Planning application
25/08645/FULL
4 - 5 Cavendish Mews North London W1W 6LA
Proposal
Variation of condition 1 of planning permission dated 12 June 2024 (RN: 24/00473/FULL) for the: Erection of a roof extension and alterations to the front elevation to enlarge and alter residential dwelling (Class C3). Namely, to allow the installation of an air source heat pump within a roof level acoustic enclosure. (Application under section 73 of the Act).
As published by the council, reference 25/08645/FULL
Timeline
Dates from the published record
-
26 Nov 2025
Received by Westminster
-
30 Mar 2026
Decision issued: Application Permitted
-
20 Jul 2026
Added to PlanIndex
What a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
26/00516/NMA Granted
4 - 5 Cavendish Mews North London W1W 6LA
Amendments to planning permission dated 12th June 2024 (RN 24/00473/FULL) for the erection of a roof extension and alterations to the front elevation to enlarge and alter residential dwelling (Class C3). NAMELY, roof extension reprofiling.
-
25/06141/NMA Granted
4 - 5 Cavendish Mews North London W1W 6LA
Amendments to planning permission dated 12th June 2024 (RN:24/00473/FULL) for Erection of a roof extension and alterations to the front elevation to enlarge and alter residential dwelling (Class C3) namely, the repositioning of windows to function as a skylight within the second floor mansard roof, the northernmost rooflight to be repositioned to serve as a secondary means of escape, the northernmost window at first floor level to be reconfigured to match the positioning of the existing surveyed windows and the omission of two rooflights.
-
26/04113/LBC Awaiting decision
46 Portland Place London W1B 1NF
Installation of replacement all non-original windows and relevant external glazed doors with new painted windows and new glazed painted external doors together with reinstatement of suitable joinery profiles throughout.
-
26/04128/LBC Awaiting decision
46 Portland Place London W1B 1NF
Internal alterations to the rear of the first floor comprise the removal of existing non-original internal partitions associated with the WC/shower block and kitchen within the closet wing. All fixtures, fittings, and non-original doors within these areas will be removed. Suspended ceilings will also be taken down to reinstate the original ceiling heights and proportions of the principal rooms. The proposals include the installation of a new WC and tea point, together with associated partitioning. In addition, a new opening will be formed to provide a visual and physical connection between the library/study and the rear seating area. This will be detailed with matching cornices and skirtings to ensure the works are sympathetic to, and consistent with, the character and appearance of the existing historic fabric.
-
26/02183/CLEUD Awaiting decision
46 Portland Place London W1B 1NF
Confirmation on planning permission have been lawfully implemented by carrying out a material operation at the site, in accordance with the approved plans (Variation of condition 1 of planning permission dated 29 April 2016 (RN 14/12563/FULL) for the demolition of the rear extension to the building at lower ground, mezzanine, ground and first floor levels and rebuilding to include the creation of a terrace at rear first floor level. Excavation of additional basement levels and installation of plant at main roof and basement level all in association with the use of the property as a single family dwelling (Class C3) from RN 14/12563/FULL. NAMELY, to vary the approved drawings to enable additional excavation at basement levels, installation of photovoltaics at roof level, enlargement of the openings at ground and first floors, to change a window to a door to provide access to the terrace at rear first floor level and to alter the fenestration of the front elevation to the orangery with internal alterations at all floor levels)
-
25/08376/FULL Awaiting decision
52 Portland Place London W1B 1NH
Demolition, refurbishment, restoration and alterations to 52 Portland Place as well as removal of existing external condensers at basement, ground, third and fourth floor level and provision of new, consolidated plant and screening at basement and third floor level alongside other associated works. (Linked with 25/08377/LBC)
Other full applications applications
In Westminster
-
26/04824/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Detailed design and specification of new blinds to NZH based on mock-up trials on-site. pursuant to condition 32 (i) of planning permission dated 8th April 2024 (23/00571/FULL).
-
26/04829/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Details of external and internal signage strategy pursuant to Condition 33(E) of planning permission dated 8th April 2024 (RN: 23/00571/FULL)
-
26/04841/ADFULL Granted
29 Henstridge Place London NW8 6QD
Details of the facing materials you will use, including glazing, and elevations and roof plans annotated to show where the materials are to be located pursuant to condition 5 of planning permission dated 18th November 2025 (RN:25/06159).
-
26/04989/FULL Awaiting decision
1 Kildare Terrace London W2 5JT
Erection of a mansard roof extending over the main house and side wing, replacement lower ground rear extension with roof terrace above, lowering of lower ground floor slab, installation of an air source heat pump in rear garden, new front boundary treatment, and new second floor window on the north elevation.
-
26/04986/FULL Awaiting decision
Inver Court Inverness Terrace London W2 6JB
Replacement of combustible materials in the render facades; timber decking and plastic soffits/ fascias to terraces with non-combustible materials on the 5th and 6th floors.