Planning application
22/04815/NMA
Eagle House 108 - 110 Jermyn Street London SW1Y 6EE
Proposal
Amendments to planning permission dated 05 November 2021 (RN: 21/05957/FULL) for Replacement of the main entrance and shopfront to the office premises from Jermyn Street, and replacement of the garage doors on Apple Tree Yard to provide an additional bike store door. Namely, enlargement of existing louver opening above garage doors and installation of new aluminium louvres.
As published by the council, reference 22/04815/NMA
Timeline
Dates from the published record
-
18 Jul 2022
Received by Westminster
-
2 Aug 2022
Decision issued: Application Refused
-
29 Jul 2026
Added to PlanIndex
What refusal means
The process from here
The council refused this application for the reasons set out on the decision notice, which the council portal holds in full. Only the applicant can appeal a refusal; the time limit runs from the decision date and is shorter for householder schemes.
Refusal does not prevent a fresh attempt. Applicants often address the reasons for refusal and resubmit, so a refused scheme is not necessarily the end of proposals for the site.
About amendments applications
How this application type works
An amendment application changes a permission that already exists. Non-material amendments cover small adjustments with no wider effect, while minor material amendments, usually made by varying a condition, allow modest design changes without a fresh application. Anything beyond that needs a new permission, so the scope here is deliberately narrow.
Nearby applications
Within 500 metres
-
25/07575/ADV Awaiting decision
108 Jermyn Street London SW1Y 6EE
Display of non-illuminated fascia sign measuring 0.64m x 1.35m; non illuminated hanging sign measuring 0.60m x 0.47m; and hand painted logo above entrance blazing.
-
26/00349/ADFULL Awaiting decision
103 - 105 Jermyn Street London SW1Y 6EE
Detailed drawings of office entrance and shopfront pursuant to Condition 5 of planning permission dated 21 August 2024 (RN: 24/02152/FULL).
-
25/07243/ADFULL Awaiting decision
103 - 105 Jermyn Street London SW1Y 6EE
Details of facing materials to be used, including glazing, and elevations and roof plans pursuant to Condition 4 of planning permission dated 22 August 2024 (RN24/02152/FULL)
-
25/06829/NMA Refused
103 - 105 Jermyn Street London SW1Y 6EE
Amendments to planning permission dated 21st August 2024 (RN 24/02152/FULL) for the Alterations and extensions including the erection of an additional storey at roof level with a terrace, lift overrun and plant enclosure, extensions at rear second to sixth floor level, alterations to Apple Yard Elevation treatment including addition of balconies and terraces, new façade treatment onto Jermyn Street Elevation, front terraces at fifth and sixth floor, partial excavation at lower ground level, all in association with the provision of additional Class E floorspace. NAMELY, rear balconies at 2nd and 3rd floors; location of rainwater pipes; internal core alterations; addition of a window to the staircore at seventh floor level; and addition of a pergola at sevent floor (roof) level.
-
26/00281/FULL Granted
103 - 105 Jermyn Street London SW1Y 6EE
Variation of condition 1 of planning permission dated 21st August 2024 (RN: 24/02152/FULL) (as amended by RN's: 24/08276/NMA, 24/08342/NMA, 25/02403/NMA & 25/07936/NMA) for Alterations and extensions including the erection of an additional storey at roof level with a terrace, lift overrun and plant enclosure, extensions at rear second to sixth floor level, alterations to Apple Yard Elevation treatment including addition of balconies and terraces, new façade treatment onto Jermyn Street Elevation, front terraces at fifth and sixth floor, partial excavation at lower ground level, all in association with the provision of additional Class E floorspace. NAMELY, amendments to allow re-addition of smaller, previously consented balconies at 2nd and 3rd floors; amendments to the location of rainwater pipes; internal core alterations; addition of a window to the stair core at 7th floor level; addition of a pergola at roof level; and addition of new balconies to the rear elevation at 2nd and 3rd floors.
-
25/07936/NMA Granted
103 - 105 Jermyn Street London SW1Y 6EE
Amendments to planning permission dated 22 August 2024 (RN: 24/02152/FULL) for Alterations and extensions including the erection of an additional storey at roof level with a terrace, lift overrun and plant enclosure, extensions at rear second to sixth floor level, alterations to Apple Yard Elevation treatment including addition of balconies and terraces, new façade treatment onto Jermyn Street Elevation, front terraces at fifth and sixth floor, partial excavation at lower ground level, all in association with the provision of additional Class E floorspace. Namely, the re-addition of smaller balconies at 2nd and 3rd floors, minor amendments to the location of select rain water pipes, internal core alterations and addition of a window to the stair core at 7th floor level.
Other amendments applications
In Westminster
-
26/04962/NMA Awaiting decision
Serpentine Gallery Kensington Gardens Exhibition Road London W2 3XA
Amendments to planning permission dated 27 February 2025 (RN: 24/08940/FULL) for the installation of temporary art sculpture from 24 March 2025 to 09 September 2025; NAMELY to extend the temporary planning consent until 21st March 2027.
-
26/04951/NMA Awaiting decision
43 - 45 Portman Square London W1H 6LY
Amendments to planning permission dated 22 April 2026 (25/06153/FULL) for: Variation of Condition 1 of planning permission dated 7 April 2025 (24/04987/FULL) for: Partial demolition of the existing roof and removal of plant equipment; construction of a roof extension providing new office (Class E) floorspace with associated external amenity spaces and plant equipment; refurbishment of the existing building, including infilling of the existing atrium; alterations to the existing façade; provision of cycle parking spaces and end of journey facilities, and all associated and ancillary works NAMELY; to amend the wording of Condition 27 to allow basement demolition work to proceed.
-
26/04873/NMA Awaiting decision
Orbis House 5 Mansfield Street London W1G 9NG
Amendments to planning permission dated 05 September 2024 (RN: 24/01895/FULL) for: new courtyard surface including walk-on rooflight; window and door alterations; new window to Mansfield Mews at second floor level; new rooflights; repairs to roof and external brickwork; erection of new staircase in front area lightwell; partial infill of rear lightwell at ground floor level; erection of roof terrace; installation of PV panels at roof level; and associated works namely; to allow provision of guarding system to provide safe access for maintenance across the roof; alteration at south elevation omitting window SFW11 from the new WC, remove the existing RWP from the internal courtyard corner, removal of the existing plastic section of a redundant vent pipe at lower level and retain original lead; new cast iron rain water pipes at west elevation; and internal layout alterations at basement, ground, 2nd, 3rd floors. (Linked with 26/04876/LBC)
-
26/04870/NMA Awaiting decision
34 Park Street London W1K 2JD
Amendments to planning permission dated 8 May 2026 (25/07808/FULL) for general refurbishment and M&E upgrade of the office building namely; roof walkable skylight, GF meeting room wall mounted TV, garden bench and planters, fire lobbies, L4 glass partition, reception to hall door swing change, front lightwell electric cupboard change, wall panelling on LGF and L5, LGF modular screen, LGF courtyard window door infill, and LGF cove lighting.
-
26/04816/NMA Awaiting decision
Ebury Bridge Estate Ebury Bridge Road London SW1W 8PX
Amendments to planning permission dated 21 July 2023 (RN:23/00331/COOUT) for a mixed use development in outline for residential floorspace and ancillary residential facilities (Class C3) non-residential floorspace comprising flexible retail (Classes A1 - A4), community (Class D1), leisure (Class D2) and workspace (Class B1) floorspace; provision of basement; new pedestrian and vehicular access; and associated amenity space, open space, plant, landscaping, car and cycle parking, refuse storage, servicing area, and other associated infrastructure works; and detailed planning consent for Blocks 7 and 8 comprising residential floorspace and ancillary residential facilities (Class C3); provision of a basement; new pedestrian and vehicular access; and associated amenity space landscaping, car and cycle parking, refuse storage, servicing area, and other associated infrastructure works, namely amendments to the approved Masterplan Phasing to incorporate enabling works and piling in Phase 2a and 3a.