Decision times · East Midlands

How long planning decisions take in North East Derbyshire

63 days.

In the year to December 2026, the median planning application decided by North East Derbyshire took 63 days from submission to decision — 7 days beyond the eight week target. That is measured across 233 decisions where the council published both dates.

This council carries a figure but no rank

Not ranked yet: our records do not yet pass the historical coverage, monthly continuity, missing-date and refresh checks for this window. The figure above is still what the published dates say; it is left out of the league table so it cannot distort the ranking. See the methodology.

63 days
Median decision 7 days beyond the eight week target
39%
Within eight weeks 72% within thirteen
180 days
Nine in ten decided by The wait to budget for

How North East Derbyshire compares

Year to December 2026

North East Derbyshire takes longer than the country as a whole: 6 days above the national median of 57 days. Nationally 49% of applications are decided within eight weeks; here it is 39%.

The average here is 89 days, longer than the median because a handful of applications take very much longer than the rest. For planning around, 180 days is the more useful number: nine applications in ten were decided inside it.

  1. Within eight weeks the statutory target 92 39%
  2. Eight to thirteen weeks the major development band 76 33%
  3. Over thirteen weeks commonly an agreed extension 65 28%

By type of application

Year to December 2026 · types with at least ten decisions

The headline median mixes every kind of application together. A householder extension and an outline application for a housing site are not the same job, and the difference between them is usually larger than the difference between two councils.

  1. Lawful development 11 decided 41 days
  2. Trees 37 decided 54 days
  3. Householder 41 decided 60 days
  4. Conditions 62 decided 67 days
  5. Full applications 41 decided 132 days

How these types compare nationally

What North East Derbyshire decides

Year to December 2026

North East Derbyshire issued 233 decisions in the year to December 2026. Of the clear-cut outcomes, 91% were approvals: 193 granted against 19 refused. Split decisions, withdrawals and other outcomes sit outside that percentage rather than being counted as either.

Speed and approval rate are separate things. A council that refuses quickly is not doing the same job as one that negotiates an approval slowly, and neither figure alone says which served the applicant better.

Common questions

How long does a planning decision take in North East Derbyshire?

The median planning application decided by North East Derbyshire in the year to December 2026 took 63 days from submission to decision, 7 days beyond the eight week target. That is measured across 233 decisions where the council published both a start date and a decision date.

Does North East Derbyshire meet the eight week target?

39% of the 233 decisions North East Derbyshire made in the year to December 2026 came within eight weeks of the application being received, and 72% within thirteen weeks. Nine in ten were decided within 180 days. Councils can agree an extension of time with an applicant, so a decision past eight weeks is not necessarily a missed deadline.

Is North East Derbyshire faster or slower than average?

North East Derbyshire is slower than average: its median of 63 days is 6 days above the national median of 57 days.

What proportion of applications does North East Derbyshire approve?

91% of the clear-cut outcomes North East Derbyshire issued in the year to December 2026 were approvals: 193 granted against 19 refused. Split decisions, withdrawals and other outcomes are excluded from that percentage.

Cite these figures

Click the text to select the whole citation.

North East Derbyshire planning decision times, year to December 2026: median 63 days from application to decision (7 days beyond the eight week target), across 233 decisions with both dates published. 39% were decided within the eight week statutory target, 72% within thirteen weeks; nine in ten within 180 days. 91% of clear-cut outcomes were approvals. Source: PlanIndex, planindex.co.uk.

Or take the data itself: this council's history (CSV) or the full league table (CSV).

Embed these figures

Paste either snippet into your page. Click a snippet to select all of it. The credit line is part of the embed.

<script src="https://planindex.co.uk/embed/decision-times.js" data-council="north-east-derbyshire" defer></script>

If your CMS strips scripts, use the frame directly:

<iframe src="https://planindex.co.uk/embed/decision-times/north-east-derbyshire" title="Planning decision times in North East Derbyshire" width="100%" height="215" loading="lazy" frameborder="0"></iframe>
<p>Data: <a href="https://planindex.co.uk/planning-decision-times/north-east-derbyshire">Planning decision times, from PlanIndex</a></p>