Planning application
Redshaw To Hagshaw Tee To Bankend Rig III Substation
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Erection of 132kV OHL approximately 36km in length and 1.72km of UGC running from Redshaws Substation to Bankend Rigg III Substation via the provision of a connection to Hagshaw Hill Repowering Phase 3 Substation. (Request for a Scoping opinion)
As published by the council, reference P/26/0912
Application record
- Reference
- P/26/0912
- Status
- Decided
- Decision
- Granted As published: Permitted
- Received
- 14 Jul 2026
- Validated
- 22 Jul 2026
- Decided
- 28 Aug 2026
- Ward
- 17 Hamilton North And East
- Decision by
- Delegated
Timeline
Dates from the published record
-
14 Jul 2026
Received by South Lanarkshire
-
22 Jul 2026
Validated
Checked as complete and ready for consideration.
-
28 Jul 2026
Added to PlanIndex
-
28 Aug 2026
Decision issued: Permitted
-
6 Sep 2026
Status changed to Awaiting decision
Previously Registered.
-
10 Sep 2026
Status changed to Decided
Previously Awaiting decision.
Documents
Plans, drawings, consultee responses and the officer's report
20 documents on file for this application
- Scoping response
- Consultation response - scottish water
- The proposed route
- Nature considerations and forestry constraints.
- Hydrology and peat constraints
- Hagshaw affected forestry sheet 1.
- Hagshaw affected forestry sheet 2
- Form of the proposed overhead line
- Principal high level constraints
- Wind farms and wind turbines
- Landscape and visual study area
- Landscape designations and key routes
- Topography
- Zone of theoretical visibility and proposed viewpoints overview
- Zone of theoretical visibility and proposed viewpoints sheet 1
- Zone of theoretical visibility and proposed viewpoints sheet 2
- Zone of theoretical visibility and proposed viewpoints sheet 3
- Zone of theoretical visibility and proposed viewpoints sheet 4
- Archaeology and cultural heritage constraints
- Routeing study area
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
South Lanarkshire granted permission on 28 August 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on South Lanarkshire's portal will say. Our guide explains the common types.