Planning application
25/05034/FULL
Second Floor Flat 11 Croxley Road London W9 3HH
Proposal
Installation of two rooflights to front roofslope, a dormer and access door to the rear roofslope and the creation of a roof terrace.
As published by the council, reference 25/05034/FULL
Timeline
Dates from the published record
-
21 Jul 2025
Received by Westminster
-
1 Aug 2025
Validated
Checked as complete and ready for consideration.
-
17 Oct 2025
Decision issued: Application Permitted
-
21 Jul 2026
Added to PlanIndex
What a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
26/00428/FULL Awaiting decision
First Floor Flat 52 Fordingley Road London W9 3HF
Provision of roof terrace at the rear of property above existing ground floor rear projection, with associated screens and railing, installation of internal steps and a pair of external double doors.
-
25/07058/FULL Awaiting decision
Second Floor Flat 25 Croxley Road London W9 3HH
Erection of rear dormer with access door, creation of rear terrace and associated railings.
-
26/01753/FULL Awaiting decision
16A Croxley Road London W9 3HL
Installation of heat pumps at ground floor and solar panels to roofslopes.
-
26/02653/FULL Awaiting decision
Top Floor Flat 91 Fernhead Road London W9 3EA
Erection of second floor rear extension with inset balcony
-
25/05728/TPO Granted
24 Macroom Road London W9 3HY
1 x lime (T1, rear): reduce height to previous pruning points that are about 1.5m / 2m below the most recent pruning points and reduce lateral branches to the previous most recent reduction points; pruning as indicated in the attached photograph.
-
26/03861/FULL Awaiting decision
14A Fordingley Road London W9 3HE
Erection of a single storey side extension and alterations to existing ground floor rear elevation - works to ground floor flat.
Other full applications applications
In Westminster
-
26/04824/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Detailed design and specification of new blinds to NZH based on mock-up trials on-site. pursuant to condition 32 (i) of planning permission dated 8th April 2024 (23/00571/FULL).
-
26/04829/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Details of external and internal signage strategy pursuant to Condition 33(E) of planning permission dated 8th April 2024 (RN: 23/00571/FULL)
-
26/04841/ADFULL Granted
29 Henstridge Place London NW8 6QD
Details of the facing materials you will use, including glazing, and elevations and roof plans annotated to show where the materials are to be located pursuant to condition 5 of planning permission dated 18th November 2025 (RN:25/06159).
-
26/04989/FULL Awaiting decision
1 Kildare Terrace London W2 5JT
Erection of a mansard roof extending over the main house and side wing, replacement lower ground rear extension with roof terrace above, lowering of lower ground floor slab, installation of an air source heat pump in rear garden, new front boundary treatment, and new second floor window on the north elevation.
-
26/04986/FULL Awaiting decision
Inver Court Inverness Terrace London W2 6JB
Replacement of combustible materials in the render facades; timber decking and plastic soffits/ fascias to terraces with non-combustible materials on the 5th and 6th floors.