Proposal
Variation of Condition 7 of planning permission dated 25 September 2023 (RN: 22/05897/FULL) for, "Installation of 4x air source heat pumps at roof level, single-story extension to the existing rear ground floor to extend existing office use, erection of small closet extension to accommodate WCs at rear mid-ground/first and mid-first/second floors, replacement of non-original windows with double glazed timber sash windows, external repairs to building and associated works, all in association with continued office (Class E) use"; NAMELY, to allow the use of ground floor roof as a communal roof terrace for occupiers of the building. (Application under Section 73).
As published by the council, reference 25/08883/FULL
Timeline
Dates from the published record
-
8 Dec 2025
Received by Westminster
-
13 Apr 2026
Decision issued: Application Permitted
-
20 Jul 2026
Added to PlanIndex
What a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
25/09191/ADLBC Granted
45 Manchester Street London W1U 7LS
Details of method statement of repair of the plasterwork pursuant to condition 4 of listed building consent dated 19 June 2025 (RN: 24/04922/LBC)
-
25/08834/LBC Granted
46 Manchester Street London W1U 7LS
Installation of porcelain decking, liquid waterproofing and lead flashing to rear ground floor roof. (linked to 25/08883/FULL)
-
25/06196/ADFULL Granted
48 Blandford Street London W1U 7HU
Detailed drawings of the new external doors (1:10 including detailed section drawings) pursuant to condition 3 of planning permission dated 1st July 2025 (RN: 25/03149/FULL)
-
26/00271/ADLBC Granted
44 Manchester Street London W1U 7LR
Details of method statement for the plasterwork and joinery repairs pursuant to Condition 3 of listed building consent dated 30 September 2024 (RN: 24/04921/LBC)
-
12/02136/FULL Refused
8 Chiltern Street London W1U 7PU
Retention of two air conditioning units at rear ground floor level.
-
25/06738/ADFULL Granted
41 Manchester Street London W1U 7LN
Details of how waste is to be stored on site and how materials for recycling will be stored separately and cycle storage pursuant to Conditions 7 and 8 of planning permission dated 8th April 2025 (RN: 24/06665/FULL).
Other full applications applications
In Westminster
-
26/04824/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Detailed design and specification of new blinds to NZH based on mock-up trials on-site. pursuant to condition 32 (i) of planning permission dated 8th April 2024 (23/00571/FULL).
-
26/04829/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Details of external and internal signage strategy pursuant to Condition 33(E) of planning permission dated 8th April 2024 (RN: 23/00571/FULL)
-
26/04841/ADFULL Granted
29 Henstridge Place London NW8 6QD
Details of the facing materials you will use, including glazing, and elevations and roof plans annotated to show where the materials are to be located pursuant to condition 5 of planning permission dated 18th November 2025 (RN:25/06159).
-
26/04989/FULL Awaiting decision
1 Kildare Terrace London W2 5JT
Erection of a mansard roof extending over the main house and side wing, replacement lower ground rear extension with roof terrace above, lowering of lower ground floor slab, installation of an air source heat pump in rear garden, new front boundary treatment, and new second floor window on the north elevation.
-
26/04986/FULL Awaiting decision
Inver Court Inverness Terrace London W2 6JB
Replacement of combustible materials in the render facades; timber decking and plastic soffits/ fascias to terraces with non-combustible materials on the 5th and 6th floors.