Planning application
Land Off Huddersfield Road, Mossley
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Reserved matters application for 175 dwellings with associated works pursuant to outline planning permission 18/00159/OUT (layout, scale, appearance and landscaping).
As published by the council, reference 26/00004/REM
Application record
- Reference
- 26/00004/REM
- Category
- Reserved matters
- Status
- Decided
- Decision
- Granted As published: Approve
- Received
- 5 Jan 2026
- Validated
- 9 Mar 2026
- Decided
- 24 Jul 2026
- Ward
- Mossley
- Parish
- Mossley
- Decision by
- Committee (Speakers Panel) Decision
Timeline
Dates from the published record
-
5 Jan 2026
Received by Tameside
-
9 Mar 2026
Validated
Checked as complete and ready for consideration.
-
21 Jul 2026
Added to PlanIndex
-
24 Jul 2026
Decision issued: Approve
Related applications
Cases linked to this one on the register
- Application: 18/00159/OUT (Decided)
- Buildingcontrol: 26/00438/INIT (Initial notice accepted)
Documents
The council's own list, drawings first
65 documents on file for this application
Drawings (27)
- Proposed site sections
- Streetscenes
- Site sections
- Planning layout
- Materials & hard surfaces
- Growall
- Garden roll
- Screen wall abutting fence
- Screen fence
- Hit and miss fence
- Boundary plan
- Ball top railing
- Cheshire railing
- Knee rail
- Post and 2 rail fence
- Timber gate
- Ev plan
- Refuse plan
- Parking provision
- Tenure plan
- External works
- External works
- External works
- House type pack
- Landscaping structure plan
- Land to west of huddersfield rd leap
- Location plan
Everything on file (65)
- DECISION NOTICE
- APPLICANT STATEMENT TO OBJECTIONS
- ADDENDUM SLOPE STABILITY LETTER
- SLOPE STABILITY ADDENDUM
- CONSULTATION RESPONSE - MOSSLEY TOWN COUNCIL
- CONSULTATION RESPONSE - ECOLOGY
- PROPOSED SITE SECTIONS
- MATERIALS & HARD SURFACES
- PLANNING LAYOUT
- CONSULTEE COMMENT - ENVAGE 12.06.2026
- CONSULTEE COMMENT - NATURAL ENGLAND - 28.05.2026
- CONSULTEE COMMENT - CANAL AND RIVER, 28.05.2026
- CONSULTATION RESPONSE - TFGM
- CONSULTATION RESPONSE - CONTAMINATED LAND
- CONSULTATION RESPONSE - GREATER MANCHESTER ARCHEOLOGICAL ADVISORY SERVICE (GMAAS
- CONSULTATION RESPONSE - LOCAL HIGHWAYS AUTHORITY
- CONSULTEE COMMENT - TREES 19.05.2026
- CONSULTEE COMMENT - ACTIVE TRAVEL ENGLAND - 15.05.2026
- LOCATION PLAN
- DESIGN AND ACCESS STATEMENT
- GROWALL
- GARDEN ROLL REV A
- 1.8M SCREEN WALL ABUTTING FENCE
- 1.8M SCREEN FENCE
- 1.8M HIT AND MISS FENCE
- BOUNDARY PLAN
- 1.2M BALL TOP RAILING
- 1.2M CHESHIRE RAILING
- 450MM KNEE RAIL
- 900MM POST AND 2 RAIL FENCE
- TIMBER GATE
- EV PLAN
- REFUSE PLAN
- STREETSCENES
- PARKING PROVISION
- SITE SECTIONS
- TENURE PLAN
- EXTERNAL WORKS SHEET 1 OF 3
- EXTERNAL WORKS SHEET 2 OF 3
- EXTERNAL WORKS SHEET 3 OF 3
- POS CALCULATION
- HOUSE TYPE PACK
- COVERING LETTER - ADDITIONAL INFORMATION
- LANDSCAPING STRUCTURE PLAN
- ENERGY AND SUSTAINABILITY STATEMENT
- MEMO: NOISE IMPACT FROM MOSSLEY HOLLINS SPORTS PITCHES
- CONSULTATION RESPONSE - ENVIRO AGENCY
- CONSULTATION RESPONSE - GMAAS
- CONSULTATION RESPONSE - TREES
- CONSULTATION RESPONSE - NATURAL ENGLAND
- CONSULTATION RESPONSE - EDUCATION
- CONSULTATION RESPONSE - WASTE SERVICES
- CONSULTATION RESPONSE - OLDHAM
- CONSULTATION RESPONSE - CANAL & RIVERS
- CONSULTATION RESPONSE - ENVIRONMENT AGENCY
- CONSULTATION RESPONSE - CONTAMINATED LAND
- CONSULTATION RESPONSE - ACTIVE TRAVEL
- PLANNING STATEMENT
- ARBORICULTURAL IMPACT ASSESSMENT
- PRELIMINARY ECOLOGICAL APPRAISAL AND BIODIVERSITY NET GAIN BASELINE
- CRIME IMPACT STATEMENT
- LAND TO WEST OF HUDDERSFIELD RD LEAP
- TECHNICAL NOTE
- SLOPE STABILITY ASSESSMENT REPORT
- APPLICATION FORM - WITHOUT PERSONAL DATA
Watch members (£5 a month) open the document list from here.
Open the documentsWorking a patch? Trade sends you the drawings on every job in your area. 14 days free.
What this grant of permission means
Tameside granted permission on 24 July 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About reserved matters applications
A reserved matters application fills in the detail held back from an earlier outline permission, judged against that permission rather than the principle of development. More in our guide to planning application types.
Other reserved matters applications
In Tameside
-
26/00384/REM Awaiting decision
Godley Green Eastern Village Mottram Old Road Hyde Tameside SK14 3AL
Reserved Matters application for Phase EV1, EV2 and part EV3 site infrastructure and enabling works to include: demolition of on-site structures and provision of site access off Mottram Old Road; internal primary spine road; and associated earthworks; drainage; substation(s); landscaping and play space
-
25/00468/REM Granted
Droylsden Labour Club 100 Manchester Road Droylsden Tameside M43 6PF
Application for approval of reserved matters (scale) following outline approval of 22/00952/OUT for proposed one-storey vertical extension to create 5 number apartments above a retail warehouse. Revised building (reduction in height) from the previously approved reserved matters - 23/00151/REM.
-
23/00151/REM Granted
Droylsden Labour Club 100 Manchester Road Droylsden Tameside M43 6PF
Application for approval of reserved matters (access, appearance, layout and scale) following outline approval of 22/00952/OUT for proposed one-storey vertical extension to create 5 number apartments above a retail warehouse
-
19/01090/REM Granted
Land Between Ford Grove Atherton Avenue And Hyde Road Mottram Tameside
Approval of the reserved matters with respect to access, appearance, layout, scale and landscaping for the construction of 20 new dwellings (pursuant to outline planning permission ref. 16/00944/OUT)
-
21/00835/REM Granted
Land Between Springfield And Pentire Mottram Road Hyde Tameside SK14 3AR
Application for approval of reserved matters following outline approval of 20/00948/OUT Proposed demolition of redundant BT building and construction of single detached two storey building. All matters to be considered including access, appearance, landscaping, layout and scale