Planning application
26/04577/ADFULL
7 St James's Square London SW1Y 4JU
Proposal
Details of precise location of each external item; product specifications, finishes and dimensions; sections and fixing details; and cable routes, penetrations and any making good of historic fabric pursuant to condition 4 of planning permission dated 19 March 2026 (RN: 25/07345/FULL).
As published by the council, reference 26/04577/ADFULL
Timeline
Dates from the published record
-
9 Jul 2026
Received by Westminster
-
21 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with Westminster for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
25/05354/LBC Granted
Chatham House 10 St James's Square London SW1Y 4LE
Remedial structural works to the lightwell and basement vault.
-
26/03269/LBC Awaiting decision
Chatham House 10 St James's Square London SW1Y 4LE
Removal of internal partition wall in the office spaces at the second floor.
-
25/06829/NMA Refused
103 - 105 Jermyn Street London SW1Y 6EE
Amendments to planning permission dated 21st August 2024 (RN 24/02152/FULL) for the Alterations and extensions including the erection of an additional storey at roof level with a terrace, lift overrun and plant enclosure, extensions at rear second to sixth floor level, alterations to Apple Yard Elevation treatment including addition of balconies and terraces, new façade treatment onto Jermyn Street Elevation, front terraces at fifth and sixth floor, partial excavation at lower ground level, all in association with the provision of additional Class E floorspace. NAMELY, rear balconies at 2nd and 3rd floors; location of rainwater pipes; internal core alterations; addition of a window to the staircore at seventh floor level; and addition of a pergola at sevent floor (roof) level.
-
26/00281/FULL Granted
103 - 105 Jermyn Street London SW1Y 6EE
Variation of condition 1 of planning permission dated 21st August 2024 (RN: 24/02152/FULL) (as amended by RN's: 24/08276/NMA, 24/08342/NMA, 25/02403/NMA & 25/07936/NMA) for Alterations and extensions including the erection of an additional storey at roof level with a terrace, lift overrun and plant enclosure, extensions at rear second to sixth floor level, alterations to Apple Yard Elevation treatment including addition of balconies and terraces, new façade treatment onto Jermyn Street Elevation, front terraces at fifth and sixth floor, partial excavation at lower ground level, all in association with the provision of additional Class E floorspace. NAMELY, amendments to allow re-addition of smaller, previously consented balconies at 2nd and 3rd floors; amendments to the location of rainwater pipes; internal core alterations; addition of a window to the stair core at 7th floor level; addition of a pergola at roof level; and addition of new balconies to the rear elevation at 2nd and 3rd floors.
-
25/07936/NMA Granted
103 - 105 Jermyn Street London SW1Y 6EE
Amendments to planning permission dated 22 August 2024 (RN: 24/02152/FULL) for Alterations and extensions including the erection of an additional storey at roof level with a terrace, lift overrun and plant enclosure, extensions at rear second to sixth floor level, alterations to Apple Yard Elevation treatment including addition of balconies and terraces, new façade treatment onto Jermyn Street Elevation, front terraces at fifth and sixth floor, partial excavation at lower ground level, all in association with the provision of additional Class E floorspace. Namely, the re-addition of smaller balconies at 2nd and 3rd floors, minor amendments to the location of select rain water pipes, internal core alterations and addition of a window to the stair core at 7th floor level.
-
26/00349/ADFULL Awaiting decision
103 - 105 Jermyn Street London SW1Y 6EE
Detailed drawings of office entrance and shopfront pursuant to Condition 5 of planning permission dated 21 August 2024 (RN: 24/02152/FULL).
Other full applications applications
In Westminster
-
26/04824/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Detailed design and specification of new blinds to NZH based on mock-up trials on-site. pursuant to condition 32 (i) of planning permission dated 8th April 2024 (23/00571/FULL).
-
26/04829/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Details of external and internal signage strategy pursuant to Condition 33(E) of planning permission dated 8th April 2024 (RN: 23/00571/FULL)
-
26/04841/ADFULL Granted
29 Henstridge Place London NW8 6QD
Details of the facing materials you will use, including glazing, and elevations and roof plans annotated to show where the materials are to be located pursuant to condition 5 of planning permission dated 18th November 2025 (RN:25/06159).
-
26/04989/FULL Awaiting decision
1 Kildare Terrace London W2 5JT
Erection of a mansard roof extending over the main house and side wing, replacement lower ground rear extension with roof terrace above, lowering of lower ground floor slab, installation of an air source heat pump in rear garden, new front boundary treatment, and new second floor window on the north elevation.
-
26/04986/FULL Awaiting decision
Inver Court Inverness Terrace London W2 6JB