Planning application

Easter Score Holm Scalloway Shetland

Granted Shetland Islands 2026/001/MAR Marine Fish Farm

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Modification of an existing salmon farm by removing existing black-coloured feed pipes and replacing with white-coloured feed pipes

As published by the council, reference 2026/001/MAR

Application record

Reference
2026/001/MAR
Type
Marine Fish Farm
Status
Decided
Decision
Granted As published: Grant subject to conditions
Received
22 Dec 2025
Validated
14 Jan 2026
Decided
5 Mar 2026
Parish
SCALLOWAY
Decision by
Delegated Decision

Timeline

Dates from the published record

  1. 22 Dec 2025

    Received by Shetland Islands

  2. 14 Jan 2026

    Validated

    Checked as complete and ready for consideration.

  3. 5 Mar 2026

    Decision issued: Grant subject to conditions

  4. 28 Jul 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

18 documents on file for this application

  • ADMIRALTY CHART Approved Plans · 05 Mar 2026
  • COORDINATES Approved Plans · 05 Mar 2026
  • SITE PLAN Approved Plans · 05 Mar 2026
  • SITE PLAN Approved Plans · 05 Mar 2026
  • LOCATION PLAN Approved Plans · 05 Mar 2026
  • DECISION NOTICE Decision · 05 Mar 2026
  • DELEGATED REPORT OF HANDLING Delegated Report of Handling · 05 Mar 2026
  • SCREENING OPINION Other · 05 Mar 2026
  • CONSULTATION RESPONSE - COMMUNITY COUNCIL Consultee Comment · 13 Feb 2026
  • ADVERT Advert · 23 Jan 2026
  • CONSULTATION RESPONSE -MARINE DIRECTORATE SCOTTISH GOVERNMENT Consultee Comment · 22 Jan 2026
  • CONSULTATION RESPONSE - NLB Consultee Comment · 16 Jan 2026
  • CONSULTATION RESPONSE - NATURESCOT Consultee Comment · 16 Jan 2026
  • APPLICATION FORM Application Form · 14 Jan 2026
  • APPLICATION FORM Correspondence · 14 Jan 2026
  • EXISTING BARGE ILLUSTRATION Drawing · 22 Dec 2025
  • EXISTING PHOTO Photo · 22 Dec 2025
  • SUPPORTING STATEMENT Supporting Documents · 22 Dec 2025

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Shetland Islands granted permission on 5 March 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Shetland Islands's portal will say. Our guide explains the common types.

Nearby applications

Within 500 metres

  • Easter Score Holm, Scalloway Islands

    2026/007/MPN Submitted 27 Mar 2026 19m away

    Application for prior notification under class 21B of the Town and Country Planning (General Permitted Development) (Scotland) Order 1992 (as amended): To replace an existing feed barge with a feed barge of a different size and colour at the same location within the existing site area

    Granted Prior approval 12 docs