Planning application
Buzz Bingo Denby Dale Road Wakefield WF1 1JN
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Installation of 4 Ultra Rapid EV chargers serving 8 bays along with associated electrical equipment and car park reconfiguration.
As published by the council, reference 24/01344/FUL
Application record
- Reference
- 24/01344/FUL
- Type
- Full Application
- Status
- Decided
- Decision
- Granted As published: Application Approved
- Received
- 7 Aug 2024
- Validated
- 12 Aug 2024
- Decided
- 21 Nov 2024
- Ward
- Wakefield North
- Decision by
- Delegated Decision
- Postcode
- WF1 1JN
Site history
Applications at this address on the Wakefield register
This site has had 2 applications since 2024: 2 approved, 0 refused.
-
26/01027/SPN Granted
Buzz Bingo Denby Dale Road Wakefield WF1 1JN
Installation of Solar PV on roof across site.
Timeline
Dates from the published record
-
7 Aug 2024
Received by Wakefield
-
12 Aug 2024
Validated
Checked as complete and ready for consideration.
-
21 Nov 2024
Decision issued: Application Approved
-
7 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
10 documents on file for this application
- HIGHWAYS DEVELOPMENT MANAGEMENT WAKEFIELD COUNCIL
- LOCATION PLAN
- BLOCK PLAN
- APPLICATIONFORMREDACTED
- PLANNING LAYOUT
- ELEVATIONS-ALPITRONIC HYC300
- ELEVATIONS-5 WAY SCHNEIDER PILLAR
- ELEVATIONS-SUBSTATION TR18
- 4-METRE TUBULAR COLUMN ROOT MOUNT PART
- STREET LIGHT
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Wakefield granted permission on 21 November 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Buzz Bingo Denby Dale Road Wakefield WF1 1JN
Installation of Solar PV on roof across site.
Granted 9 docs -
Church House 1 South Parade Wakefield WF1 1LP
Variation of condition 2 (approved plans) pursuant to approved planning application 22/02502/FUL (dated 06.06.23) which granted planning permission for the change of use to create 10 residential units with minor internal alterations and external works to allow for changes to the floor plans and elevations. (retrospective)
Granted Amendments 20 docs -
1 South Parade Wakefield WF1 1LP
Discharge of Condition 4 (CMS) from approved application 22/02502/FUL
Granted Conditions 3 docs -
1 South Parade Wakefield WF1 1LP
Discharge of Condition 3 (Landscaping), Condition 6 (Radon) and Condition 7 (Bats) from approved application 22/02502/FUL
Granted Conditions 6 docs -
Church House 1 South Parade Wakefield West Yorkshire WF1 1LP
Listed building consent application for the change of use of building to create 10 residential units with minor internal alterations and external works (amended scheme) (retrospective)
Granted Heritage and listed buildings 21 docs -
Capa College 1 South Parade Wakefield WF1 1LP
88% historically approved · decision due ~29 Oct
Discharge Of Condition 4 (Crime) from approved application 22/02502/S7301
Awaiting decision 4 docs
Other full applications
In Wakefield
-
26/01505/FUL Decided
75 Jenkin Road Horbury Wakefield WF4 6DP
Single storey glazed rear extension
-
26/01320/FUL Decided
Taylor Wimpey Site Newland Grange Neil Fox Way Wakefield WF1 4GQ
New permanent public artwork and associated works
-
26/01917/FUL Awaiting decision
179 Bradford Road Wakefield WF1 2AS
single storey rear & side extension.
-
26/01484/FUL Decided
117 Mountbatten Crescent Outwood Wakefield WF1 3EQ
Proposed two apartments
-
26/01559/FUL Decided
Waterton Park Golf Club The Balk Walton Wakefield WF2 6QL
Siting of a temporary WC and shower/welfare unit (replacing two existing WC units) with associated non-mains foul drainage holding tank, for a temporary period of five years