight week target?
67% of the 5,787 decisions Wiltshire made in the year to September 2026 came within eight weeks of the application being received, and 85% within thirteen weeks. Nine in ten were decided within 112 days. Councils can agree an extension of time with an applicant, so a decision past eight weeks is not necessarily a missed deadline.
Is Wiltshire faster or slower than average?
Wiltshire is faster than average: its median of 50 days is 6 days below the national median of 56 days.
Is Wiltshire getting faster or slower?
Against the same twelve month window a year earlier, when its median was 44 days, Wiltshire has moved up 12 places in the table. Its median has risen by 6 days.
What proportion of applications does Wiltshire approve?
95% of the clear-cut outcomes Wiltshire issued in the year to September 2026 were approvals: 5,057 granted against 277 refused. Split decisions, withdrawals and other outcomes are excluded from that percentage.
Cite these figures
Click the text to select the whole citation.
Wiltshire planning decision times, year to September 2026: median 50 days from application to decision (6 days inside the eight week target), across 5,787 decisions with both dates published. 67% were decided within the eight week statutory target, 85% within thirteen weeks; nine in ten within 112 days. Ranked 31 of 343 UK councils on decision speed (national median 56 days). 95% of clear-cut outcomes were approvals. Source: PlanIndex, planindex.co.uk.