Planning application
22/02305/OUT
Zacara Polo Ground Martins Lane Shurlock Row Reading RG10 0PP
Proposal
Outline application for scale only to be considered at this stage with all other matters to be reserved for a Clubhouse Pavilion.
As published by the council, reference 22/02305/OUT
Timeline
Dates from the published record
-
19 Aug 2022
Received by Windsor and Maidenhead
-
12 Sep 2022
Validated
Checked as complete and ready for consideration.
-
28 Jun 2023
Decision issued: Application Permitted
-
27 Jul 2026
Added to PlanIndex
What a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About outline applications
How this application type works
An outline application tests the principle of developing a site before the detail is worked up. Some or all of the particulars, such as appearance, layout, scale, access and landscaping, are held back as reserved matters for later approval. Permission at outline stage does not by itself allow building to start; the reserved matters must be approved first.
Nearby applications
Within 500 metres
-
26/01434/FULL Awaiting decision
4 Beenhams Farm Cottages Beenhams Heath Shurlock Row Reading RG10 0QB
Single storey front extension following demolition of existing conservatory.
-
22/03407/CPD Granted
Zacara Polo Ground To The East of Great Martins Martins Lane Shurlock Row Reading
Certificate of lawfulness to determine whether the proposed enclosure is lawful.
-
24/01995/FULL Refused
4 Beenhams Farm Cottages Beenhams Heath Shurlock Row Reading RG10 0QB
Replacement/self build dwelling.
-
26/01013/CLU Refused
Bellman Hanger Shurlock Row Reading RG10 0PL
Certificate of lawfulness to determine whether the existing use of the land as an external storage area and the restrictions on hours of vehicle movements, including movements on Sundays is lawful.
-
26/00258/FULL Granted
The Oaks Martins Lane Shurlock Row Reading RG10 0PP
New track.
-
26/00792/CONDIT Granted
The Oaks Martins Lane Shurlock Row Reading RG10 0PP
Details required by Condition 3 (Biodiversity gain plan) of planning permission 26/00258/FULL for a New track.
Other outline applications
In Windsor and Maidenhead
-
26/00843/OUT Refused
The Black Boys Inn Henley Road Hurley Maidenhead SL6 5NQ
Outline application for access only to be considered at this stage with all other matters to be reserved for the erection of 3 dwellings following the demolition of existing buildings.
-
25/00977/OUT Granted
Land At Maryland Horse Gate Ride Ascot
Outline application for access only to be considered at this stage with all other matters to be reserved for the phased development of 2 no. self / custom build dwelling houses with associated access, tree works, landscaping and parking.
-
26/01554/PIP Awaiting decision
Land Adjacent To House Jeer Oakley Green Road Oakley Green Windsor
Erection of 1no. self build dwelling, bin store and boundary treatment following demolition of existing 2no. barns.
-
26/01442/EIASCO Awaiting decision
Horton Quarry And Landfill Horton Road Horton Slough
EIA Scoping Opinion Request letter and supporting EIA Scoping Report under Regulation 15 of The Town and Country Planning (Environmental Impact Assessment) Regulations 2017 in respect for further development of Horton Quarry and Landfill.
-
26/01124/EIASCR Granted
Land Between Ascot Road And Holyport Road Holyport Maidenhead
Screening Opinion from the Council under Regulation 6 of the Environmental Impact Assessment Regulations 2017 ("the EIA Regulations"), to confirm whether or not there is a requirement for an Environmental Impact Assessment ("EIA") in relation to the demolition of existing structures (Lodge Farm former stable building, concrete framed open barn, pigsty and agricultural hardstanding) to deliver 180 dwellings alongside public realm improvements, restoration of the water tower, soft and hard landscaping, SuDS, vehicular and cycle parking, and other associated works.