Skip to content
PlanIndex Get alerts
Menu

Planning application

Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

Decided South Gloucestershire DCO/32/52B/PRE DCO Major Requirements PreApp

Decided. The decision notice on the council portal carries the outcome in full, including any conditions.

Proposal

Pre-application submission seeking advice on Requirement 5(2)(b) (Biodiversity Mitigation Strategy) addendum for Stage 3.2 of the authorised development

As published by the council, reference DCO/32/52B/PRE

Application record

Reference
DCO/32/52B/PRE
Type
DCO Major Requirements PreApp
Status
Awaiting decision
Decision
DCO DoR PreApplication Decision
Received
19 Aug 2021
Validated
19 Aug 2021
Decided
16 Sep 2021

Site history

Applications at this address on the South Gloucestershire register

This site has had 17 applications since 2021: 7 approved, 0 refused.

  • DCO/10/01/R15 Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Hinkley Point C Connection Project - Requirement 15(1) Reinstatement Schemes

    Decided 21 Aug 2026 Full applications
  • DCO/10.1/15 Awaiting decision

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal Submission to discharge of Requirement 15 (Reinstatement Scheme) for Stage 10.1 of the authorised development

    Submitted 19 Dec 2025 Full applications
  • DCO/10.1/10 Awaiting decision

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Submitted 28 Apr 2023 Full applications
  • DCO/10.1/61F Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal Submission to discharge of Requirement 6(1)(f) Emergency Response Plan for Flood Events for Stage 10.1 of the authorised development

    Decided 21 Apr 2023 Full applications
  • DCO/10/52B/C Granted

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Formal Submission to discharge of Requirement 5(2)(b) Biodiversity Mitigation Strategy for Stage 10.1 of the authorised development

    Decided 14 Apr 2025 Full applications
  • DCO/32/25/PRE Decided

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    HCCP Stage 3.2 Pre-application advice on Requirement 25 (Highway Signage Plans)

    Decided 30 Sep 2021
  • Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Pre-application request for Requirements 6(1)(i) and 12 (Tree and Hedgerow Protection Strategy) for Stage 3.2 of the authorised development.

    Decided 23 Sep 2021 Full applications
  • DCO/32/61G/PRE Decided

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    HCCP Stage 3.2 Pre-application advice on Requirement 6(1)(G) - Site Waste Management Plan

    Decided 2 Sep 2021 Full applications
  • DCO/32/16/PRE Decided

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Pre-application submission seeking advice on Requirement 16 (Fencing and other means of enclosure) for Stage 3.2 of the authorised development

    Decided 19 Aug 2021
  • DCO/32/61F/PRE Decided

    Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.

    Pre-application submission seeking advice on Requirement 6(1)(f) (Emergency Response Plan) for Stage 3.2 of the authorised development

    Decided 24 Aug 2021 Full applications

Timeline

Dates from the published record

  1. 19 Aug 2021

    Received by South Gloucestershire

  2. 16 Sep 2021

    Decision issued: DCO DoR PreApplication Decision

  3. 9 Sep 2026

    Added to PlanIndex

After the decision

South Gloucestershire has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

In South Gloucestershire

  • P25/01990/F Granted

    286 And Land At 286 Badminton Road Coalpit Heath South Gloucestershire BS36 2NN

    Partial demolition of existing dwelling and erection of 1no. new self-build dwelling with access, parking provision and other associated works.

    Received 18 Aug, published by the council 1 Aug 2026 Full applications
  • P26/01768/F Granted

    Lyegrove Farm Lyegrove Badminton South Gloucestershire GL9 1HA

    Erection of extension to existing agricultural building.

    Received 6 Aug, published by the council 15 Aug 2026 Full applications
  • P26/00514/F Refused

    Land At 151 New Cheltenham Road Kingswood South Gloucestershire BS15 4RR

    Erection of 2 no. new dwellings with parking and associated works.

    Received 3 Mar, published by the council 26 Jul 2026 Full applications
  • P26/01534/F Granted

    Tesco Metro 58 Broad Street Staple Hill South Gloucestershire BS16 5NP

    Erection of 2.9m high gate (Retrospective).

    Received 7 Jul, published by the council 26 Jul 2026 Full applications
  • P26/02237/F Awaiting decision

    Gatehouse Building At Tortworth Court Four Pillars Hotel Estate Office Lane Tortworth South Gloucestershire GL12 8HH

    Erection of single storey front extension to form lobby area with external access ramp, erection of raised terrace to side elevation.

    Received 2 Oct, published by the council 11 Oct 2026 Full applications