Proposal
Details to satisfy Appendix 3, Schedule 7, Clause 1.1 'District Heat Network Strategy' in respect of Phase 2 of the Unilateral Undertaking associated with planning permission 23/AP/3474 (as amended by 24/AP/2526, 25/AP/1784 and 25/AP/2801) which gave consent for: "Minor Material Amendment of Condition 2 (Approved Plans) of planning permission 22/AP/1221 dated 27/10/2022 for hybrid application comprising a full planning application for Phase 1 comprising the demolition of Hillbeck Close, Ullswater House and garages at Manor Grove and the erection of four buildings at 2/3- storeys (D1 and D2), 5/9-storeys (C) and 7/13-storeys (G1) providing 167 homes (Class C3) with associated parking, public realm, open spaces, landscaping and ancillary infrastructure; and the refurbishment of properties at Manor Grove. Outline planning permission (all matters reserved except for access) for phases 2, 3 and 4 comprising the demolition of Bowness House, Pilgrims Way Primary School, Kentmere House and Heversham House and the erection of 12 buildings [...]".
As published by the council, reference 26/AP/3034
Application record
- Reference
- 26/AP/3034
- Status
- Under consideration/assessment
- Received
- 13 Oct 2026
- Validated
- 14 Oct 2026
Site history
Applications at this address on the Southwark register
This site has had 4 applications since 2025.
-
26/AP/2819 Decided
Phase 2 Tustin Estate Land Bounded By Manor Grove Ilderton Road Hillbeck Close Old Kent Road London Southwark SE1
Details to satisfy Appendix 3, Schedule 6, Clause 1.1 'Employment and Skills Methodology' in respect of Phase 2 of the Unilateral Undertaking associated with planning permission 23/AP/3474 (as amended by 24/AP/2526, 25/AP/1784 and 25/AP/2801), which gave consent for: "Minor Material Amendment of Condition 2 (Approved Plans) of planning permission 22/AP/1221 dated 27/10/2022 for hybrid application comprising a full planning application for Phase 1 comprising the demolition of Hillbeck Close, Ullswater House and garages at Manor Grove and the erection of four buildings at 2/3- storeys (D1 and D2), 5/9-storeys (C) and 7/13-storeys (G1) providing 167 homes (Class C3) with associated parking, public realm, open spaces, landscaping and ancillary infrastructure; and the refurbishment of properties at Manor Grove. Outline planning permission (all matters reserved except for access) for phases 2, 3 and 4 comprising the demolition of Bowness House, Pilgrims Way Primary School, Kentmere House and Heversham House and the erection of 12 buildings [...]".
-
26/AP/2731 Decided
Phase 2 Tustin Estate Land Bounded By Manor Grove Ilderton Road Hillbeck Close Old Kent Road London Southwark SE1
Details to satisfy Appendix 3, Schedule 7 Clause 2.1 'Energy Strategy' and Schedule 3A, Paragraph 1.2 'Amount of Phase 2 Carbon Green Fund Contribution' in respect of Phase 2 of the Unilateral Undertaking associated with planning permission 23/AP/3474 (as amended by 24/AP/2526, 25/AP/1784 and 25/AP/2801) which gave consent for: "Minor Material Amendment of Condition 2 (Approved Plans) of planning permission 22/AP/1221 dated 27/10/2022 for hybrid application comprising a full planning application for Phase 1 comprising the demolition of Hillbeck Close, Ullswater House and garages at Manor Grove and the erection of four buildings at 2/3- storeys (D1 and D2), 5/9-storeys (C) and 7/13-storeys (G1) providing 167 homes (Class C3) with associated parking, public realm, open spaces, landscaping and ancillary infrastructure; and the refurbishment of properties at Manor Grove. Outline planning permission (all matters reserved except for access) for phases 2, 3 and 4 comprising the demolition of Bowness House, Pilgrims Way Primary School, Kentmere House and Heversham House and the erection of 12 buildings [...]".
-
25/AP/2374 Awaiting decision
Phase 2 Tustin Estate Land Bounded By Manor Grove Ilderton Road Hillbeck Close Old Kent Road London Southwark SE1
Non-Material Amendment to planning permission ref. 24/AP/2446 dated 16/04/2025 for 'Approval of Reserved Matters Access, Appearance, Landscaping, Layout and Scale in relation to Phase 2 pursuant to hybrid planning permission ref. 23/AP/3474 for Minor Material Amendment of Condition 2 (Approved Plans) of planning permission 22/AP/1221 dated 27/10/2022 comprising a full planning application for Phase 1 comprising the demolition of Hillbeck Close, Ullswater House and garages at Manor Grove and the erection of four buildings at 2/3-storeys (D1 and D2), 5/9-storeys (C) and 7/13-storeys (G1) providing 167 homes (Class C3) with associated parking, public realm, open spaces, landscaping and ancillary infrastructure; and the refurbishment of properties at Manor Grove. Outline planning permission (all matters reserved except for access for phases 2, 3 and 4 comprising the demolition of Bowness House, Pilgrims Way Primary School, Kentmere House and Heversham House and the erection of 12 buildings (A, B, E1, E2, E3, E4, F1, F2, G2, H, J and Pilgrims Way Primary School) ranging in height from 2 to 21 storeys to provide up to 57,786 sqm of floorspace (GEA), comprising up to 523 affordable and market homes (Class C3), up to 3,452 sqm (GEA) of flexible commercial floorspace (Class E, F1 and sui generis) and up to 2,214 sqm (GEA) of educational floorspace (Class F1) including temporary space for the children's centre, with associated parking, public realm, open spaces (including MUGA), landscaping and ancillary infrastructure. total of 690 homes (Use Class C3) and 5,666 sqm (GEA) of non-residential floorspace (Use Classes E, F1 and sui generis)' The amendment seeks the following changes: - alterations to the external fenestration on facades of Blocks F1, F2 and G2 - small reduction in the heights of Blocks F1, F2 and G2 - re-provision of an internal substation within Block F1 from the existing building. - a reduction in lift overruns to all Blocks (F1, F2 and G2) with sta
Timeline
Dates from the published record
-
13 Oct 2026
Received by Southwark
-
14 Oct 2026
Validated
Checked as complete and ready for consideration.
-
14 Oct 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 9 December 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Southwark took a median of 52 days over the applications it decided in the last year.
Related applications
Cases linked to this one on the register
-
25/AP/2801 Decided
Tustin Estate Land Bounded By Manor Grove Ilderton Road Hillbeck Close , Old Kent Road London Southwark SE1
Non-material amendment to wording of Condition 33 and 34 of planning permission ref no. 23/AP/3474 , which gave consent for: "Minor Material Amendment of Condition 2 (Approved Plans) of planning permission 22/AP/1221 dated 27/10/2022 for hybrid application comprising a full planning application for Phase 1 comprising the demolition of Hillbeck Close, Ullswater House and garages at Manor Grove and the erection of four buildings at 2/3- storeys (D1 and D2), 5/9-storeys (C) and 7/13-storeys (G1) providing 167 homes (Class C3) with associated parking, public realm, open spaces, landscaping and ancillary infrastructure; and the refurbishment of properties at Manor Grove. [...]" The non-material amendment seeks to change the triggers of post completion report of Circular Economy Statement and post construction Whole Life Carbon Assessment in respect of Phase 1.
-
22/AP/1221 Granted
Tustin Estate Land Bounded By Manor Grove Ilderton Road Hillbeck Close Old Kent Road London Southwark SE1
Hybrid application comprising a full planning application for Phase 1 comprising the demolition of Hillbeck Close, Ullswater House and garages at Manor Grove and the erection of four buildings at 2/3-storeys (D1 and D2), 5/9-storeys (C) and 7/13-storeys (G1) providing 167 homes (Class C3) with associated parking, public realm, open spaces, landscaping and ancillary infrastructure; and the refurbishment of properties at Manor Grove.Outline planning permission (all matters reserved except for access) for phases 2, 3 and 4 comprising the demolition of Bowness House, Pilgrims Way Primary School, Kentmere House and Heversham House and the erection of 12 buildings (A, B, E1, E2, E3, E4, F1, F2, G2, H, J and Pilgrims Way Primary School) ranging in height from 2 to 21 storeys to provide up to 57,786 sqm of floorspace (GEA), comprising up to 523 affordable and market homes (Class C3), up to 3,452 sqm (GEA) of flexible commercial floorspace (Class E, F1 and sui generis) and up to 2,214 sqm (GEA) of educational floorspace (Class F1) including temporary space for the children's centre, with associated parking, public realm, open spaces (including MUGA), landscaping and ancillary infrastructure. Providing a total of 690 homes (Use Class C3) and 5,666 sqm (GEA) of non-residential floorspace (Use Classes E, F1 and sui generis).
What happens while it is decided
This application is with Southwark for determination, against a statutory target of eight weeks. Over the last year Southwark's median decision took 52 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Southwark's portal will say. Our guide explains the common types.