Granted West Northamptonshire WNS/2022/0992/DCOR Development Consent Order Requirements

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Requirement 8 (2)(p) - Estate roads & highways signage for Authorised Works No. 4(1)(m) and Works No.5 and 'Further Works’ (2)(k). [Approval of details pursuant to Schedule 2 Requirements of The Northampton Gateway Rail Freight Interchange Order 2019]

As published by the council, reference WNS/2022/0992/DCOR

Application record

Reference
WNS/2022/0992/DCOR
Type
Development Consent Order Requirements
Status
10 - Approved
Decision
Granted As published: Approval
Received
23 May 2022
Validated
23 May 2022
Decided
4 Aug 2022
Parish
Blisworth
Decision by
Delegated

Site history

Applications at this address on the West Northamptonshire register

This site has had 14 applications since 2021: 13 approved, 0 refused.

  • 2023/5187/DCOR Awaiting decision

    NGRFI Land west of M1-J15

    Requirement 8 (2) (t) - Substations - Works No 2 - (Estate Road) and Further Works Component (e) 'substations' [Approval of details pursuant to Schedule 2 Requirement of The Northampton Gateway Rail Freight Interchange Order 2019]

    Submitted 3 May 2023
  • NGRFI Land west of M1-J15

    Requirement 25,(1) - Land Contamination Risk Assessment Works No. 12 and 13 Works No.14 [Approval of details pursuant to Schedule 2 Requirements of The Northampton Gateway Rail Freight Interchange Order 2019]

    Decided 31 Jan 2023
  • NGRFI Land west of M1-J15

    Requirement 23 (1) Noise during the operational phase - Works No. 2. (rail terminal) Component 3 (1) (b) – rail terminal and related infrastructure [Approval of details pursuant to Schedule 2 Requirement of The Northampton Gateway Rail Freight Interchange Order 2019]

    Decided 9 Dec 2022
  • NGRFI Land west of M1-J15

    Requirement 8 (2) - Rail infrastructure and Rail terminal Works No 2 - Part of DCO Requirement 3(1) component (b) [Approval of details pursuant to Schedule 2 Requirement of The Northampton Gateway Rail Freight Interchange Order 2019]

    Decided 23 Dec 2022
  • NGRFI Land west of M1-J15

    Requirement 12 - P-CEMP for Authorised Works No.2 (Rail Terminal) phase 2. Construction Environmental Management Plan for Works No.s 1-6 Revision 6. [Approval of details pursuant to Schedule 2 Requirement of The Northampton Gateway Rail Freight Interchange Order 2019].

    Decided 4 Aug 2022
  • NGRFI Land west of M1-J15

    Requirement 25(1) - Contamination Risk relevant to works Nos 15, 16 and 17 (Highways Works) [Approval of details pursuant to Schedule 2 Requirement of The Northampton Gateway Rail Freight Interchange Order 2019]

    Decided 2 Dec 2022
  • NGRFI Land west of M1-J15

    Requirement 15(1) - External Lighting scheme for Works No. 4(3) - Estate Office (Management Suite). [Approval of details pursuant to Schedule 2 Requirement of The Northampton Gateway Rail Freight Interchange Order 2019

    Decided 8 Jul 2022
  • NGRFI Land west of M1-J15

    Requirement 8 (2), Works No 2 - Component (b) - rail infrastructure and rail terminal, as defined in DCO Requirement 3(1)(b) [Approval of details pursuant to Schedule 2 Requirement of The Northampton Gateway Rail Freight Interchange Order 2019]

    Decided 26 Apr 2022
  • NGRFI Land west of M1-J15

    Requirement 15 - Lighting for rail terminal - Works No. 2. Part of Component (b) - rail infrastructure and rail terminal as defined in DCO Requirement 3 (1) (b) [Approval of details pursuant to Schedule 2 Requirement of The Northampton Gateway Rail Freight Interchange Order 2019]

    Decided 8 Jul 2022
  • NGRFI Land west of M1-J15

    Erection of Estate Management & Security Office, details pursuant to Requirement 8 (2) (f) – built development design and layout & Requirement 10 - landscaping. [Approval of details pursuant to Schedule 2 Requirement of The Northampton Gateway Rail Freight Interchange Order 2019]

    Decided 13 May 2022

Timeline

Dates from the published record

  1. 23 May 2022

    Received by West Northamptonshire

  2. 4 Aug 2022

    Decision issued: Approval

  3. 5 Sep 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

5 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

West Northamptonshire granted permission on 4 August 2022, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on West Northamptonshire's portal will say. Our guide explains the common types.