Decision times · North West

How long planning decisions take in Rossendale

84 days. Ranked 314 of 343.

In the year to September 2026, the median planning application decided by Rossendale took 84 days from submission to decision — 28 days beyond the eight week target. That is measured across 121 decisions where the council published both dates.

84 days
Median decision 28 days beyond the eight week target
314 of 343
UK rank down 35 places in a year
21%
Within eight weeks 56% within thirteen
231 days
Nine in ten decided by The wait to budget for

How Rossendale compares

Year to September 2026

Rossendale takes longer than the country as a whole: 28 days above the national median of 56 days. Nationally 55% of applications are decided within eight weeks; here it is 21%.

The average here is 114 days, longer than the median because a handful of applications take very much longer than the rest. For planning around, 231 days is the more useful number: nine applications in ten were decided inside it.

  1. Within eight weeks the statutory target 26 21%
  2. Eight to thirteen weeks the major development band 42 35%
  3. Over thirteen weeks commonly an agreed extension 53 44%

The last few years

Each row is a full twelve months of decisions, ending in the quarter shown

Rolling twelve month windows overlap by nine months, so this reads as a trend rather than as four separate quarters. Only windows our records reach far enough back to measure in full are listed.

Rossendale: median days from application to decision, by rolling twelve month window. Source: PlanIndex, planindex.co.uk.
Twelve months to Median days UK rank
September 2026 84 314 of 343
June 2026 79 305 of 328
September 2025 70 279 of 324
June 2025 66 237 of 313
March 2025 66 244 of 315
December 2024 66 250 of 319

Against the same twelve months a year earlier, when the median was 70 days, Rossendale has moved down 35 places in the table.

By type of application

Year to September 2026 · types with at least ten decisions

The headline median mixes every kind of application together. A householder extension and an outline application for a housing site are not the same job, and the difference between them is usually larger than the difference between two councils.

  1. Householder 25 decided 84 days
  2. Conditions 31 decided 100 days
  3. Full applications 30 decided 101 days

How these types compare nationally

What Rossendale decides

Year to September 2026

Rossendale issued 121 decisions in the year to September 2026. Of the clear-cut outcomes, 88% were approvals: 90 granted against 12 refused. Split decisions, withdrawals and other outcomes sit outside that percentage rather than being counted as either.

Speed and approval rate are separate things. A council that refuses quickly is not doing the same job as one that negotiates an approval slowly, and neither figure alone says which served the applicant better.

Common questions

How long does a planning decision take in Rossendale?

The median planning application decided by Rossendale in the year to September 2026 took 84 days from submission to decision, 28 days beyond the eight week target. That is measured across 121 decisions where the council published both a start date and a decision date. It ranks 314 of 343 UK councils on decision speed.

Does Rossendale meet the eight week target?

21% of the 121 decisions Rossendale made in the year to September 2026 came within eight weeks of the application being received, and 56% within thirteen weeks. Nine in ten were decided within 231 days. Councils can agree an extension of time with an applicant, so a decision past eight weeks is not necessarily a missed deadline.

Is Rossendale faster or slower than average?

Rossendale is slower than average: its median of 84 days is 28 days above the national median of 56 days.

Is Rossendale getting faster or slower?

Against the same twelve month window a year earlier, when its median was 70 days, Rossendale has moved down 35 places in the table. Its median has risen by 14 days.

What proportion of applications does Rossendale approve?

88% of the clear-cut outcomes Rossendale issued in the year to September 2026 were approvals: 90 granted against 12 refused. Split decisions, withdrawals and other outcomes are excluded from that percentage.

Cite these figures

Click the text to select the whole citation.

Rossendale planning decision times, year to September 2026: median 84 days from application to decision (28 days beyond the eight week target), across 121 decisions with both dates published. 21% were decided within the eight week statutory target, 56% within thirteen weeks; nine in ten within 231 days. Ranked 314 of 343 UK councils on decision speed (national median 56 days). 88% of clear-cut outcomes were approvals. Source: PlanIndex, planindex.co.uk.