Timeline
Dates from the published record
-
21 Jan 2026
Received by Westminster
-
10 Apr 2026
Decision issued: Application Permitted
-
21 Jul 2026
Added to PlanIndex
What a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
26/01853/FULL Awaiting decision
9 Carlos Place London W1K 3AT
Internal and external alterations associated with a new shop fit-out at 9 Carlos Place, including a new entrance ramp, partial lowering of the internal floor level, installation of a platform lift and new stairs, creation of a new entrance lobby and lowering of the external entrance door.
-
25/05833/FULL Awaiting decision
Flat 2 49 Grosvenor Square London W1K 3EP
Installation of two air condenser units at roof level and two ventilation grills in rear first floor windows.
-
26/04607/FULL Awaiting decision
9 Carlos Place London W1K 3AT
Installation of a new front door at No.10 Carlos Place.
-
25/08815/FULL Granted
8 Carlos Place London W1K 3AW
Installation of kitchen extract duct and associated works [Linked to 25/08816/LBC]
-
25/08816/LBC Granted
8 Carlos Place London W1K 3AW
Installation of commerical kitchen, back-of-house areas, and WCs; removal and replacement of doors across various levels; amendments to partitions and layout across different levels; installation of lift within pre-existing shaft, new vertical service lifts and internal ductwork; introduction of kitchen extract duct; installation of fixed furniture, joinery and associated features. [Linked to 25/08815/FULL]
-
25/06762/FULL Awaiting decision
Flat 11 45 - 47 Grosvenor Square London W1K 2HS
Installation of one air conditioning unit located in existing lightwell 2, within acoustic enclosure.
Other full applications applications
In Westminster
-
26/04824/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Detailed design and specification of new blinds to NZH based on mock-up trials on-site. pursuant to condition 32 (i) of planning permission dated 8th April 2024 (23/00571/FULL).
-
26/04829/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Details of external and internal signage strategy pursuant to Condition 33(E) of planning permission dated 8th April 2024 (RN: 23/00571/FULL)
-
26/04841/ADFULL Granted
29 Henstridge Place London NW8 6QD
Details of the facing materials you will use, including glazing, and elevations and roof plans annotated to show where the materials are to be located pursuant to condition 5 of planning permission dated 18th November 2025 (RN:25/06159).
-
26/04989/FULL Awaiting decision
1 Kildare Terrace London W2 5JT
Erection of a mansard roof extending over the main house and side wing, replacement lower ground rear extension with roof terrace above, lowering of lower ground floor slab, installation of an air source heat pump in rear garden, new front boundary treatment, and new second floor window on the north elevation.
-
26/04986/FULL Awaiting decision
Inver Court Inverness Terrace London W2 6JB
Replacement of combustible materials in the render facades; timber decking and plastic soffits/ fascias to terraces with non-combustible materials on the 5th and 6th floors.