Planning application

Substation Terminus Terrace Southampton

Granted Southampton 26/00146/PAEL Prior Approval for Electricity Works

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Prior Approval for the design and external appearance of proposed new substation buildings, as required under Class B, Part 15, Schedule 2 of the Town and Country Planning (General Permitted Development) (England) Order 2015 (the GPDO).

As published by the council, reference 26/00146/PAEL

Application record

Reference
26/00146/PAEL
Type
Prior Approval for Electricity Works
Status
Approved
Decision
No Objection
Received
11 Feb 2026
Validated
11 Feb 2026
Decided
13 Apr 2026
Ward
Bargate
Decision by
Delegated Decision

Site history

Applications at this address on the Southampton register

This site has had 2 applications since 2025: 2 approved, 0 refused.

  • 25/01390/FUL Granted

    Substation Terminus Terrace Southampton

    Change of use of hardstanding for use as a part of the existing site of Central Bridge electricity substation (Sui Generis Use)

    Decided 20 Jan 2026 Full applications

Timeline

Dates from the published record

  1. 11 Feb 2026

    Received by Southampton

  2. 13 Apr 2026

    Decision issued: No Objection

  3. 25 Jul 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

21 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Southampton granted permission on 13 April 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About prior approval applications

Prior approval applies where permitted development rights already grant the principle of the work, leaving the council only the specific matters the rules name, commonly within 56 days. More in our guide to planning application types.

In Southampton

  • 26/00674/PLDC Granted

    6 Hanover Buildings Southampton SO14 1JW

    Prior Approval sought for change of use of the upper floors from Commercial, Business and Service (Use Class E) to a 3 bed dwelling (Use Class C3)

    30 Jun 2026 Prior approval
  • 26/00568/PA56 Granted

    105 - 107 Bitterne Road West Southampton SO18 1AU

    Permitted Development Assessment - Prior Approval sought for a change of use of the ground floor from office to 2 x 2 bed flats (Use Class C3)

    18 May 2026 Prior approval
  • 26/00648/PAH Granted

    27 Exford Avenue Southampton SO18 5DP

    Erection of a single storey rear extension (Max Depth 4 m, Max Height 3.6 m, Eaves Height 2.25 m

    4 Jun 2026 Prior approval
  • 26/00620/PAH Granted

    372 Bitterne Road Southampton SO18 1DR

    Erection of a single storey rear extension (Max Depth 3.9 m, Max Height 4 m, Eaves Height 2.45 m)

    3 Jun 2026 Prior approval
  • 26/00651/PAH Granted

    15 Wilton Gardens Southampton SO15 7QS

    Erection of a single storey rear extension (Max Depth 4 m, Max Height 3.5 m, Eaves Height 3 m)

    4 Jun 2026 Prior approval