Planning application

Land At Foxbridge North Wanborough Road Swindon

Granted Swindon S/RES/25/0741 Reserved Matters

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Reserved Matters application for layout, landscaping, scale and appearance pursuant to Outline permission S/OUT/20/0533/JABU for erection of 220no. dwellings, local centre, access, landscaping, infrastructure and associated works.

As published by the council, reference S/RES/25/0741

Application record

Reference
S/RES/25/0741
Type
Reserved Matters
Status
Application Permitted
Decision
Granted As published: Reserved Matters Approved
Received
16 Jun 2025
Validated
16 Jun 2025
Decided
19 Dec 2025
Ward
Ridgeway
Parish
Wanborough
Decision by
Delegated Decision

Timeline

Dates from the published record

  1. 16 Jun 2025

    Received by Swindon

  2. 19 Dec 2025

    Decision issued: Reserved Matters Approved

  3. 16 Aug 2026

    Added to PlanIndex

Who's behind it

Company information only, from the register and Companies House

Pegasus Planning Group Ltd Agent, a planning consultancy registered in Cirencester

Active · incorporated 2010 · Cirencester

727 applications on PlanIndex · across 143 councils · 92% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Danescroft (PCDF IV Swindon) LLP Applicant, registered in London

Active · incorporated 2019 · London

2 applications on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

177 documents on file for this application

  • MIXED-USE BUILDING - GA ELEVATIONS Revised Drawing · 08 Dec 2025
  • DRAINAGE TECHNICAL NOTE Supporting Documents · 01 Dec 2025
  • ENVIRONMENTAL RISK ASSESSMENT Supporting Documents · 01 Dec 2025
  • EXCEEDANCE ROUTES PLAN Revised Drawing · 01 Dec 2025
  • HOUSE TYPE PLANNING DRAWINGS Supporting Documents · 27 Nov 2025
  • SITE LAYOUT Revised Drawing · 27 Nov 2025
  • HERITAGE MANAGEMENT PLAN UPDATES Correspondence · 17 Nov 2025
  • OPEN SPACE QUANTUM PLAN Revised Drawing · 17 Nov 2025
  • HERITAGE MANAGEMENT PLAN Supporting Documents · 17 Nov 2025
  • HIGHWAYS COMMENTS Consultee Comment · 13 Nov 2025
  • GENERAL ARRANGEMENT PLAN SHEET 1 Revised Drawing · 10 Nov 2025
  • EXTERNAL WORKS PLAN Revised Drawing · 10 Nov 2025
  • EXTERNAL WORKS PLAN Revised Drawing · 10 Nov 2025
  • GENERAL ARRANGEMENT PLAN SHEET 3 Revised Drawing · 10 Nov 2025
  • GENERAL ARRANGEMENT PLAN SHEET 4 Revised Drawing · 10 Nov 2025
  • DETAILED ON PLOT PLANTING PLAN SHEET 1 Revised Drawing · 10 Nov 2025
  • DETAILED ON PLOT PLANTING PLAN SHEET 2 Revised Drawing · 10 Nov 2025
  • DETAILED ON PLOT PLANTING PLAN SHEET 3 Revised Drawing · 10 Nov 2025
  • DETAILED ON PLOT PLANTING PLAN SHEET 4 Revised Drawing · 10 Nov 2025
  • DETAILED ON PLOT PLANTING PLAN SHEET 5 Revised Drawing · 10 Nov 2025
  • EXTERNAL WORKS PLAN Revised Drawing · 10 Nov 2025
  • GENERAL ARRANGEMENT PLAN SHEET 2 Revised Drawing · 10 Nov 2025
  • GENERAL ARRANGEMENT PLAN SHEET 5 Revised Drawing · 10 Nov 2025
  • GENERAL ARRANGEMENT PLAN SHEET 6 Revised Drawing · 10 Nov 2025
  • GENERAL ARRANGEMENT PLAN SHEET 7 Revised Drawing · 10 Nov 2025
  • GENERAL ARRANGEMENT PLAN SHEET 8 Revised Drawing · 10 Nov 2025
  • GENERAL ARRANGEMENT PLAN SHEET 9 Revised Drawing · 10 Nov 2025
  • HIGHWAYS COMMENTS Consultee Comment · 22 Oct 2025
  • APPLICANT RESPONSE TO ARCHAEOLOGY/ HISTORIC ENGLAND Supporting Documents · 21 Oct 2025
  • THAMES WATER Consultee Comment · 21 Oct 2025
  • LANDSCAPE ARCHITECT COMMENTS Consultee Comment · 21 Oct 2025
  • ENVIRONMENTAL HEALTH OFFICER COMMENTS Consultee Comment · 21 Oct 2025
  • FIRE TENDER VEHICLE TRACKING SHEET 3 OF 3 Revised Drawing · 14 Oct 2025
  • CAR VEHICLE TRACKING SHEET 3 OF 3 Revised Drawing · 14 Oct 2025
  • GENERAL ARRANGEMENT SHEET 1 OF 3 Revised Drawing · 14 Oct 2025
  • GENERAL ARRANGEMENT SHEET 3 OF 3 Revised Drawing · 14 Oct 2025
  • GENERAL ARRANGEMENT PLAN SHEET 1 OF 9 Revised Drawing · 14 Oct 2025
  • GENERAL ARRANGEMENT PLAN SHEET 5 OF 9 Revised Drawing · 14 Oct 2025
  • GENERAL ARRANGEMENT PLAN SHEET 6 OF 9 Revised Drawing · 14 Oct 2025
  • GENERAL ARRANGEMENT PLAN SHEET 7 OF 9 Revised Drawing · 14 Oct 2025
  • GENERAL ARRANGEMENT PLAN SHEET 8 OF 9 Revised Drawing · 14 Oct 2025
  • EXTERNAL WORKS PLAN Revised Drawing · 14 Oct 2025
  • MATERIALS PLAN Revised Drawing · 14 Oct 2025
  • REFUSE VEHICLE TRACKING SHEET 1 OF 3 Revised Drawing · 14 Oct 2025
  • REFUSE VEHICLE TRACKING SHEET 2 OF 3 Revised Drawing · 14 Oct 2025
  • REFUSE VEHICLE TRACKING SHEET 3 OF 3 Revised Drawing · 14 Oct 2025
  • GENERAL ARRANGEMENT PLAN SHEET 4 OF 9 Revised Drawing · 14 Oct 2025
  • EXTERNAL CYCLE STORE Revised Drawing · 14 Oct 2025
  • PARKING SCHEDULE Supporting Documents · 14 Oct 2025
  • SITE LAYOUT Revised Drawing · 14 Oct 2025
  • SITE LAYOUT Revised Drawing · 14 Oct 2025
  • SITE LAYOUT Revised Drawing · 14 Oct 2025
  • EXTERNAL WORKS PLAN Revised Drawing · 14 Oct 2025
  • EXTERNAL WORKS PLAN Revised Drawing · 14 Oct 2025
  • DRAINAGE SHEET 3 OF 3 Revised Drawing · 14 Oct 2025
  • DETAILED PUBLIC OPEN SPACE PLANTING PROPOSALS Revised Drawing · 14 Oct 2025
  • RESPONSE TO LANDSCAPE Correspondence · 14 Oct 2025
  • MATERIALS PLAN Revised Drawing · 14 Oct 2025
  • AFFORDABLE HOUSING PLAN Revised Drawing · 14 Oct 2025
  • AFFORDABLE HOUSING PLAN Revised Drawing · 14 Oct 2025
  • AFFORDABLE HOUSING PLAN Revised Drawing · 14 Oct 2025
  • EV CHARGING PLAN Revised Drawing · 14 Oct 2025
  • HOUSE TYPE BOOKLET 1 2.20-3.6 Supporting Documents · 14 Oct 2025
  • FIRE TENDER VEHICLE TRACKING SHEET 1 OF 3 Revised Drawing · 14 Oct 2025
  • FIRE TENDER VEHICLE TRACKING SHEET 2 OF 3 Revised Drawing · 14 Oct 2025
  • CAR VEHICLE TRACKING SHEET 1 OF 3 Revised Drawing · 14 Oct 2025
  • GENERAL ARRANGEMENT SHEET 2 OF 3 Revised Drawing · 14 Oct 2025
  • PROPOSED LEVELS SHEET 3 OF 3 Revised Drawing · 14 Oct 2025
  • DRAINAGE SHEET 1 OF 3 Revised Drawing · 14 Oct 2025
  • DRAINAGE SHEET 2 OF 3 Revised Drawing · 14 Oct 2025
  • GENERAL ARRANGEMENT PLAN SHEET 3 OF 9 Revised Drawing · 14 Oct 2025
  • RESUBMISSION COVERING LETTER Supporting Documents · 14 Oct 2025
  • MATERIALS PLAN Revised Drawing · 14 Oct 2025
  • EV CHARGING PLAN Revised Drawing · 14 Oct 2025
  • EV CHARGING PLAN Revised Drawing · 14 Oct 2025
  • MIXED-USE BUILDING - GA PLANS Revised Drawing · 14 Oct 2025
  • CAR VEHICLE TRACKING SHEET 2 OF 3 Revised Drawing · 14 Oct 2025
  • PROPOSED LEVELS SHEET 1 OF 3 Revised Drawing · 14 Oct 2025
  • PROPOSED LEVELS SHEET 2 OF 3 Revised Drawing · 14 Oct 2025
  • DETAILED ON PLOT PLANTING PROPOSALS Revised Drawing · 14 Oct 2025
  • GENERAL ARRANGEMENT PLAN SHEET 9 OF 9 Revised Drawing · 14 Oct 2025
  • GENERAL ARRANGEMENT PLAN SHEET 2 OF 9 Revised Drawing · 14 Oct 2025
  • HISTORIC ENGLAND Consultee Comment · 13 Oct 2025
  • DRAINAGE COMMENTS Consultee Comment · 09 Oct 2025
  • DRAINAGE COMMENTS Consultee Comment · 06 Oct 2025
  • SBC HOUSING Consultee Comment · 29 Sep 2025
  • WANBOROUGH PARISH COUNCIL COMMENTS Consultee Comment · 23 Sep 2025
  • LANDSCAPE OFFICER COMMENTS Consultee Comment · 22 Sep 2025
  • ECOLOGIST COMMENTS Consultee Comment · 29 Jul 2025
  • ARCHAEOLOGIST COMMENTS Consultee Comment · 16 Jul 2025
  • HIGHWAYS COMMENTS Consultee Comment · 14 Jul 2025
  • SITE NOTICE PHOTO Site Notice · 04 Jul 2025
  • SITE NOTICE PHOTO Site Notice · 04 Jul 2025
  • SITE NOTICE PHOTO Site Notice · 04 Jul 2025
  • SITE NOTICE PHOTO Site Notice · 04 Jul 2025
  • SITE NOTICE PHOTO Site Notice · 04 Jul 2025
  • SITE NOTICE PHOTO Site Notice · 04 Jul 2025
  • SITE NOTICE PHOTO Site Notice · 04 Jul 2025
  • SITE NOTICE PHOTO Site Notice · 04 Jul 2025
  • DORSET AND WILTSHIRE FIRE AND RESCUE Consultee Comment · 01 Jul 2025
  • PHASE 1 EV CHARGING PLAN Revised Drawing · 01 Jul 2025
  • PHASE 1 EV CHARGING PLAN Revised Drawing · 01 Jul 2025
  • PHASE 1 EV CHARGING PLAN Revised Drawing · 01 Jul 2025
  • DETAILED PLAY AREA PROPOSALS Drawing · 27 Jun 2025
  • PLAY AREA - DETAILED PUBLIC OPEN SPACE LANDSCAPE PROPOSALS Drawing · 27 Jun 2025
  • PLAY AREA -DETAILED ON PLOT PLANTING PLAN Drawing · 27 Jun 2025
  • PLAY AREA -DETAILED ON PLOT PLANTING PLAN Drawing · 27 Jun 2025
  • PLAY AREA -DETAILED ON PLOT PLANTING PLAN Drawing · 27 Jun 2025
  • PLAY AREA -DETAILED ON PLOT PLANTING PLAN Drawing · 27 Jun 2025
  • PLAY AREA -DETAILED ON PLOT PLANTING PLAN Drawing · 27 Jun 2025
  • PLAY AREA - DETAILED PUBLIC OPEN SPACE LANDSCAPEPROPOSALS Drawing · 27 Jun 2025
  • PLAY AREA - DETAILED PUBLIC OPEN SPACE LANDSCAPEPROPOSALS Drawing · 27 Jun 2025
  • PLAY AREA - DETAILED PUBLIC OPEN SPACE LANDSCAPEPROPOSALS Drawing · 27 Jun 2025
  • PLAY AREA - DETAILED PUBLIC OPEN SPACE LANDSCAPEPROPOSALS Drawing · 27 Jun 2025
  • PLAY AREA - DETAILED PUBLIC OPEN SPACE LANDSCAPEPROPOSALS Drawing · 27 Jun 2025
  • PLAY AREA - DETAILED PUBLIC OPEN SPACE LANDSCAPEPROPOSALS Drawing · 27 Jun 2025
  • PLAY AREA - DETAILED PUBLIC OPEN SPACE LANDSCAPEPROPOSALS Drawing · 27 Jun 2025
  • ADVERT LIST 4 JULY 2025 BackGround Papers · 27 Jun 2025
  • LANDSCAPE STRATEGY PLANS SHEET 2 OF 9 Drawing · 26 Jun 2025
  • LANDSCAPE STRATEGY PLANS SHEET 3 OF 9 Drawing · 26 Jun 2025
  • LANDSCAPE STRATEGY PLANS SHEET 4 OF 9 Drawing · 26 Jun 2025
  • LANDSCAPE STRATEGY PLANS SHEET 5 OF 9 Drawing · 26 Jun 2025
  • SBC PUBLIC HEALTH Consultee Comment · 26 Jun 2025
  • LANDSCAPE STRATEGY PLANS PLAN SHEET 1 OF 9 Drawing · 26 Jun 2025
  • LANDSCAPE STRATEGY PLANS SHEET 6 OF 9 Drawing · 26 Jun 2025
  • LANDSCAPE STRATEGY PLANS SHEET 7 OF 9 Drawing · 26 Jun 2025
  • LANDSCAPE STRATEGY PLANS SHEET 8 OF 9 Drawing · 26 Jun 2025
  • LANDSCAPE STRATEGY PLANS SHEET 9 OF 9 Drawing · 26 Jun 2025
  • ECOLOGY Consultee Comment · 26 Jun 2025
  • ACTIVE TRAVEL ENGLAND Consultee Comment · 26 Jun 2025
  • PUBLIC HEALTH Consultee Comment · 25 Jun 2025
  • NORTH WILTSHIRE SWIFTS BEAUMONT HAMEL, WYNDHAM ROAD SALISBURY Public Comment · 25 Jun 2025
  • PLANNING STATEMENT Supporting Documents · 18 Jun 2025
  • HERITAGE MANAGEMENT PLAN Supporting Documents · 18 Jun 2025
  • DESIGN AND ACCESS STATEMENT AND DESIGN CODE COMPLIANCE Supporting Documents · 18 Jun 2025
  • TREE RETENTION REMOVAL AND PROTECTION PLAN Drawing · 18 Jun 2025
  • PUBLIC ART STRATEGY Supporting Documents · 18 Jun 2025
  • SHADOW HABITATS REGULATIONS ASSESSMENT Supporting Documents · 18 Jun 2025
  • ECOLOGY TECHNICAL NOTE Supporting Documents · 18 Jun 2025
  • FLOOD RISK AND DRAINAGE ASSESSMENT Supporting Documents · 18 Jun 2025
  • PROPOSED LAYOUT PLAN Drawing · 13 Jun 2025
  • PROPOSED SITE LAYOUT Drawing · 13 Jun 2025
  • PROPOSED SITE LAYOUT Drawing · 13 Jun 2025
  • EXTERNAL WORKS PLAN Drawing · 13 Jun 2025
  • EXTERNAL WORKS PLAN Drawing · 13 Jun 2025
  • EXTERNAL WORKS PLAN Drawing · 13 Jun 2025
  • MATERIALS PLAN Drawing · 13 Jun 2025
  • MATERIALS PLAN Drawing · 13 Jun 2025
  • MATERIALS PLAN Drawing · 13 Jun 2025
  • AREAS FOR ADOPTION Drawing · 13 Jun 2025
  • AREAS FOR ADOPTION Drawing · 13 Jun 2025
  • AREAS FOR ADOPTION Drawing · 13 Jun 2025
  • AFFORDABLE HOUSING PLAN Drawing · 13 Jun 2025
  • AFFORDABLE HOUSING PLAN Drawing · 13 Jun 2025
  • AFFORDABLE HOUSING PLAN Drawing · 13 Jun 2025
  • APARTMENT TYPE PLANS Drawing · 13 Jun 2025
  • EXTERNAL CYCLE STORAGE Drawing · 13 Jun 2025
  • GARAGE PLANS Drawing · 13 Jun 2025
  • PARKING SCHEDULE Supporting Documents · 13 Jun 2025
  • LOCATION PLAN Drawing · 13 Jun 2025
  • SITE LOCATION PLAN Drawing · 13 Jun 2025
  • HOUSETYPE BOOKLET Drawing · 13 Jun 2025
  • HOUSETYPE BOOKLET Drawing · 13 Jun 2025
  • CAR VEHICLE TRACKING Drawing · 13 Jun 2025
  • GENERAL ARRANGEMENT SHEET 1 OF 3 Drawing · 13 Jun 2025
  • GENERAL ARRANGEMENT SHEET 2 OF 3 Drawing · 13 Jun 2025
  • GENERAL ARRANGEMENT SHEET 3 OF 3 Drawing · 13 Jun 2025
  • REFUSE VEHICLE TRACKING SHEET 1 OF 3 Drawing · 13 Jun 2025
  • FIRE TENDER VEHICULAR TRACKING SHEET 3 OF 3 Drawing · 13 Jun 2025
  • REFUSE VEHICLE TRACKING Drawing · 13 Jun 2025
  • FIRE TENDER VEHICULAR TRACKING SHEET 1 OF 3 Drawing · 13 Jun 2025
  • FIRE TENDER VEHICULAR TRACKING SHEET 2 OF 3 Drawing · 13 Jun 2025
  • FIRE TENDER VEHICLE TRACKING Drawing · 13 Jun 2025
  • CAR VEHICLE TRACKING Drawing · 13 Jun 2025
  • CAR VEHICLE TRACKING Drawing · 13 Jun 2025
  • COVERING LETTER Supporting Documents · 13 Jun 2025
  • REVIEW OF ACCESS TO PRIMARY SCHOOL Supporting Documents · 13 Jun 2025

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Swindon granted permission on 19 December 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About reserved matters applications

A reserved matters application fills in the detail held back from an earlier outline permission, judged against that permission rather than the principle of development. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Land At Foxbridge Village North Wanborough Road Swindon

    S/AMEND/25/1350 Submitted 21 Oct 2025 50 yards away

    Non-Material Amendment from previous application S/OUT/20/0533 relating to an adjustment of wording to Conditions 4, 6 and 20.

    Granted Amendments 3 docs
  • Land At Foxbridge Village North Wanborough Road Swindon

    S/COND/25/1219 Submitted 26 Sep 2025 100 yards away

    Discharge of Conditions (10) Wheelchair Accessible Housing (27) Street Lighting and Utility Provision (28) Refuse Storage and Collection from previous application S/OUT/20/0533 - Outline application for the erection of up to 220 no. dwellings, commercial facilities up to 300 sq.m. (Use Classes A1/ A2/A3/A4/A5/ B1 & D1) and 2.2 ha land for a primary school with associated parking, landscaping, drainage and heritage trail; access to Southern Connector Road not reserved.

    Granted Conditions 18 docs
    Major scheme
  • Phase 2 Land At Foxbridge Village North Wanborough Road Swindon SN4 0AB

    S/25/0992 Submitted 11 Aug 2025 100 yards away

    Erection of 71 no. dwellings, creation of access, landscaping, infrastructure and associated works.

    Granted Full applications 96 docs
    Major scheme
  • Land At Foxbridge Village North Wanborough Road Swindon

    S/COND/25/0451 Submitted 3 Apr 2025 150 yards away

    Discharge of Conditions (7) Phasing plan (9) Noise mitigation measure details (11) FLEAMP (38) Surface Water Drainage Scheme from previous application S/OUT/20/0533 - Outline application for the erection of up to 220 no. dwellings, commercial facilities up to 300 sq.m. (Use Classes A1/ A2/A3/A4/A5/ B1 & D1) and 2.2 ha land for a primary school with associated parking, landscaping, drainage and heritage trail; access to Southern Connector Road not reserved.

    Granted Conditions 19 docs
    Major scheme
  • 45 Kestrel Drive Covingham Swindon SN3 5DP

    S/HOU/21/1867 Submitted 27 Nov 2021 300 yards away

    Erection of single storey side and rear extensions.

    Granted Householder Extension 13 docs
    Small domestic
  • 43 Kestrel Drive Covingham Swindon SN3 5DP

    S/HOU/22/0280 Submitted 20 Feb 2022 300 yards away

    Erection of single storey front, side and rear extensions.

    Granted Householder Extension 10 docs
    Small domestic

In Swindon

  • S/RES/26/0873 Granted

    Little Rose Farm Lower Village Blunsdon SN26 7BJ

    Reserved matters application (following planning application S/OUT/23/1499) for details of appearance, landscaping and layout

    Received 10 Jul, published by the council 26 Jul 2026 Reserved matters
  • S/RES/25/1485 Granted

    Land To The North Of A420 South Marston Swindon

    Reserved matters application (following planning application S/OUT/13/1555) for details of the access, layout, scale, appearance and landscaping in relation to South Marston West electricity substation. The outline planning application was subject to and submitted with an Environmental Impact Assessment.

    Received 13 Nov, published by the council 26 Jul 2026 Reserved matters
  • S/RES/25/1581 Granted

    Land North Of A420 Known As South Marston And Rowborough Eastern Villages Swindon

    Construction of the Rowborough Primary Street and associated infrastructure (access, layout and scale) - Reserved Matters from previous outline permission S/OUT/13/1555.

    Received 3 Dec, published by the council 26 Jul 2026 Reserved matters
  • S/RES/26/0208 Granted

    Land At Langton Park Wroughton Swindon

    Partial Reserved Matters application (following Outline planning application S/OUT/23/0240) for the erection of 2 dwellings.

    Received 13 Feb, published by the council 26 Jul 2026 Reserved matters
  • S/RES/25/1389 Granted

    Parcels R1-R2 New Eastern Villages Swindon Wiltshire

    Reserved matters application (access, appearance, layout, scale and landscaping) for 122 dwellings and associated infrastructure -Reserved Matters from previous outline permission S/OUT/13/1555.

    Received 27 Oct, published by the council 26 Jul 2026 Reserved matters