Planning application
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Listed building consent for the installation of entrance sign on the Southwark Street elevation
As published by the council, reference 26/AP/2512
Application record
- Reference
- 26/AP/2512
- Status
- Under consideration/assessment
- Received
- 21 Aug 2026
- Validated
- 21 Aug 2026
- Postcode
- SE1 1TY
Site history
Applications at this address on the Southwark register
This site has had 20 applications since 2025: 13 approved, 0 refused.
-
26/AP/2522 Awaiting decision
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Advertisement consent for 1x entrance sign
-
26/AP/1914 Awaiting decision
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Listed building consent application for the replacement gate to Park Street entrance to the Hop Exchange (rear), requiring works to the flank walls of nos.11 and 13 Park Street (revised).
-
26/AP/1646 Decided
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Details of condition 4 'Refurbished office suites (inc boardroom) details ' required for Listed bulidng consent 25/AP/2128 'Listed building consent for demolition of atrium rooflight and replacement with barrel-shaped rooflight; replacement of first floor rooflight; new accessible entrance on Southwark Street, new accessible lift car, and extension of lift core down to basement and overrun to the roof; new rooftop plant and associated screens; new substation in rear loading bay; refurbishment of office suites including redecoration, repairs and upgrades to internal finishes, upgrading MEP services, refurbishment of WCs, new accessible welfare facilities, and associated works.'
-
26/AP/1385 Awaiting decision
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Variation of a Condition 1 (approved plans) of the planning permission ref: 25/AP/2349 granted on 25.12.2025 for: (External alterations to the west wing (upper ground and first floors) in connection with a restaurant fit-out, including: new entrances and service entrance (to Southwark Street and Cart-way), replacement gates (to Park Street, the Cart-way, and bin store),installation of an outdoor dining veranda beneath Arch 15, and provision of associated mechanical plant and signage (Associated LBC: 25/AP/2351) to allow a revised design to the external dining verandah which in turn require changes to condition 4 (the cycle parking details) approved ref: 26/AP/0128 and condition 5 (hard and soft landscaping details) approved ref: 26/AP/0245 to accommodate the new verandah design.
-
26/AP/0686 Granted
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Details of condition 9 (materials) pursuant to listed building consent 25/AP/2128 (Listed building consent for demolition of atrium rooflight and replacement with barrel-shaped rooflight; replacement of first floor rooflight; new accessible entrance on Southwark Street, new accessible lift car, and extension of lift core down to basement and overrun to the roof; new rooftop plant and associated screens; new substation in rear loading bay; refurbishment of office suites including redecoration, repairs and upgrades to internal finishes, upgrading MEP services, refurbishment of WC?s, new accessible welfare facilities, and associated works.)
-
26/AP/0633 Granted
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Details of Condition 3 'Detailed drawings inc sections ' required by Listed Building Consent 25/AP/2128: 'Listed building consent for demolition of atrium rooflight and replacement with barrel-shaped rooflight; replacement of first floor rooflight; new accessible entrance on Southwark Street, new accessible lift car, and extension of lift core down to basement and overrun to the roof; new rooftop plant and associated screens; new substation in rear loading bay; refurbishment of office suites including redecoration, repairs and upgrades to internal finishes, upgrading MEP services, refurbishment of WC?s, new accessible welfare facilities, and associated works.'
-
26/AP/0280 Granted
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Minor material amendment of planning permission ref no. 25/AP/2351 (Listed building consent for Internal and external alterations to the west wing (upper ground and first floors) in connection with a restaurant fit-out, including: installation of internal and external plant; creation of minor openings in the floor slab for new staircases and DDA-compliant lifts; new entrances and service entrance (to Southwark Street and Cartway), replacement gates (to Park Street, the Cartway, and bin store), replacement of wall, floor, and ceiling finishes, general decoration works, and associated lighting and signage) Amendment sought: condition 1 (list of approved drawings) condition 5 (amend wording ) condition 6 (amend wording). (Revised description).
-
26/AP/0245 Granted
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Details of condition 5 'Landscaping' required by plannng permission ref no. 25/AP/2349: 'External alterations to the west wing (upper ground and first floors) in connection with a restaurant fit-out, including: new entrances and service entrance (to Southwark Street and Cart-way), replacement gates (to Park Street, the Cart-way, and bin store), installation of an outdoor dining veranda beneath Arch 15, and provision of associated mechanical plant and signage (Associated LBC: 25/AP/2351).'
-
26/AP/0228 Granted
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Details of condition 4 (Section 278 agreement) required by planning permission ref no. 25/AP/2127 for 'Demolition of atrium rooflight and replacment with barrel-shaped rooflight; replacement of first floor rooflight; new accessible entrance on Southwark Street, new accessible lift car, and extension of lift core down to basement and overrun to the roof; new rooftop plant and associated screens; new substation in rear loading bay; refurbishment of office suites including upgrading MEP services, refurbishment of WCs, new accessible welfare facilities, and associated works'.
-
26/AP/0167 Granted
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Details of condition 7 (Demonstrating the minimal extent of demolition necessary, detailed drawings (incl. sections) of the extent of floorslab to be demolished) required by listed building consent ref no. 25/AP/2128
Timeline
Dates from the published record
-
21 Aug 2026
Received by Southwark
-
28 Aug 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 16 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Southwark took a median of 52 days over the applications it decided in the last year.
What happens while it is decided
This application is with Southwark for determination, against a statutory target of eight weeks. Over the last year Southwark's median decision took 52 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Southwark's portal will say. Our guide explains the common types.
Nearby applications
Within 500 metres
-
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
95% historically approved · decision due ~22 Oct
Advertisement consent for 1x entrance sign
Awaiting decision 7 docs -
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
95% historically approved · decision due ~11 Sep
Listed building consent application for the replacement gate to Park Street entrance to the Hop Exchange (rear), requiring works to the flank walls of nos.11 and 13 Park Street (revised).
Awaiting decision -
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
95% historically approved · decision due ~4 Aug
Details of condition 4 'Refurbished office suites (inc boardroom) details ' required for Listed bulidng consent 25/AP/2128 'Listed building consent for demolition of atrium rooflight and replacement with barrel-shaped rooflight; replacement of first floor rooflight; new accessible entrance on Southwark Street, new accessible lift car, and extension of lift core down to basement and overrun to the roof; new rooftop plant and associated screens; new substation in rear loading bay; refurbishment of office suites including redecoration, repairs and upgrades to internal finishes, upgrading MEP services, refurbishment of WCs, new accessible welfare facilities, and associated works.'
Decided Extension Loft or dormer +1 -
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Minor material amendment of planning permission ref no. 25/AP/2351 (Listed building consent for Internal and external alterations to the west wing (upper ground and first floors) in connection with a restaurant fit-out, including: installation of internal and external plant; creation of minor openings in the floor slab for new staircases and DDA-compliant lifts; new entrances and service entrance (to Southwark Street and Cartway), replacement gates (to Park Street, the Cartway, and bin store), replacement of wall, floor, and ceiling finishes, general decoration works, and associated lighting and signage) Amendment sought: condition 1 (list of approved drawings) condition 5 (amend wording ) condition 6 (amend wording). (Revised description).
Granted Heritage and listed buildings 13 docs -
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Details of condition 5 'Detailed drawings (incl. sections) of the adaptation of a single small office suite ' required by Listed building consent ref no. 25/AP/2128
Granted Conditions 3 docs -
The Hop Exchange 24 Southwark Street London Southwark SE1 1TY
Details of Condition 3 'Detailed drawings inc sections ' required by Listed Building Consent 25/AP/2128: 'Listed building consent for demolition of atrium rooflight and replacement with barrel-shaped rooflight; replacement of first floor rooflight; new accessible entrance on Southwark Street, new accessible lift car, and extension of lift core down to basement and overrun to the roof; new rooftop plant and associated screens; new substation in rear loading bay; refurbishment of office suites including redecoration, repairs and upgrades to internal finishes, upgrading MEP services, refurbishment of WC?s, new accessible welfare facilities, and associated works.'
Granted Conditions Extension Loft or dormer +1 6 docs