Planning application
Third Floor 144 - 146 New Bond Street London W1S 2TR
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Details of visual screening for the proposed air conditioning unit pursuant to Condition 3 of planning permission dated 30 November 2007 (RN: 07/08140).
As published by the council, reference 08/05527/ADFULL
Application record
- Reference
- 08/05527/ADFULL
- Type
- Approval of Details (Full PP)
- Status
- Decided
- Decision
- Application Permitted
- Received
- 25 Jun 2008
- Validated
- 25 Jun 2008
- Decided
- 22 Jul 2008
- Ward
- West End
- Decision by
- Delegated Decision
- Postcode
- W1S 2TR
Site history
Applications at this address on the Westminster register
This site has had 2 applications since 2008: 1 approved, 1 refused.
-
08/02504/ADFULL Refused
Third Floor 144 - 146 New Bond Street London W1S 2TR
Details of visual screening for the proposed air conditioning unit pursuant to Condition 3 of planning permission dated 30 November 2007 (RN: 07/08140).
Timeline
Dates from the published record
-
25 Jun 2008
Received by Westminster
-
22 Jul 2008
Decision issued: Application Permitted
-
14 Sep 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
5 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
Westminster granted permission on 22 July 2008, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
Third Floor 144 - 146 New Bond Street London W1S 2TR
Details of visual screening for the proposed air conditioning unit pursuant to Condition 3 of planning permission dated 30 November 2007 (RN: 07/08140).
Refused Full applications 4 docs -
144-146 New Bond Street London W1S 2TR
New access doors and installation of louvres to the alley to the North of the property, internal alterations at basement, ground, first and second floors including insertion of stairs and the installation of external plant with associated screening and railings at rear first floor roof level. Installation of uplighters to front elevation.
Granted Heritage and listed buildings 3 docs -
144-146 New Bond Street London W1S 2TR
Internal alterations at first and second floor level.
Granted Heritage and listed buildings 9 docs -
144-146 New Bond Street London W1S 2TR
Display of an internally illuminated (letters and logos only) seasonal display at first to third floor levels, measuring 9m x 12.65m, for a temporary period.
Granted Advertising 8 docs -
144-146 New Bond Street London W1S 2TR
Details showing the omission of all works to remove/relocate the doors at first floor level and the associated installation of a fire curtain pursuant to Condition 2 of listed building consent dated 23rd May 2023 (RN: 23/01385/LBC).
Granted Conditions 11 docs -
144 - 146 New Bond Street London W1S 2TR
84% historically approved · decision due ~13 Aug
Display of a temporary full facade cover to the principal street elevation of 144 - 146 New Bond Street measuring 16.118m X 12.462m between 22/06/2026 and 22/07/2026. (Linked with 26/04043/LBC)
Awaiting decision Advertising
Other full applications
In Westminster
-
26/03576/FULL Decided
15A Devonshire Terrace London W2 3DW
Erection of an infill extension to basement courtyard to form new bedroom and internal alterations. (Linked with 26/03577/LBC)
-
26/06207/FULL Awaiting decision
8 Moscow Road London W2 4BT
Installation of rooftop plant and a metal plant enclosure, together with associated external alterations including the demolition of 7 (no.) existing chimney stacks, levelling of the parapet between Nos. 8-14 Moscow Road, and the installation of a new riser conduit and restaurant duct to the rear elevation.
-
26/06205/FULL Awaiting decision
Richmond House 79 Whitehall London SW1A 2NS
Temporary ground investigation works and archaeological monitoring including the excavation of trial pits and boreholes within Richmond House.
-
26/06154/FULL Awaiting decision
24 Castellain Road London W9 1EZ
Use of part of the existing main flat roof as a private residential roof terrace; installation of black painted metal balustrading/railings; provision of safe access to the roof terrace via a sliding rooflight; installation of an Air Source Heat Pump (ASHP) at roof terrace level; construction of enlarged dormer and a terrace the rear of the 3rd floor; and associated works.
-
26/06175/FULL Awaiting decision
66 Chepstow Road London W2 5BE
Replacement of front and rear windows with vacuum glazing and slightly narrower glazing bars; replacement of front and basement access doors with new front door, fanlight and frame (vacuum-glazed) and new (vacuum-glazed) basement access door. (Linked with 26/05852/LBC)