Planning application
Ingrebourne Valley Ltd Orsett Quarry Buckingham Hill Road Linford Essex SS17 0PP
Refused. Only the applicant can appeal, within the statutory time limit, and a revised scheme can be submitted instead.
Proposal
Mineral extraction at Walton Hall Farm for processing on land at Orsett Quarry, erection of a processing plant and ancillary activities at Orsett Quarry, importation and treatment of reclamation material with progressive restoration to farmland with landscape planting at Walton Hall Farm followed by mineral extraction at Orsett Quarry, reclamation and infilling at Orsett Quarry followed by landscape restoration works at Orsett Quarry. [Revised plans and additional documents], [Amended description of development].
As published by the council, reference 19/01709/FUL
Application record
- Reference
- 19/01709/FUL
- Type
- Full Planning Permission Application
- Status
- Refused
- Decision
- Refused
- Received
- 19 Nov 2019
- Validated
- 21 Nov 2019
- Decided
- 27 Mar 2026
- Ward
- OLD East Tilbury
- Decision by
- Committee Decision
- Postcode
- SS17 0PP
Timeline
Dates from the published record
-
19 Nov 2019
Received by Thurrock
-
21 Nov 2019
Validated
Checked as complete and ready for consideration.
-
27 Mar 2026
Decision issued: Refused
-
19 Aug 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
David Walker Limited Agent, registered in Shipley
Active · incorporated 2015 · Shipley
2 applications on PlanIndex · across 2 councils
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordIngrebourne Valley Limited Applicant, registered in Harlow Common Harlow
Active · incorporated 1993 · Harlow Common Harlow
12 applications on PlanIndex · across 2 councils
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
159 documents on file for this application
- ENV HEALTH
- DECISION NOTICE
- 24TH FEB 2026 PUBLISHED COMMITTEE REPORT
- BUGLIFE
- ESSEX FIELD CLUB
- ESSEX WILDLIFE TRUST
- NATIONAL GAS
- NATIONAL GRID
- NATIONAL GAS 1 OF 2
- NATIONAL GAS 2 OF 2
- NATIONAL GAS
- ENVIRONMENT AGENCY
- ARCHAEOLOGICAL SECTION ESSEX COUNTY COUNCIL.
- ARCHAEOLOGICAL SECTION ESSEX COUNTY COUNCIL.
- NATIONAL HIGHWAYS RESPONSE
- PUBLIC FOOTPATH
- LISTED BUILDINGS/CONSERVATION
- ENVIRONMENTAL HEALTH
- HIGHWAYS
- ANGLIAN WATER
- ESSEX BADGER GROUP
- 2405- IVL - ORSETT QUARRY - SECOND SUPPLEMENTARY SUBMISSION 10.05.24
- COMPOSITE OPERATIONS PLAN
- PROGRESSIVE OPERATIONS PLANS - PHASES 5A & 5B
- PROGRESSIVE OPERATIONS PLANS - PHASES 6 & 7
- PROGRESSIVE OPERATIONS PLANS - PHASE 8 TO COMPLETION
- CLIMATE CHANGE STATEMENT
- LHO COMMENTS
- HIGHWAYS
- LANDSCAPE & ECOLOGY
- FOOTPATH PROPOSALS
- FOOTPATH PROPOSALS
- NATURAL ENGLAND
- NATURAL ENGLAND
- PHASE 1 HABITAT SURVEY
- REVISED RESTORATION SURVEY
- COMPOSITE OPERATIONS PLAN
- PROGRESSIVE OPERATIONS PLANS PHASES 5A & 5B
- PROPOSED UNDERGROUND TUNNEL & CONVEYOR PHASE 5A
- PROPOSED TUNNEL & CONVEYOR - ILLUSTRATIVE CROSS SECTIONS PHASE 5A
- PROPOSED UNDERGORUND TUNNEL & CONVEYOR - PHASE 5B
- PROPOSED TUNNEL &CONVETOR - ILLUSTARTIVE CROSS SECTIONS - PHASE 5B
- NATURAL ENGLAND RESPONSE
- ORSETT QUARRY ECOLOGY PARK UPDATE
- ADDITIONAL INFO NATURAL ENGLAND
- NATURAL ENGLAND (BUCKINGHAM HILL PIT MITIGATION)
- STRATEGIC PLANNING
- NATURAL ENGLAND
- ENVIRONMENTAL HEALTH
- 17 TORRIDGE EAST TILBURY ESSEX RM18 8SN
- ESSEX BADGER PROTECTION GROUP
- ENVIRONMENTAL AGENCY
- HIGHWAYS RESPONSE
- 45 QUEEN ELIZABETH AVENUE EAST TILBURY RM18 8SP
- TC_ HIGHWAYS
- ESSEX COUNCIL MINERAL AND WASTE
- ST HELIER MUCKINGFORD ROAD
- HISTORIC ENVIRONMENT
- ECC AS
- APPLICATION PLAN
- BREEDING BIRD SURVEY
- ILLUSTRATIVE CROSS SECTIONS A-A1 & B-B1
- ILLUSTRATIVE CROSS SECTIONS C-C1 & D-D1
- ECOLOGICAL ENHANCEMENT PLAN
- RETAINED LAKE ECO PARK
- CENTRAL ECO PARK
- PHASE 1 HABITAT SURVEY
- WATERBODY LOCATIONS
- PROGRESSIVE OPERATIONS PLANS KEY
- PHASES 1 AND 2
- PHASES 3 AND 4
- PHASES 5A AND 6B
- PHASES 6 AND 7
- PHASE 8 TO COMPLETION
- REVISED RESTORATION PLAN CIRCA YEAR 10
- REVISED RESTORATION PLAN CIRCA YEAR 20.
- REPTILE DISTRIBUTION PLAN
- SITE CONTEXT PLAN
- SILT MANAGEMENT
- 2207 - IVL - ORSETT QUARRY - SUPPLEMENTARY SUBMISSION FINAL AS AT 27.07.2022
- APPENDIX 1 - COPY OF APPROVED WORKING AND RESTORATION PLANS
- APPENDIX 3 - IVERTEBRATE REPORT [FINAL ISSUE 190722]
- APPENDIX 4 - SUDS STRATEGY - FINAL
- APPENDIX 5 - TRANSPORT STATEMENT - 17 JULY 2022-REV B
- ORSETT UPDATING ECOLOGICAL ASSESSMENT - LESS APPENDIX 1
- HIGHWAYS ENGLAND
- NATIONAL GRID
- HIGHWAYS ENGLAND RESPONSE
- HIGHWAYS ENGLAND RESPONSE
- ENVIRONMENTAL PROTECTION TEAM
- HIGHWAYS ENGLAND RESPONSE
- HIGHWAYS RESPONSE
- PETITION WITH 583 SIGNATURES
- BARVILLS STATION ROAD EAST TILBURY ESSEX RM18 8QP
- 18 NORTHUMBERLAND ROAD LINFORD ESSEX SS17 0PT
- TABEK PRINCESS MARGARET ROAD EAST TILBURY ESSEX RM18 8PB
- 7 ALEXANDRA WAY TILBURY RM18 8NT
- ESSEX FIELD CLUB
- ESSEX FIELD CLUB
- NATIONAL GRID 1/2
- NATIONAL GRID 2/2
- ESSEX BADGER GROUP
- PRESS NOTICE 05.12.19
- CADENT GAS
- ESSEX WILDLIFE TRUST
- NATURAL ENGLAND
- BUGLIFE 19.12.19
- LISTED BUILDINGS/CONSERVATION
- RSPB
- ENVIRONMENT AGENCY
- FLOOD RISK MANAGER
- HIGHWAYS ENGLAND
- NETWORK RAIL
- ESSEX COUNTY COUNCIL ARCHAELOGY
- NATURAL ENGLAND
- PUBLIC FOOTPATH
- CADENT GAS
- HIGHWAYS
- ANGLIAN WATER
- COVERING LETTER 19.11.19
- ES VOL.2: AIR QUALITY ASSESSMENT
- ES VOL.2: ARCHAEOLOGY & CULTURAL HERITAGE
- ES VOL.2: AGRICULTURAL LAND QUALITY APPRAISAL
- ES VOL.2: ECOLOGICAL ASSESSMENT
- ES VOL. 2: LANDSCAPE & VISUAL IMPACT ASSESSMENT
- ES VOL.2: NOISE ASSESSMENT
- ES VOL.2: COVER SHEET
- ES VOL.2 ORSETT QUARRY HYDROGEOLOGICAL ASSESSMENT APPENDIX F
- ES VOL.2: TRANSPORT STATEMENT
- APPLICATION PLAN
- ES VOL.2: WALTON'S HALL FM HYDROGEOLOGICAL IMPACT ASSESSMENT APPENDIX F
- ES VOL.2: WALTON'S HALL FM FRA APPENDIX D
- ES VOL.2: ORSETT QUARRY FRA APPENDIX C
- ES VOL.2: WALTON'S HALL FM FRA
- ES VOL.2: ORSETT QUARRY FRA
- ES VOL.1 APPENDIX 1 - DETAILS OF MOBILE SCREENING UNIT & CRUSHER UNIT
- ES VOL.2: WALTON'S HALL FM HYDROGEOLOGICAL IMPACT ASSESSMENT
- ES VOL.2: ORSETT QUARRY HYDROGEOLOGICAL IMPACT ASSESSMENT
- SITE CONTEXT
- APPLICATION PLAN
- ILLUSTRATIVE CROSS SECTIONS
- ILLUSTRATIVE CROSS SECTIONS
- PROGRESSIVE OPERATIONS PLANS PHASES 1
- PROGRESSIVE OPERATIONS PLANS PHASES 3
- PROGRESSIVE OPERATIONS PLANS PHASES 5A
- PROGRESSIVE OPERATIONAL PLANS - PHASES 6
- PROGRESSIVE OPERATIONAL PLANS - PHASE 8 TO COMPLETION
- PROCESSING PLANT (THORLEY HALL FARM)
- RESTORATION SCHEME C. YEAR 10
- RESTORATION SCHEME C. YEAR 20
- PRELIMINARY ACCESS DETAILS
- ES NON-TECHNICAL SUMMARY COVER
- COMPOSITE OPERATIONS PLAN
- LOCATION PLAN
- ES VOL.1
- ES APPENDIX 1 - DETAILS OF MOBILE SCREENING & CRUSHER UNITS
- ES VOL.1: APPENDIX 2 SUMMARY OF PROPOSALS SHEET
- ES NON-TECHNICAL SUMMARY
- APPLICATIONFORMREDACTED
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this refusal means
Thurrock refused this application for the reasons on the decision notice; only the applicant can appeal, and refused schemes often return in revised form. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Other full applications
In Thurrock
-
26/01219/FUL Awaiting decision
70 Argent Street Grays Essex RM17 6PG
Change of use from C3 to C4 HMO
-
26/01217/FUL Awaiting decision
1 Wilsman Road South Ockendon Essex RM15 6QB
Application for the change of use of a dwelling (Use Class C3a) to a children's home for up to two children (Use Class C2), involving the conversion of a garage to an office.
-
26/01203/FUL Awaiting decision
Oozedam High Road Fobbing Essex SS17 9HT
Part demolition and alterations to the existing dwelling to provide a three-bedroom retained home; demolition of the pool enclosure and ancillary outbuildings; and erection of four detached dwellings, comprising one three-bedroom, two four-bedroom and one five-bedroom home, with access, parking, cycle and refuse storage, landscaping, biodiversity enhancement, drainage and associated works. The existing basement and electric entrance gates are retained.
-
26/01202/FUL Awaiting decision
39 Woodmanhurst Road Corringham Essex SS17 7RX
Chnage of use from Dwellinghouse (C3A) to Childrens Home (C2)
-
26/01199/FUL Awaiting decision
38 Clarence Road Grays Essex RM17 6QJ
Change of use from residential dwellinghouse (Use Class C3(a)) to children's residential care home (Use Class C2) for up to three children aged 6 -17.