Planning application
The Cocoa Works Haxby Road York YO31 8TA
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Condition 7 of 19/01509/FULM
As published by the council, reference AOD/21/00353
Application record
- Reference
- AOD/21/00353
- Type
- Approval of Details
- Status
- Awaiting decision
- Decision
- Approve Details
- Received
- 23 Dec 2021
- Validated
- 23 Dec 2021
- Decided
- 16 Feb 2022
- Ward
- Guildhall
- Parish
- Guildhall Planning Panel
- Decision by
- Delegated Decision
- Postcode
- YO31 8TA
Site history
Applications at this address on the York register
This site has had 3 applications since 2021: 3 approved, 0 refused.
-
22/00625/FUL Granted
The Cocoa Works Haxby Road York YO31 8TA
Erection of electricity substation and re-arrangement of car parking along the southern boundary with associated earthworks and landscaping
-
22/00593/NONMAT Granted
The Cocoa Works Haxby Road York YO31 8TA
Non-material amendment to permitted application 19/01509/FULM to alter location of proposed substations along northern boundary
Timeline
Dates from the published record
-
23 Dec 2021
Received by York
-
16 Feb 2022
Decision issued: Approve Details
-
6 Sep 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
Agent on file, registered in London
99 applications on PlanIndex · across 6 councils · 94% granted
Trade members see who it is, their full track record, and every application they have filed.
See who's behind itDocuments
Plans, drawings, consultee responses and the officer's report
33 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
York granted permission on 16 February 2022, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
Nuffield Health York Hospital Haxby Road York YO31 8TA
98% historically approved · decision due ~5 Oct
Fell 2no. trees in a Conservation Area
Awaiting decision Trees -
Yearsley Swimming Baths Haleys Terrace York YO31 8SB
Re-pollard 1no. tree; trim back 1no. London Plane to clear guttering - tree works in a Conservation Area
Granted Trees 2 docs -
Yearsley Swimming Baths Haleys Terrace York YO31 8SB
Fell 2no. Whitebeam - trees in a conservation area
Granted Trees 3 docs -
Yearsley Swimming Baths Haleys Terrace York YO31 8SB
Installation of 400no. PV panels to roof
Granted Other 11 docs -
The Cocoa Works Haxby Road York
Fell and replace T19, T48 and T59 plus remedial pruning of T12, T42, T44 and T49 as recommended in Barnes associates Tree report -trees in a conservation area
Granted Trees 3 docs -
Joseph Rowntree Theatre Haxby Road York YO31 8TA
Up to 2m crown reduction of 1no. Flowering Plum and up to 0.5m crown reduction of 1no. Cherry - trees in a conservation area
Granted Trees 2 docs
Other condition discharge and variation applications
In York
-
AOD/26/00082 Withdrawn
Axcel Hospitality (York) Limited 36 Piccadilly York YO1 9NX
Condition 5 (External Materials) of 24/01499/FUL
-
AOD/26/00093 Granted
Dean Court Hotel 1 - 6 Duncombe Place York YO1 7EF
Condition 3 (bats) of 22/01053/FUL
-
AOD/26/00089 Granted
The Milner Station Road York YO24 1AY
Condition 3 (materials) of 22/02629/FULM
-
AOD/26/00062 Granted
10 St Marys York YO30 7DD
Condition 3 of 25/02059/FUL
-
AOD/26/00090 Granted
Tang Hall Cp School Sixth Avenue York YO31 0UT
Conditions 3 (Bio-diversity Gain Plan), 4 (Habitat Management and Monitoring Plan), 7 (Detailed method of works/Construction Traffic Managment Plan), 8 (Construction Environmental Management Plan), 9 (Arboricultural Method Statement), and 22 (Remediation Strategy) of of 24/00857/FULM